Post Job Free
Sign in

Project Engineer and Planner

Location:
Kuala Lumpur, Federal Territory of Kuala Lumpur, Malaysia
Posted:
December 28, 2014

Contact this candidate

Resume:

Curriculum Vitae

Name : MOHD AMINULLAH BIN MOHD KHALID

Address (1) : NO. 4, PT 10992, TAMAN MESRA,

KAMPUNG BALAI BESAR, 23000,

DUNGUN, TERENGGANU

Address (2) : NO. 4, JALAN SERI PUTRA 3/4,

BANDAR SERI PUTRA, BANGI,

43000, KAJANG, SELANGOR

H/P No : +601*-******* / +601*-*******

E-mail : *********@*****.***

LinkedIn : https://www.linkedin.com/pub/mohd-aminullah-mohd-khalid/a2/365/738

PERSONAL DETAIL

Age : 31 Health : Excellent

Date of Birth : 29 January 1983 Marital status : Married

Gender : Male Weight : 63kg

Nationality : Malaysian Height : 167cm

CAREER OBJECTIVE

To find a challenging position to meet my competencies, capabilities, skills, education and

experience especially in project management area

PROFESSIONAL EXPERIENCES

Job Title: Project Engineer and Planner

Year: January 2007 – today

Company: Technical Services Department (TSD) from 2011 until today,

Maintenance Department (2007 – 2011), Gas Processing & Utilities Division, PETRONAS

Gas Berhad (PGB), Terengganu

Job Responsibilities at TSD:

- Plan, establish, implement, evaluate & coordinate the project initiation activities such as

the project execution plan (PEP) and project budget as well as project tendering plan or

contracting strategy and to facilitate project approval by relevant Approving Authority (AA).

- Supervise and coordinate project engineering activities with the Engineering Section &

Users (Operation and Maintenance) such as Conceptual Design and Basic Engineering

Design activities through data compilation, studies conducted, evaluates and exercises

considerable judgment to solve project engineering problems under variable conditions in

order to ensure engineering control system are in place and in accordance to the project

execution plan.

- Assess, evaluate and ensure the approved engineering deliverables e.g study, drawings etc.

are produced timely for smooth transfer to the relevant parties through expediting,

meeting, reviewing, discussion, circulate to other relevant personnel for further input in

order to ensure compliance with the construction and project execution plan & timeline.

- Evaluate and analyze the pre-qualification of potential bidders & project cost estimates and

implementation of tendering process through consideration in terms of nature of work,

technological aspects, value of tender, availability of licenses/ registered company,

commercial value etc in order to ensure proper selection of suitable contractor.

- Plan and inspect the procured material and assess the performance of service providers

through inspection and test activity and the result shall be recorded on appropriate

inspection form. Verify acceptance or non-acceptance of the deliverables to ensure

compliance to the contract and project requirements

- Coordinate and liaise with client/ users/ area owner at all phases of the in order to ensure

issues are resolved accordingly as well as meeting the client/ user (PGB management,

operation etc.) requirements for the smooth project execution and implementation.

- Evaluate, supervise (if required by the client/ users) & coordinate the site activities

performance and progress as well as the crew during all phases of the project in order to

meet the quality, Health Safety & Environment (HSE), schedule & budget requirements

- Review and recommend the construction and commissioning plans, procedures, manuals

and schedule through expediting, meeting, reviewing, discussion, circulate to other

relevant personnel for further input, perform joint site visit with Contractor for better

project progress judgment and revision, notify Project Manager on any critical issues

encountered in order to ensure the construction and commissioning activities are

performed as per schedule and in compliance to the contract requirement

- Update Project Manager on regularly basis on the status of project deliverables, project

manpower and project execution plan through weekly / monthly meeting to ensure timely

resolve of related issues and project progression and updates

- Plan and coordinate the project risk assessment, project independent review, team

building, and lesson learnt session through preparing the necessary data (design

parameters, operating conditions, etc), Process & Instrument Diagram (P&ID) and package

it into suitable format for the presentation during the review session to ensure compliance

to the Quality Assurance practices and quality project deliverables

Summarize Job Responsibilities at Maintenance Dept:

- Plan, coordinate and execute all maintenance and operational aspects of plant equipment

to support activities for Operational Process of GPP-B Complex within approved budget and

resources through Maintenance Best Practices, in compliance with safety, quality and

statutory requirements to achieve targeted plant availability and reliability for continuous

plant operation

- Budget focal person for Maintenance Department

Projects Handled:

Among projects' assigned as Project Engineer at TSD (most are MOC projects):

2013 - 2014: Gas Processing Plant B (GPPB) LV Motor Protection Relay Upgrade (RM 7.4 mil)

2011 - 2012: UPS upgrading at Gas Processing Plant A (GPPA) and Export Terminal (RM 2 mil)

2012 - 2014: Arc Protection System installation at GPPB 6.6kV feeders (RM 1.5 mil)

2012 - 2014: LV switchboards upgrading at GPPA (RM 1 mil)

2012 - 2013: Cathodic Protection System upgrading at GPPA (RM 1 mil)

2013 - 2014: Main Control Room upgrading at Export Terminal (ET) (RM 2 mil)

2013 - 2014: HVAC upgrading at Analyzer Houses, FAR and Substations at GPPB (RM 9 mil)

Mega Project's attachment as Site Coordinator:

2012 - 2013: Engineering, Procurement, Construction & Commissioning (EPCC) of Gas Processing

Plant A (GPPA) & Gas Processing Plant B (GPPB) Flare Gas Recovery Units project (RM 135 mil)

Among projects' assigned while being a Planner at Maintenance Department, Gas Processing Plant

B, Paka, Terengganu:

2010: Lead GPP6 Flare Stack (110m height) refurbishment project (RM 6 mil)

2009: Lead Vessel V5-0805A refurbishment project (RM 285k)

Job Title: Junior Electrical Engineer

Year: February 2006 – December 2006

Company: Export Terminal (ET), Gas Processing & Utilities Division, PETRONAS Gas Berhad (PGB)

Job Responsibilities:

- As a Junior Electrical Engineer at Export Terminal (ET), Kemaman, Terengganu.

- Attached to GPP3 Turnaround for 1.5 months as Packed Vessel CF Renewal Project

Engineer (July – Aug 2006)

- Other project’s assigned while at ET: Cathodic Protection system upgrading

Job Title: Industrial Internship

Year: June 2004 – January 2005

Company: PETRONAS Research & Scientific Services (PRSS) Sdn Bhd, Bangi, Selangor

Job Responsibilities:

- 8 months attachment to Natural Gas Vehicle (NGV) Department of Petroleum Product

Group (PPG) during 4th year study at UTP.

- Projects involved: Vehicle Refueling Appliances (VRA) and UTP 2T Mixer.

- Tasks assigned: Assisted the Engineer to design Printed Circuit Board (PCB) for

microcontroller of both projects, calibrate pressure sensors used in VRA projects and

program the PIC microcontrollers using PIC Basic Pro programming language

AWARD & RECOGNITION

Gold Medal for Best Performance of Maintenance Management for GPPB in 2009, at PETRONAS

Level

Bronze Medal for Best Performance of Maintenance Management for GPPB in 2008, at PETRONAS

Level

EDUCATION BACKGROUND

Level : Master’s Degree

Field of Study : MSc of Project Management

Institution : Universiti Malaya (UM), Kuala Lumpur

Duration : 1.5 Years (September 2013 - January 2015)

Level : Bachelor’s Degree

Field of Study : BSc of Electrical & Electronics Engineering

Institution : University Technology of PETRONAS (UTP), Tronoh, Perak

Duration : 5 years (January 2001 – December 2005)

Level : Secondary Education

Duration : 5 years (1996 - 2000)

Institution : Sekolah Menengah Sains Tengku Abdullah, Raub, Pahang

NOTICE PERIOD

3 months’ notice (negotiable for earlier notice period)

OTHER SKILLS

Skills Proficiency Level

Computer Skills (i.e MS PowerPoint, MS Excel) Skill

MS Project Intermediate

Primavera P6 Beginner

SAP Plant Maintenance Module Advance

LANGUAGES PROFICIENCY

Languages Proficiency:

Spoken: Bahasa Malaysia, English Language

Written: Bahasa Malaysia, English Language

SPORT ACTIVITIES

BASKETBALL:

Represent Gas Business Team from 2007 – 2014 for PETRONAS East Coast Games. Achievement:

2012: 2nd Runners Up

2013: 1st Runners Up

2014: Champion

BOWLING:

2014: 1st Runners Up for Double Event (PMD Departmental Bowling Tournament

REFERENCES

(Former Manager) (Former Manager)

M Husni B Wahid, Marizam B Ramli,

Manager, Project Manager,

Plant Revamp & Rejuvenation 4 (PRR4), Project Management Section,

Gas Processing & Utilities (GPU) Division, Technical Services Department (TSD),

PETRONAS Gas Berhad, Gas Processing & Utilities (GPU) Division,

Kertih, Kemaman, Terengganu PETRONAS Gas Berhad,

Email: ******@********.***.** Kertih, Kemaman, Terengganu