* + years experience in the Construction Industry in Power with
Bechtel Corporation and Capital Improvement Projects with the
City of Fort Worth. I am passionate about safety, quality, schedule
adherence and customer satisfaction with a record of improving
efficiency, resourcefulness, productivity, and profitability through
automation and process improvements. My outstanding
interpersonal, motivational, cross discipline coordination and
presentation skills permit me to be extremely flexible and easily
adaptable to a multitude of challenging assignments.
Education
2002 – 2007 University of Arkansas at Little Rock Little Rock, Arkansas
Bachelor of Science Degree in Construction Management
2002 – 2006 University of Arkansas at Little Rock Little Rock, Arkansas
Associate of Science Degree in Electronics and Computer Engineering Technology
2005 – 2006 City of Fort Worth Forth Worth, Texas
Co operative (Rotation in Survey, Soils/Concrete Lab, Field Inspection, As built, Wastewater treatment plant: Instrument &
Controls (I&C) and Mechanical (plant component) groups)
QUALIFICATIONS/Certifications/Professional development/memberships
Society of Piping and Engineering Design (SPED) Level 1
PPD Certification (in progress)
Primevera P6 (Oracle University)
Project Management Fundamentals (Second Edition) New
Horizons
Revit Architecture Fundamentals (LEDET Training)
LEDET
Mechanical/Piping Workshop Bechtel University
Maxi bolt, Hilti Anchors, GSSI Scanner Trained
Proficient in Maximo, Passport & NAMs
CANstruction Lead at Watt’s Bar Project 2013 – “Winner of
Competition”
Professional experience
03/2013 – Present Bechtel Construction Watts Bar Unit 2 Completion TVA
Mechanical Field Engineer (FE) for installation and inspection of ASME (Section III and Section XI) and Non ASME
piping, rotating equipment alignment, pipe supports, instrumentation and controls systems in the completion of Watts Bar
Unit 2 for TVA in Spring City, TN.
Selected by Senior Management to perform “constructability walkdowns” to provide constructability and correctness
•
completeness on new piping work orders released by the Planning group.
Member of the “Project Mechanical Readiness Team” performing initial & final constructability walkdown of (legacy and new)
•
T 4 work order packages with craft to identify issues (predecessors, successors, material restraints, specialty tools, proposed
schedule durations) and provide solutions. Reviewed work orders having low float, schedule priority and systems/project system
waterfall work orders. Worked closely with schedulers to verify and adjust schedule work order activity logic ties.
Managed work orders utilizing client’s MAXIMO and BSL system. Coordination with Design engineering through the engineering
•
change documentation process, worked with Authorized Nuclear Inspectors for material separation and work order hold points,
Quality Control, Superintendents, Foremen and craft to support/manage field work activities by performing critical technical
inspections of on going work, tracked man hours completed throughout the duration of work scope activities and performed work
order closure activities.
SWORD – System Work Order Department – Driven by project system priorities, performed scope estimation on existing and new
•
work orders and performed material take offs in an effort to re align the overall project schedule.
Gap Analysis Group – worked with the gap group to ensure that all Engineering Scope Packages drawings are captured in a work
•
order by utilizing MAXIMO & BSL in the initial planning review.
Materials Management Group – Maintained the project material tracker for all materials ordered for work orders, and processed
•
transmittals for material transfers.
02/2009 – 02/2013 Bechtel Construction Turkey Point EPU Project
Mechanical/Piping Field Engineer (FE) for installation and inspection of ASME B31.1 piping, pipe supports, heat
exchangers, instrumentation and controls systems in the completion of FPL/NextEra Turkey Point EPU Project “2013
Nuclear Project of the Year”.
Lead Field Engineer in charge of assisting field procurement in the inspection, resolution of material issues on mechanical and
•
civil materials (worked closely with suppliers to resolve design issues)
Engineering Change (EC) Lead Field Engineer over the Control Room Emergency Ventilation System (CREVS) & Spent Fuel Pool
•
(SFP) Projects scopes
Selected by Senior Management to support online pre outage hanger installation (Maxi/Hilti anchor bolts, steel fabrication and
•
component installation) for all hangers (200+) in the 4R27 outage scope.
Night shift Field Engineer for the Moisture Separator Reheater (MSR) team.
•
Provided engineering assistance to Superintendents during pre planning and implementation stages of the project
•
Planned first work package on the EPU Project for the Leading Edge Flow Meter (LEFM), worked closely with the client to
•
troubleshoot and set the expectations for the packages to follow.
Implemented initial Lessons Learned system/platform at Turkey Point EPU Project
•
Worked closely with supervision and project controls to prepare and update short term schedules.
•
Conducted field quantity take offs from “Issued For Construction” drawings
•
Coordinated Pre Outage Equipment Testing with on site group Ames and FPL on components that were received at the
•
warehouse to adhere with project schedule needs.
Evaluated engineering design to resolve issues with engineering and/or fabricator/vendor.
•
Prepared walk down packages prior to Bechtel plant outages for the implementation of design in containment areas.
•
Design/Construction Team member which consisted of the station representatives from Maintenance, Project Manager for Scope,
•
Responsible Mechanical Engineer, and Responsible Civil Engineer for the TPCW – (Turbine Plant Cooling Water System) for
constructability and design input to the vendor based on plant maintenance activities and available space for implementation.
Performed Initial Assessments and Constructability reviews with the client, engineers, Vendors and Bechtel supervision on
•
proposed Engineering Change Packages/Plant Change Modifications.
Worked closely with Bechtel procurement, Expeditors and the Client procurement group to purchase materials and perform
•
technical bid evaluations to ensure delivery dates supported the project’s schedule
Participated in P&ID System walkdowns with the client, system engineers and design engineers for final system turnover;
•
identified open items and discrepancies, monitored completion of open items on the punch list and identified systems/components
to be turned over on P&IDs.
Performed In Service Leak Check inspections on the stations Post Maintenance Testing documentation to ensure systems meet
•
design requirements
Developed a Project Management tracking tool using Microsoft Excel called “Scope Management Spreadsheet” that was utilized
•
on the CREVS (Control Room Emergency Ventilation System) and SFP (Spent Fuel Pool System) projects this concept was
implemented and used by the Field Engineering Dept.
Monitored the Client’s T Week schedule to ensure that the associated work packages and material aligned with the work schedule
•
Prepared and Finalized the Service Requisition for the potential “Sub Contractor” solicited for the “Contingency Air Cooled
•
Chiller” in support of the Spent Fuel Pool project. Point of contact and worked closely with the Contracts, Engineering and all
groups supporting this effort
Created Project Daily Reports to report status to management
•
Partnered with the Commercial Grade Dedication Engineers at the FPL’s Corporate Procurement Office to upgrade Augmented
•
Quality materials to Safety Related material
Quality Role – Served as the Work Package Close out Coordinator leading a team of 3 for the 3R26 Outage, reviewed all work
•
packages to process for Turnover and worked with the Welding Department to close out weld records.
Partnered with the Contract Department for the Control Room Emergency Ventilation – Filtration Unit (PMT Contract) on duct
•
work required for the modification; contracts affecting work, to request information and schedule and communicate design issues
Performed pre job briefings highlighting safety/hazard concerns, managed work order execution, Liaison with Design
•
Engineering, Quality Control, Superintendents, Foremen and craft to support field work activities by performing inspections of on
going work and close out phase of the project work packages
05/2008 – 01/2009 Bechtel Construction Fossil Division Sandow Unit 5
Piping Field Engineer (FE) for installation and inspection of ASME B31.1 piping and pipe supports in the completion of
Sandow Unit 5, Rockdale Texas.
Worked with TeamWorks (equipment and material tracking system) to verify accuracy of data from engineering, also worked with
•
other Bechtel systems Bechtel Procurement System (BPS), InfoWorks & 3DM
Worked with procurement to prioritize, expedite and control material deliveries to the site
•
Prepared Field Material Requisitions for permanent and temporary materials
•
Executed field quantity take offs for construction drawings
•
Provided technical assistance to craft
•
Performed inspections and documentation on assigned systems in working progress on a continuing basis to ensure quality and
•
conformance to project specifications are met and also created punchlist items to track working systems utilizing Punch Item in
TeamWorks.
Assisted in the execution of piping work packaging program
•
Participated in P&ID System walkdowns with the client and start up engineers
•
Attended punchlist and safety meetings as the piping rep.
•
Prepared and organized reports for Construction to Startup system turnover
•
Gained experience/understanding with Bechtel Program 3DM (shadowed Plant Design Engineer while visited site)
•
Coordinated with design engineering and vendors to resolve issues utilizing (RFI’s, FCR’s, Backcharges etc.)
•
Supported boiler Hydro test team for monitoring pump pressure gauge
•
Responsible Field Engineer for the Feedwater System and Bag House
•