Post Job Free
Sign in

Engineer Manager

Location:
Beeville, TX, 78102
Salary:
200000
Posted:
August 11, 2014

Contact this candidate

Resume:

Lance Baylor

*** ***** **.

Odem,Tx USA

D.O.B 18DEC1968

+1-979-***-**** cell

Email: ***********@*****.***

Summary of Qualifications: Completions &Commissioning Lead/Manager: Twenty

plus years plus experience in regards to completions, pre-commissioning,

commissioning tasks on various Power, Industrial Gas, Petro-Chemical,

Offshore Oil& Gas projects. Managing the multi-discipline systems

completion and commissioning activities as followed:

Duties & Responsibilities

-Implement system completion and turnover process methodology throughout

project including risk assessments: Working knowledge with Opercomm Icap

and EM PEGASUS System completions management databases.

Provide field support to insure owner is involved in the process.

Plan and coordinate resources to complete commissioning activities.

Lead pre-commissioning, commissioning and completions of new projects.

Support construction planning to allow quick and efficient commissioning of

equipment and systems.

Create functional performance tests and orchestrate the tests with

contractors and owners.

Maintain commissioning documentation, packaging and completions data base

for final hand over of project.

Direct and manage field personnel that are assigned to projects.

Setting up pre-commissioning and commissioning activities into a job

sequence to monitor and following:

*Complete system walk downs and punch lists of plant leading to mechanical,

electrical and instrumentation completion.

*Coordinate and supervise on-site visits from process equipment vendors.

*Troubleshoot design and software issues during commissioning, contacting

appropriate resource to correct issue.

*Conduct qualification testing and operation of equipment, i.e. Compression

system, backup system, etc.

*Conduct review of critical systems.

*Estimate commissioning cost based on components to be commissioned.

Work History:

2/10/2014 to present: Completions/Commissioning Manager, CORE Engineering

Corpus Christi TX. Lead all systems completions and pre-commissioning

activities for Texstar 63,000 bpd NGL fraction unit. Also managing multi

discipline mechanical completion along with functional testing and all pre-

commissioning and commissioning activities.

6/21/2012 to 12/17/2013: Completions Manager, DeltaAfrik Nigeria, Lead

all completions and commissioning scope for flare reduction project that

consisted of Offshore Gas Compressor/booster station, Fuel Gas treating&

gas dehydration unit along with revamping Oil terminal flare and Produced

Water Project for Mobil Producing Nigeria EPCM-1 projects.

1/3/2012 to 6/15/2012: Commissioning Manager, Enterprise NGL Eagle Ford

Gas Plant, Lead all commissioning scope for a 600MMcf/d cryogenic NGL gas

processing trains.. Managing sub-contractor to support Pre-commissioning

activities, system completions, operations startup of train 1.

6/1/11 to 12/15/2011: Completions Manager, Jacobs Field Services, Port

Arthur TX Movita CEP Managed all commissioning aspects for the new Cat Feed

Hydrotreater Unit, PS4( 400MW) utility unit consisting of 4 Nuovo Pignone

GTG/HRSG and associated demineralized water and instrument air areas.

Directly managed over 100 personal of the Pre-commissioning sub-contractor

staff, along with commissioning in house team directly working with Motiva

Operation to support RFSU.

4/19/10 to 4/15/11: Commissioning Team Leader, Sonangolpp Angola, Africa.

Lead Sonangolpp performance testing( Block 4) activities for

120kBPD,260kBPD water with gas re-injection FPSO commissioning in Block

4.However main project(Block 2) I Lead Sonangolpp commissioning activities

for 308MMSCFD Offshore Gas Injection Platform. Main focus was coordinating

the construction contractor to meet mechanical completion for RFSC. Managed

all commissioning activities along with consumables for startup. Organized

commissioning team to operate & maintain platform 4 months after startup.

12/4/09 to 3/23/10: Commissioning Engineer, KBR, Saudi Arabia: Lead sub-

completions and commissioning activities for offshore multi-well oil and

gas plat. Main focus was coordinating the sub-system function test,

scheduling and organizing vender support. Perform functional test for

client sign off on all major equipment prior to startup.

10/1/08 to 11/4/09: Commissioning Lead Engineer, Shaw Stone& Webster Arabia

LTD, Sharq Ethylene Project Jubail, Saudi Arabia: Managed commissioning

activities for 1300KTA Ethylene Cracker. Main focus was pre-commissioning

(4) Mitsubishi Turbine Compressors check out and commissioning of 115

additional systems. Supported startup for client.

3/1/08 to 8/15/08: Commissioning Engineer Shaw Stone & Webster, Saudi

Aramco Petro-Rabigh HOFCC Project. Commissioning activates o 1300 KTA

Ethylene Cracker& High Olefins Cat Cracker. Responsibilities were inclusive

as for all pre-commissioning and commissioning.

7/16/07 to 4/7/08: Commissioning Lead Engineer - Shaw Stone&Webster, PSEG

Bridgeport Harbor Mercury Control Project. Responsibilities were inclusive

for commissioning back end mercury reduction coal fire power project, PJFF

(Wheelabrator) bag house project. Pre- commissioning functional and

performance test along with all aspects of startup management as main

focus.

1/07 to 7/2/07:- Commissioning Manager Linde Group, William Opal TXP-5

Unit. Commissioning& Performance test support performed on a 350MMSCFD

Natural Gas Cryogenic NGL plant. Accomplishment included working heavily

with Linde process engineering to trouble shoot demethanizer tray re-

designs and final managing of construction contractor final punch list

close out.

5/06 to 12/06: Commissioning Manager-Linde Group HU-4

Managed pre-commissioning activities on 100MMSCFD Hydrogen Steam Methane

Reformer. The following duties were performed: I&E, mechanical check out,

inspection of sub contactors to meet mechanical completion, validation of

Safety shutdown system and assist operations during steam blows and

refractory dry out.

10/05 to 5/06: Commissioning Manager-Linde Group BOC. Toledo, Ohio. Pre-

Commissioning duties performed on two 50MMSCFD Steam Methane Reformers with

PSA units. Managed all aspects of pre-commissioning, commissioning duties.

7/05 to 10/05: Commissioning Lead -Bechtel/EPC Mountain View Project.

Responsibilities were inclusive for commissioning for two, 2 on 1 GE Frame

7FA combine cycle power plant gas turbine generators and BOP. Plant

capacity (800MW)

2/05 to 6/05: Commissionioning/Owner Rep. at Valero Refinery Ardmore O.K.

Performed pre-commissioning and start up on a Sulfur & Amine Recovery, CO

Boiler unit, G.E.9m Steam turbine generator. Responsibilities were

inclusive as owners Rep. to manage all discipline of commissioning.

10/03 to 10/04: Commissioning/Startup Lead -Kellogg Brown& Root, Southern

Iraq Oil Field, Responsibilities were inclusive with start-up and

commissioning activities that consisted of 12 high pressure water cluster

pumping stations for a 935,000BPD oil field. The field consisted of oil and

gas separation, with the projects main focus on water injection of well

displacement and startup of large water plant, including 12 GE TM-2500 gas

turbine generators.

7/03 to 9/03, Commissioning Manager. Responsible for the field calibration

and turbine monitoring &control system on a 22 simple cycle Pratt&Whitney

FT8

1/03 to 5/03: Commissioning Lead, Black & Veatch;G.W.F.Tracy, CA Peaker

site. Responsibilities were inclusive with start-up and commissioning

activities on a 2GE frame 7ea gas turbine generators (170MW) including

S.C.R.

8/02 to1/03: Commissioning Lead Engineer, Florida Power & Light ;

responsibilities are inclusive with start-up&commissioning activities on a

(1800mw) combine cycle with GE frame 7fa gas turbine generator with a 3 on

1 configuration with Toshiba steam turbine and Westinghouse Ovation for

DCS.

4/02 to7/02: Commissioning Manager, PIC Group for PWPS peaker sites.

Responsibilities were inclusive of commissioning and performance testing

Pratt & Whitney 50mw aero-derivative gas turbine generators. Also trained

operators for up coming peaker season daily operational duties. Utilizing

GE Fanuc for BOP PLC.

11/01 to 4/02: Commissioning Engineer Engineer Black & Veatch for Rio

Nogales Constellation Project. (800MW) Start up duties for three GE Frame

7FA combined cycle gas turbine generators and BOP. Utilizing Mark V gas

turbine controls, and Westinghouse Ovation for BOP and steam turbine

control system. Plant capacity 800mw.

4/01 to 10/01: Commissioning & Startup Manager, Technical Diagnostic

Services, for Handsome Lake Constellation Project. 600MW Responsibilities

were inclusive of the precommissioning, commissioning, and start-up

activities for five Pratt & Whitney 50 MW units. Stayed on until winter as

consultant to teach operators to run plant. Plant capacity 250mw.

12/00 to 4/01: Commissioning Lead, Technical Diagnostic Services, for

University Park Constellation Project. Responsibilities were inclusive of

the precommissioning, commissioning, and start-up activities for six Pratt

& Whitney 50 MW units.Plant capacities (300MW).

9/00 to 11/00: Startup Lead Scheck Technical Services, for Common Wealth

Edison Nuclear Stations. Responsible for Controls and Calibrations on a

Westinghouse 900 MW steam turbine for the refueling outages at Byron and

Braidwood Nuclear Power Stations.

6/00 to 9/00: Outage Lead, Fluor Global Services, for Topeka Vitamin

Plant. Responsible for supervising for direct and contract I&C Technicians

and construction electricians for a turnaround at Wilmington N.C. facility.

3/00 to 6/00: Commissioning Engineer Electrical Contracting Services,

for TVA New Johnsonville, TN. Project. Verified instrument and controls

for four GE Frame 7EA 85 MW gas turbines with Mark V controls. Inclusive

of BOP/Auxiliary systems: Co2 Deluge, Fire Water protection, &Turbine

Water Wash equipment. Plant capacity (350MW).

12/99 to 3/00: Commissioning Engineer Black & Veatch, for Farmland,

Coffeyville, KS. Responsible for all commissioning activities for a Coke

to fertilizer unit.

9/99 to 12/99: Outage Advisor. Rabalais Electric Inc. for Citgo Refining,

Corpus Christi, TX. Responsible for routine and emergency instrumentation

work orders plant wide.

2/99 to 7/99: . Instr. Advisor, Indtech Inc., for Koch Refining, Corpus

Christi, TX. Responsible for routine and emergency instrumentation work

orders plant wide.

7/98 to 2/99: Function Test Advisor. ITI, for Equistar Chemical Plant,

Corpus Christi, TX

Performed trip test on control systems plant wide with O.S.H.A. 9, 010

certification standards, with Honeywell Loveland Document program. Used

Triconex as PLC and Honeywell TDC 3,000. Also responsible for

commissioning new control loops and resolution of problems with ladder

logic on Triconex PLC systems.

7/97 to 7/98: Outage Advisor, Rabalais Electric Inc. for Citgo Refining,

Corpus Christi, TX. Responsible for routine and emergency

instrumentation work orders plant wide.

12/96 to 6/97: Field Service Engineer, Hi-Ran Systems, Charlotte, NC.

Responsible for the installation check out and start-up of water and

wastewater plants throughout lower East coast. This included coordination

of vendors and contractors as well as field-engineered modifications.

7/95 to 11/96: Instrument Tech Advisor Rabalais Electric Inc. for Citgo

Refining, Corpus Christi, TX. Responsible for routine and emergency

instrumentation work orders plant wide.

3/92 to 7/95: Instrument Tech Advisor. Diamond Shamrock, Three Rivers

Refinery. Responsible for startup of all new equipment as well as work

orders involving instrumentation and control equipment. Performed start-up

on

New Hydro Cracker unit, including supervision of contract personnel and

resolution of installation, measurement, and control problems.



Contact this candidate