CURRICULUM VITAE
Mr. Mamerto B. Macuha
As-is, Bauan, Batangas
Philippines
Tel. No. (63-091********)
Email: ********@*****.***
Certification : CSWIP 3.1 - Welding Inspector - Level 2
: API Piping Inspector (API Certification No. 49184)
Sixteen years (16) of extensive working experience in Inspection, in
various engineering practices for constructing oil and gas industry,
petrochemical and refinery plant, upstream and downstream, on-shore and
offshore, cryogenics, power plant, mining's, modularization project and
pipeline projects from front end engineering (FEED), detail design
engineering, construction, hook-up, commissioning, hand over, operation and
maintenance.
Familiar with common codes standards, such as ASME IX (Welding and Brazing
qualifications), ASME B31.3 (Pressure Piping), ASME V (Nondestructive
Examination), ASME VIII (Rules for Construction of Pressure Vessels), ASTM
(American Society for Testing and Materials), API 5L (Specification for
Line pipes), API 1104 (Welding of Pipelines and Related Facilities), API
650 (Specification for welded steel tanks for oil storage), AWS D1.1
(American National Standards for Structural Welding Code-Steel).
RESUME OF WORKING EXPERIENCE:
SUMMARY OF FUNCTIONAL EXPERIENCE:
EMPLOYER : Bechtel, Oil Gas and Chemicals, Inc.
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : Piping Field Engineer
INCLUSIVE DATE : March, 2013 to Present
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : QC Supervisor
INCLUSIVE DATE : July, 2012 to March, 2013
EMPLOYER : Qatar Gas 3&4, QCS (Qatar Gas, Conoco Phillips,
Shell)
LOCATION : Ras Laffan Industrial City, State of Qatar
POSITION : Mechanical Piping Inspector
INCLUSIVE DATE : February 2010 to November 2010
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : Lead QC Inspector (Piping/Welding)
INCLUSIVE DATE : March 2009 to January 2010
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : New Caledonia (France colony)
POSITION : Lead QC Inspector (Piping/Welding)
INCLUSIVE DATE : December 2007 to December 2008
EMPLOYER : Prosafe Production Services Pte Ltd
LOCATION : Subic Shipyard, Philippines
POSITION : QC Inspector (Mechanical)
INCLUSIVE DATE : July 2007 to September 2007
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : QC Inspector (Piping/Welding)
INCLUSIVE DATE : March 2007 to July 2007
EMPLOYER : Alaa Industrial Equipment Factory (AFI)
LOCATION : P.O. Box 42425 Canada Dry, Street, Shuiwaikh 70655
State of Kuwait
POSITION : QA/QC Inspector (Structural/Piping Welding)
INCLUSIVE DATE : July 2006 to December 2006
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : QC Inspector (Piping/Vessel/Tanks/Welding)
INCLUSIVE DATE : September 2005 to July 2006
EMPLOYER : Plant Engineering Construction Pte. Ltd.
LOCATION : 21 Shipyard Road, Singapore 628144
POSITION : QC Inspector (Piping/Vessel/Tanks/Welding)
INCLUSIVE DATE : August 1999 to September 2002
EMPLOYER : Atlantic Gulf and Pacific Co. of Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : QC Inspector (Piping/Welding)
INCLUSIVE DATE : August 1998 to August 1999
EMPLOYER : Kharafi National Company
LOCATION : P.O. Box 24081 Safat 13101 State of Kuwait
POSITION : QC Inspector (Piping/Welding)
INCLUSIVE DATE : November 01, 1996 to September 10, 1997
EMPLOYER : Atlantic Gulf and Pacific Co. Manila
LOCATION : San Roque, Bauan, Batangas, Philippines
POSITION : QC Inspector (Structural/Piping/Vessel/ Welding)
INCLUSIVE DATE : July 1993 to September 1996
PROJECT INVOLVED:
MARCH 2013 to PRESENT
PROJECT : GLNG PLANT PROJECT Modular
Fabrication
OWNER : GLNG Operation Pty Ltd. (GLNG OPL)
JOB DESCRIPTION : Fabrication and erection of piping
on pipe rack and equipment
JULY 2012 to MACH 2013
PROJECT : LIR/LER MODULE FABRICATION
OWNER : ICHTHYS
JOB DESCRIPTION : Fabrication and erection of structural steel and
equipment on LIR/LER module
FEBRUARY 2010 to NOVEMBER 2010
PROJECT : Qatar Gas 3 & 4 Project (Train 6 &
7)
OWNER : Qatar Liquefied Gas Company Limited
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment
MACH 2009 to JANUARY 2010
PROJECT : Malampaya Asset Integrity &
Debottlenecking Project
OWNER : Shell Philippines Exploration (SPEX)
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment
DECEMBER 2007 to DECEMBER 2008
PROJECT : Goro Nickel Project
OWNER : Inco Australia Management Pty. Ltd
JOB DESCRIPTION : Fabrication & erection of piping on pipe rack and
equipment on
Mining Plant
JULY 2007 to DECEMBER 2007
PROJECT : Van Gogh
OWNER : Apache North West Pty Ltd (APACHE)
JOB DESCRIPTION : Converting the Tank MT KUDAM to Van Gogh Floating
Production
Storage and
Offloading (FPSO)
MARCH 2007 to JULY 2007
PROJECT : Goro Nickel Project
OWNER : Inco Australia Management Pty. Ltd
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment on
Mining Plant
JULY 2006 to DECEMBER 2006
PROJECT : Al Basra Oil Terminal Phase II
Project
CLIENT : Parson Iraq Joint Venture
OWNER : PCO Oil Sector North
JOB DESCRIPTION : Fabrication and erection of piping and structural on
flat forms (offshore)
SEPTEMBER 2005 to JULY 2006
PROJECT : Goro Nickel Project
OWNER : Inco Australia Management Pty. Ltd
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment on mining
Plant
SEPTEMBER 2001 to SEPTEMBER 2002
PROJECT : Maintenance on Exxon Mobil Oil Plant.
OWNER : Exxon Mobil Asia Pacific Pte Ltd
JOB DESCRIPTION : Maintenance work (Commissioning) on Oil & Gas
APRIL 2001 to SEPTEMBER 2001
PROJECT : Pfizer Singapore Project
CLIENT : Jacobs Lend Lease
OWNER : Pfizer Asia Pacific Pte Ltd.
JOB DESCRIPTION : Fabrication and erection of piping on
pharmaceutical plant
NOVEMBER 2000 to APRIL 2001
PROJECT : Commissioning/Maintenance on SCC-SOP
CLIENT : Exxon Mobil Singapore Pte Ltd.
OWNER : Exxon Mobil Singapore Pte Ltd.
JOB DESCRIPTION : Commissioning/Maintenance work on piping and
equipment on Oil & Gas
OCTOBER 2000 to NOVEMBER 2000
PROJECT : LRCCU SHOTDOWN
CLIENT : Shell Eastern Petroleum Pte. Ltd.
OWNER : Shell Eastern Petroleum Pte. Ltd.
JOB DESCRIPTION : Fabrication and erection of piping and equipment on
Oil & Gas
AUGUST 1999 to OCTOBER 2000
PROJECT : Singapore Olefins Project
CLIENT : Kellogs Overseas Chiyoda Joint Venture
OWNER : Exxon Chemical Singapore
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment on
Petrochemical Plant
AUGUST 1998 to AUGUST 1999
PROJECT : Singapore Olefins Project
CLIENT : Kellogs Overseas Chiyoda Joint Venture
OWNER : Exxon Chemical Singapore
JOB DESCRIPTION : Fabrication and erection of piping on pipe rack and
equipment on
Petrochemical Plant
MARCH 1997 to SEPTEMBER 1997
PROJECT : Air Separation Plant
CLIENT : Flour Daniel International Ltd. (FIL)
OWNER : Kuwait National Petroleum Company (KNPC)
JOB DESCRIPTION : Fabrication and Erection of above ground and
underground piping.
NOVEMBER 1996 to MRCH 1997
PROJECT : Equate Offsite Piping
CLIENT : Flour Daniel International
OWNER : Kuwait Petrochemical Joint Venture
JOB DESCRIPTION : Fabrication and erection of liquid gaseous, oxygen,
nitrogen,
Service piping
and equipment.
NOVEMBER 1995 to OCTOBER 1996
PROJECT : Two (2) Units 300 MW Coal Fired Thermal Power Plant
Project.
CLIENT : NKK International PTE. Ltd.
OWNER : National Power Corporation Philippines
JOB DESCRIPTION : Fabrication of sea-water intake pipes and
accessories of cooling
Water facilities.
APRIL 1995 to NOVEMBER 1995
PROJECT : Six (6) settler units for waste water treatment facilities
CLIENT : Sumitomo Heavy Industries
OWNER : Asahi Brewery
JOB DESCRIPTION : Fabrication and erection of stainless steel
structure
SEPTEMBER 1994 to APRIL 1995
PROJECT : 570m/hr. Desalination unit 7&8
CLIENT : Mitsui Engineering and Ship Building Co. Ltd.
JOB DESCRIPTION : Fabrication of Brine heater and Evaporator
APRIL to SEPTEMBER 1994
PROJECT : NPC Calaca II X 300MW Coal Fired Thermal Plant
And Pagbilao
Power Station 2x367.5 MW.
Pulverized coal
fired thermal Project
CLIENT : Mitsubishi Heavy Industries Ltd.
OWNER : National Power Corporation Philippines
JOB DESCRIPTION : Fabrication of piping and steel structure
JULY 1993 to APRIL 1994
PROJECT : 3X660MW Coal fired power station precipitators
CLIENT Asea Brown Bovery
OWNER : Shajiao "C" Power Plant
JOB DESCRIPTION : Fabrication of steel structure
DUTIES AND RESPONSIBILITIES
As QC (Welding Inspector):
. 1. Material Inspection
. Review / check mill certificate.
. Conduct visual and dimensional inspection on newly arrived
materials.
. Materials must be in proper places or storage, free from
cracks, oil, grease, and other discontinuities.
. Tags/Markings or stenciled heat numbers on the materials
should be properly inspected.
. Check the materials with respect to mill certificates that are
already approved by the Quality Assurance Engineer.
. Mill Certificates must be always available for review of the
Authorized Inspector or the Owners Representative.
. 2. Welding Inspection
. Before Welding
. Familiarization to applicable codes, standards or client
specification and also the approved drawings of the project.
. Check the welding documents such as approved Welding Procedure
Specification, Procedure Qualification Record and check all
information for all variable and range of approval for the
procedure.
. Check the variable for Welder Certificate and limits and the
history of employment.
. Check and monitor the joint preparation such as per
requirement of WPS and also the jig and fixtures for distortion
control.
. Check the condition of welding machine and the condition of
the welding cables, electrode holder; welding tools to ensure
all connection are correct.
. Check or review all the calibration certificates for all
measuring devices such as calipers, oven, and welding machine
including PWHT machines.
. Check the material size, type and condition of the materials
such as flatness and oval ness of pipe. Make sure to receive the
copy of mill certificate of the materials and must be genuine.
. Check the consumable size, type and condition such as
concentricity of flux covering and the treatment or storage and
handling of the electrode as per WPS and/or manufacturer's
recommendation.
. Check the requirement of preheat such as method of preheating,
the minimum temperature and inter pass temperature. Make sure
the heating rate is uniform and not localized heating.
. Check safety requirements.
. During Welding
. Check the weather conditions and avoid welding during rainy
day and provide adequate protection during windy situation.
. Check the welding position as per WPS used and correct welder
identification.
. Monitor the preheat maintenance by checking the minimum
temperature as per WPS used.
. Check the welding parameters used such as current, voltage and
travel speed as per WPS to avoid metallurgical effects on the
weldments.
. Check the consumable condition and storage.
. Check the inter pass temperature, recommended by the WPS.
. Check the inter run cleaning and check for the method of
cleaning whether by brushing or grinding and the type of tools
involve during cleaning.
. Perform visual on the root to ensure the welding produce a
sound root run.
. Check the removal condition allowed for distortion control
such as strong back, jig and fixtures such as 50% after
completion of weld.
. Check safety during welding.
. Maintain a log book daily.
. After Welding
. Check the cleanliness of the welded joints must be free or
remove from spatter, oil or grease and also check the welder and
joint identification.
. Perform visual inspections observe any defects, records any
defects and compare the size of the defect with the specified
code or standards.
. Monitor or witness the Non Destructive Testing activities for
the joint.
. Check or witness Post Weld Heat Treatment activities such as
heating rate, temperature attained, holding time and the cooling
rate as per procedure used. Check also the equipment before work
commences.
. Collate all documents involved during the fabrication and
submit to higher authorities.
In the event of repair
. Report to the immediate supervisor regarding the extent and
severity of the repair.
. Liaise with Engineer for the repair procedure.
. Marking of defective area for repair.
. Carry out the repair of welding as per procedure and repeat
all duties before, during and after welding.
. Witness the Non Destructive Testing if any.
. Collect the data and result and submit to immediate
supervisor.
As Piping Field Engineer:
. Performs inspection of installed module piping.
. Technical support to module construction team on site.
. Prepares field material requisitions (FMR).
. Coordinates with procurement on delivery of module piping
materials.
. Verification of module piping installation progress
. Responsible for ensuring accurate, timely and consistent
progress reporting.
. Prepare module piping work packs, compiles test packs, sign off
and witnessing testing.
. Updates module piping progress (Team works).
. Prepares piping as-built, perform line walk and prepares piping
Punch list.
. Supports People base Quality program.
. Raise and documents RFI (Request for Information), NCR, FCD
(Field Change Document).
As QC Inspector:
. Experienced in leading project inspection team, work planning,
and inspection procedures and testing preparation.
. Experienced in visual, dimensional and testing during pipe
spools fabrication, piping installation, test package
preparation and review, line checking/punch listing, leak
testing and pre-commissioning of piping systems.
. Experienced in different inspection procedures, welding
procedures, testing procedures, international codes and
standards and project specification as
Structural/Mechanical/Piping/Welding inspector, A Good team
player, able to work on its own initiative or as part of a team.
. Able to resolve non conformities with firm and justifiable
decisions, able to work under pressure effectively with good
problem solving skill and decision making skill.
. Familiar with non-destructive testing such as Radiographic (RT),
Liquid Penetrant (PT), Magnetic Particle (MT), Positive Alloy
Material Identification (PAMI), Ferrite (FT), Post Weld Heat
Treatment (PWHT), Holiday (pinhole detection) testing and Oil
Penetrant testing (OPT).
. Familiar with destructive testing such as Hydrostatic,
Pneumatic, Impact and Bend testing.
. Highly experienced in the preparations of various quality
control inspection reports and final documentation prior to hand-
over to the start-up or operation team for review.
As QC supervisor:
. Monitor Supervise the daily activities of the QC Inspector.
. Evaluate the performance of QC Inspectors.
. Coordinate With shop Engineer /Supervisor and Project Control
Head.
. Coordinate with other department and oversee the implementation
of Quality Control Program.
. To ensure that the inspection and testing has been carried out
in timely manner.
. Participate in the disposition in non-conforming items reported
by the QC Inspector.
. Liaise with the client representative and/or Authorized
inspector with the inspection and test schedule and other issue
related to quality.
. Responsible also for the preparation and submittal of
Manufacturer's Data Report to customer and after project
completion
SEMINARS ATTENDED
. API Piping Inspector 570 Certification Program, SETSCO Service Pte.
Ltd., 18 Teban Garden Cresent Singapore
. RT Film Interpretation, AES Rose Avenue, Pilar Village Las Pinas City
. Basic Offshore Safety Induction & Emergency Training (BOSIET)- OPITO CODE
5700
January 06, 2010
. Visual testing level II conducted by Flour Daniel International Ltd.
November 22, 1996
. Non-Destructive Testing conducted by SGS Philippines at AG&P BHFY
1. Visual testing level II October 18, 1994
2. Magnetic Particle Testing level II October 29, 1994
3. Radiographic testing level II October, 1994
. Quality Control Inspection Training August 02,1993
EDUCATIONAL BACKGROUND
DEGREE : Bachelor of Science in Civil Engineering
(BSCE)
SCHOOL : Western Philippine Colleges
ADDRESS : Hilltop, Batangas City, Philippines
PERSONAL DATA
NAME : Mamerto B. Macuha
DATE OF BIRTH : May 11, 1970
SEX : Male
CIVIL STATUS : Married
PASSPORT NO. : EB1435739
HEIGHT : 5'7''
WEIGHT : 170 lbs
TEL. NO. : (63-091********
SSS NO. : 04-055612-7
TIN NO. : 160-089-073
CHARACTER REFERENCES:
1. Mr. Greg Coronal
QA/QC Manager AG&P
San Roque, Bauan, Batangas, Philippines
2. Mr. Clay Morton
Welding Coordinator
Flour International Ltd. Kuwait
3 A. B. Leong
QA/QC Manager
Plant Engineering Construction Pte. Ltd.
4. Mr. Gerardo Bacalla
FE Piping GLNG project Module yard
Bechtel Overseas Corporation
AG&P Fabrication Yard, San Roque, Bauan, Batangas