HILIGHTS OF QUALIFICATIONS
Over10 years of experience on EPC and PC projects as Project Controls Engineer in each side; Client, Owner
Representative and Vendor
Experienced analyzing contractor- prepared delay claim
Integration of EPC vendor schedules with overall Program Integrated Master Schedule; review the quality of
submissions; analyze and resolve coding, structure, or other discrepancies, import schedule, assess progress, and
develop variance analysis
Fully conversant with development of WBS structure, Resource allocation, Histograms, S-Curves, Progress
Measurement Systems, Change Management & Critical Path Analysis
Solid Performance Measurement Skills with key emphasis on EVM (Earned Value Management)
Strong working knowledge of Project Management across all knowledge areas based on the PMBOK
PMP (Project Management Professional) in process
Highly Proficient in Primavera Project Planner (P6), MS Project 2010, TILOS (Linear Scheduling)
Advanced working knowledge of MS Office, AutoCAD
BSc. In Mechanical Engineering, qualified for P. Eng.
EMPLOYMENT HISTORY
2012/08-Present Options Engineering. Ltd. Toronto, Ontario
Project Planner / Scheduler
Developing the level 4 (task detailed) schedule reflects the project execution strategy using Primavera P6
Developing the hierarchy of schedule reflects the project delivery document level
Ensure the schedule is structured with appropriate coding to provide all necessary control and reporting
functionality
Preparing and keeping up the monthly manpower, resource histograms and quantity curves
Establishing the project schedule baseline to record client approved changes, against which execution
performance can be determined for variance reporting and milestone accountability
Measuring the actual progress so that it can be compared to the baseline to provide a means of assessing
project execution performance
Updating the status of the project, Progress S-Curve, and Critical Path
Determining the status of project execution against the baseline and identifying any schedule slippage
Conducting Schedule trend analysis to determine whether progress is tending to improve or deteriorate, and
determining corrective actions and developing action plans
Develop What if Scenarios evaluate the impact of potential changes and/or prepare contingency plans
Developing and updating various progress reports includes Critical Path and Variance Issue
Preparing and providing information on various forecasts, reports and look-ahead plans on a monthly basis
Phone: 647-***-**** Kamyar Hamidi, page 2
2010 /03-2012 /03 Kasra Pole Fars- Engineering & Construction Co. Iran
Senior Project Planner / Scheduler
Handled mega (EPC) & (PC) projects of Water Transmission to Azadegan Oil Station & Refinery
and completion of water line to Cheghard Iron Ore.
Developed and maintained project master schedules and various area coordination schedules for the
assigned scope of work with Primavera (P6)
Monitored, reviewed and analyzed of the schedule and status of subcontractors during all phases of the
project included the analysis of any schedule deviation and corrective action
Identified and reported the activities which had critical or potential impact on schedule
Liaised with cost controller and other functional managers as required by the project
Worked with construction project manager to maintain the critical path
Develop projects monthly status reports to control project schedule
Responsible for prioritization and forecasting for EPC construction projects
Reviewed, signed and load approved trends into the project schedule
Communicate with site construction management team on a regular basis to confirm the construction
schedule and look ahead plans
2004 /06 -2010 /02 Kasra Pole Fars- Engineering & Construction Co. Iran
Construction Project Engineer - Project Controls Engineer
Assisted in the development of the Project Management Plan, WBS (Work Breakdown Structure), Project
Schedule, Resource and Cost Estimation
Assisted the project managers and superintendents in the creation of short term schedules and monitored
these schedules, determining the impact upon the master schedule
Maintained the master schedule for each project and identified and recorded the impact of work performed
according to the schedule
Evaluated the construction progress and prepared Earned Value Analysis report
Analyzed the impact to project schedule when delays were generated by other functions (Material Delay,
Man Power Delay, Weather Impact, etc.)
Coordinated with project manager, project management team and vendors to update the schedules
2003 /07-2004 /06 Fars Combined Cycle Power Plant Iran
Project Engineer
Developed and maintained CPM schedule for PC project
Interfaced with project manager and other disciplines to obtain data for use in schedule development and
maintenance
Updated and status schedule and supplied report data for project progress reports
Prepared Manpower plan, Progress charts/ graphs and Potential Problem Area reports
Assisted in the analysis of Problem Areas, and provided recommendation for corrective action
Phone: 647-***-**** Kamyar Hamidi, page 3
EDUCATION & SKILLS
Bachelor of Science: Mechanical Engineering - Heat & Fluids, Iran 2000
Hormozgan University - School of Engineering
Primavera Project Planner (P6) Certificate, 2011
PMBOK Certificate, 5th Edition Toronto 2013
Bid and Proposal Management – Bid Winners, Workshop Toronto 2013
MS Project (2010) Certificate, -Seneca College Toronto 2013
LEED AP BD+C Training and Project Experience Certificate, University of Toronto Toronto 2013
AFFILIATION
Project Management Institute (PMI) member Toronto 2013
PMI-SOC (Southern Ontario Chapter) member
ATTACHMENT
WES (WORLD EDUCATION SERVICES) Toronto 2013
CREDENTIAL EVALUATION AND AUDENTICATION REPORT
Canadian Equivalency: Mechanical Engineering Bachelor’s Degree (four years)
Attachment