FABIO M. MINERVINI, P.G.

Senior Project Manager / Senior Geologist

**** ****** ********

San Clemente, CA 92673

949-***-****

**********@***.****

**********@**********.***

EDUCATION

– Bachelor of Science with a Major in Geology, 1991, University of California Los Angeles

(UCLA), Department of Earth and Space Sciences

– Certificate Program in Site Investigation and Remediation, 1996, UCLA Extensions

PROFESSIONAL REGISTRATIONS

– Certified Professional Geologist, California License No. 7861

PREVIOUS EMPLOYERS AND POSITION TITLES

2010 to Present Senior Project Manager, Stratus Environmental, Inc., Huntington Beach,

California

2005 to 2009 Senior Project Manager, Delta Consultants, Inc., Irvine, California

1998 to 2005 Project Manager, England Geosystem, Inc. (formerly England & Associates)

Irvine, California

1995 to 1998 Staff Geologist, Brown and Caldwell, Irvine, California

1993 to 1994 Field Engineer, Schlumberger Technology Corporation, Houma, Louisiana

Temporary Assignments June-September 1993 - Soil Technician I, Leighton & Associates, Irvine,

California

April-June 1993 - Technician, Visco Chemicals, Carson, California

OCCUPATIONAL SAFETY/TRAINING CERTIFICATIONS

– 40-Hour Hazardous Waste Operations Certificate, CAL OSHA 29 CFR 1910.120 compliance

– Petroleum Education Council, Certification No. 100*******

– Radiation Safety and Use of Nuclear Gauges, Certification No. 21966

FABIO M. MINERVINI, P.G., Senior Project Manager / Senior Geologist Page 2 of 4

REPRESENTATIVE PROFESSIONAL ASSIGNMENTS

– Tesoro Refining and Marketing Company, LLC, Senior Project Manager, June 2013 to present.

Managing the technical and financial aspects of the assessment and remediation of fuel retail

sites in Orange, Riverside, and San Bernardino Counties, California (yearly revenue

approximately $1.0 million).

– Atlantic Richfield Company (ARCO), a BP affiliated company, Senior Project Manager, March

2010 to June 2013. Managed the technical and financial aspects of the assessment and

remediation of fuel retail sites in Orange, Riverside, and San Bernardino Counties, California

(yearly revenue approximately $1.0 million).

– Atlantic Richfield Company (ARCO), a BP affiliated company, Senior Project Manager,

August 2006 to September 2009. Lead Scoper (and Lead Executer after September 2008) for

the Orange County Portfolio (yearly revenue approximately $2.5 million). Managing technical

and financial aspects associated with the assessment and remediation of leaking underground

storage tank cases in Orange County, California.

– ConocoPhillips, Project Manager, February 2006 to December 2006. Managing site assessment

and characterization, groundwater investigation and monitoring, and site remediation

for service stations impacted by petroleum hydrocarbon releases in San Mateo County,

California.

– Atlantic Richfield Company (ARCO), a BP affiliated company, Project Manager, 2005 to 2006.

Managed the assessment of releases from underground storage tanks, the investigation and

monitoring of dissolved hydrocarbon plumes, and the remediation of ARCO Stations in the

California Desert/East Los Angeles Portfolio.

– Orange County District Attorney, Project Manager, 2003 to 2005. Managed the third party

technical oversight project pertaining to the legal settlements between the Orange County

District Attorney Office and Atlantic Richfield Company, and Shell Oil. The role of the third

party consultant is to independently review the corrective action at ARCO and Shell gas

stations in Orange County, California and provide recommendations, as warranted.

– California Department of General Services, Project Manager, 2004 and 2005. Managed

assessment and monitoring of dissolved petroleum hydrocarbons from leaking underground

storage tanks at various sites in Merced, Santa Barbara, Riverside, and San Diego Counties,

California. Obtained case closure from the Riverside County Department of Environmental

Health Services for the forest fire station in Temecula, California.

– Kern County General Services Division, Project Manager, 2004 and 2005. Managed ground

water monitoring and remediation of the dissolved petroleum hydrocarbons plume originated

from the leak of an underground tank storing gasoline at the fire station in Bear Valley Springs,

California.

FABIO M. MINERVINI, P.G., Senior Project Manager / Senior Geologist Page 3 of 4

– California UST Fund Commingled Plume Site No. 00024, Project Manager, 2002 to 2005.

Managed under the California Underground Storage Tank Reimbursement Fund Account the

site assessment, remediation, and monitoring of the petroleum hydrocarbon impacted soil and

ground water at the commingled plume site consisting of ARCO Station 0087 and former

Unocal Station 5865 in Hawthorne, California.

– Dunn-Edwards Corporation, Project Manager, 2002 to 2004. At a property in Escondido,

California, formerly a Unocal service station, managed multiple phases of investigation and

characterization of petroleum hydrocarbon impacted soil and ground water.

– Dunn-Edwards Corporation, Project Manager, 2003. At a property leased in Long Beach,

California, obtained a ”no further action” letter from the City of Long Beach Department of

Environmental Health Services for the self-initiated site assessment related to the operation and

maintenance of a 10,000-gallon underground storage tank storing paint thinner.

– Boeing Realty Corporation, Project Manager, 2002 and 2003. Conducted and reported site

characterization activities related to the contamination by diesel fuel at the STEVS Unit on the

Boeing plant in Huntington Beach, California.

– Bradmore Realty Investment Company, Project Manager, 2002 and 2003. Conducted

Phase I Investigations for real estate transactions at sites in Los Angeles County, California.

– ARCO Products Company, Technical Coordinator, 1998 to 2002. At various service stations in

Los Angeles, Orange, and San Diego Counties, California, managed the site characterization,

remediation, and groundwater monitoring programs. Managed the removal and replacement of

underground storage tanks, and the complete demolition of service stations. Provided technical

support in litigation related to petroleum hydrocarbon contamination at service stations in

Orange County, California.

– Various Responsible Parties, Staff and Project Geologist, 1995 to 2002. Reviewed files related

to environmental issues at various agencies in Southern California.

– San Diego Naval Station, Staff Geologist, 1998. Performed investigation and risk assessment

study for petroleum hydrocarbon- and metals-impacted sites in the San Diego Harbor,

California.

– Marine Corps Air Base, Staff Geologist, 1997. Conducted pilot-scale ground water extraction

test for remediation of the dissolved-phase trichloroethylene (TCE) and tetrachloroethylene

(PCE) plumes at the base in Tustin, California.

– Coto de Caza, Private Residential Community, Staff Geologist, 1997. Assisted in the fixation

of lead project at the gun range in Coto de Caza, California.

– Allied-Signal Chemical Plant, Staff Geologist, 1996 and 1997. Conducted soil-gas investigation

of halogenated volatile organics plume in vadose zone at the plant in El Segundo, California.

FABIO M. MINERVINI, P.G., Senior Project Manager / Senior Geologist Page 4 of 4

– Shell/Parsons Reservoirs, Staff Geologist, 1995, and Project Geologist, 1997. Performed two

phases (floor and berms) of mitigation by soil blending, remediation by thermal desorption, and

closure with low permeability cap of crude oil reservoirs at the Tosco Refinery in Carson,

California (former property of Shell Oil Company). Subcontracted by The Ralph M. Parsons

Company for both environmental and geotechnical activities.

– Reichhold Chemical Plant, Staff Geologist, 1995 and 1996. Conducted soil-gas investigation of

polychlorinated biphenyls (PCBs) in the vadose zone installing multiple completion wells with

dual tube air percussion Stratex rig at the plant in Azusa, California.

– Caltrans, Staff Geologist, 1996. Assisted in the storm water facilities retrofit evaluation for the

Santa Monica Bay watershed in Los Angeles County, California.

– Grayson Power Plant, Staff Geologist, 1995. Conducted HydroPunch investigation of

trichloroethylene (TCE) Plume in vadose zone and ground water at the plant in Glendale,

California.

– Shell Offshore, Inc, Field Engineer, 1994. Performed downhole pressure and temperature data

collection, and reservoir interpretation analysis on production platform at Eugene Island Field,

Block 331, Gulf of Mexico.

– Conoco Oil, Inc., Field Engineer, 1994. Assisted in the drill stem test of multiple zones at the

West Delta Field, Block 96, Gulf of Mexico.

– Exxon, U.S.A., Field Engineer, 1994. Assisted in the perforation of multiple productive zones

at the South Pass Field, Block 89, Gulf of Mexico.

– Oryx Energy Company, Field Engineer, 1993. Assisted in the flow test of the Upper Zone on

the semi-submersible rig Ocean Voyager at the Mississippi Canyon Field, Block 445, Gulf of

Mexico.

– Leighton & Associates, Soil Technician I, 1993. Performed soil observation, sampling, and

testing during mass grading and utilities installation as part of the San Joaquin Hills

Transportation Corridor (Wood Canyon) Project conducted by the Mission Viejo Company in

the Laguna Hills.



Contact this candidate