OBJECTIVE
SUMMARY
Qualification
Bachelor degree of civil engineering
Master degree of business administration
Certified advanced Primavera Project Management Course and Ten-Years
experience and knowledge of project control in EPC project from tendering to
project close out in whole process including initial process, planning
process, execution, monitoring and close out by Primavera.
Over 25 years of progressive experience working in civil engineering
construction environment
Over 10 years of progressive in project management including project plan/
schedule and cost control
Technical Skill.
High specialty in project planning process with proficient project
management knowledge specially about planning and cost controlling including
Collecting of required information for the planning, tracking, updating
Producing level 1 ~ level 5 schedule based on the requirement refer to scope
of the work
Tracking the progress and cost and update the schedule
Making project performance analysis with the knowledge of earned value
management.
Providing the proposal how to improve the project performance.
Producing various kind of the report regarding progress, cost and project
performance evaluation
High specialty in Primavera P6 with good operation skill to make project
budget, cost control, activity schedule, resource schedule and progress
control with 10 years experience in following skill.
Setting up EPS and OBS and WBS
Establishing the coding system including project code, resource code and
activity code, cost account
Producing the activity schedule including defining and add activity,
establishing the logic relation and popping out critical path
Assigning the resource to each activity including expense, material, labor
and equipment.
Setting up baseline for activity timeline schedule
Setting up baseline for resource schedule in aspect of cost and manhours.
Setting up the threshold warning system for the tracking of progress and
resource
Updating the baseline when the change order is issued by Client or estimated
quantity/ manhours/equipment is changed
Making 3 weeks looks look ahead schedule and one week past rolling schedule
regarding timing, manhours, equipments.
Making weekly project evaluation by Earned Value SPI, CPI, VAC
Tracking the progress and resource and produce the threshold report to
report project manager about the reason of progress delay and resource over
budget. Make proposal to revise the schedule to catch up the progress to
meet baseline schedule.
Evaluating the project status regarding schedule performance and cost
performance VS baseline with Planned-Earned-Actual Value with graphic curve.
Making ETC (Estimate Cost/Manhours) to Completion) and EAC (Estimated Cost /
Manhours at Completion
High Specialty in construction methodology including work scope definition,
work procedure, labor involved, equipment involved and estimation of man
hour and duration estimation
High specialty technical expertise in civil engineering including
earthworks, RC work, U/G Utility, Steel Works and Road for Industry Plant
Infrastructure, Mining shaft, Dam, Open Pit, Subway Station & Cut and Cover
Tunnel, Bridge & Viaduct and Steel Structure Construction.
Excellent relationship-building and interpersonal skills to all levels of
personnel including senior and executive management,authority, client and
subcontractor.
Had good knowledge and experience in the field of construction to reading
and understanding blue prints and related specification.
Hade excellent written skill to prepare the technical and construction
document and report
Worked as self-starter, self-motivated, proactive individual.
Possessed G driver's license
Other specific skill
Proficient in Primavera P6, MS Project, Autocad, MS Excel, MS Words, MS
PowerPoint and Photoshop.
Design of Construction Methodology
CONSTRUCTION EXPERTISE
Infrastructure including underground utility, structural/mass excavation and
backfill, foundation, piling, RC works, steel works, building and Road.
Mining shaft
Tailing Dam Construction
Open Pit Excavation
Bridge and Overpass
Diaphragm Wall Construction
Bored Pile Construction
Sheet Pile and King Post Driving
Soil Nail and Shot Crete
Utility Detection and Protection
Sewer and Drainages Construction
Top-down Method of Underground Structure Construction
Jet-Grout Soil Treatment
RC Structure Construction such as Retaining Wall, Slab, Column and Pier
Segment Precasting by Mould and Installation by Launching Girder and Mobile
Crane
Steel Structure Construction such as Bridge, Building Tower and Plant
WORKING EXPERIENCE
IDL Projects Inc. British Columbia 15 Nov. 2012 until
Now
Project: Kitimat Modernization Projects
Working Senior Project Planner and Cost Controller
position:
Duty in the project:
Studying the scope of the work and specification in contract and make
original schedule during the tendering stage.
Discussing with project manager, construction manager, superintendent,
procurement department and human resource to ensure the resource to be
available for the project and making more realistic schedule after getting
the contract
Setting up resource data, resource code, activity code, cost account,
expense category for the project by P6.
Setting up WBS to breakdown the SOW into the lowest deliverables level and
try to match cost code for future summary report of cost / manhours
Adding the activity with duration under WBS. Establish the logic relations
between activities and popping out the critical path.
Assigning the resource to the activity and make bottom up budgeted cost,
units and category the cost as demand.
Making manpower schedule to display the period of construction peak and
check with project manager about manpower availability.
. Adjusting the schedule to level the manhours to make schedule more
realistic based on availability of manpower.
Producing level 5 project schedule which including detail activities to be
executed and tracked, assigned with resource. Submit it to client for
approval.
Adjusting schedule if there is comments from client and resubmit the revised
schedule to client.
Establishing baseline activity schedule, baseline manhours schedule,
baseline equipment hours schedule, baseline cost schedule, baseline manpower
schedule to establish the cost budget, manhours budget, equipment hours
budget and manpower budget, after getting approval by client,
Setting up the threshold warning system
Making one week back and 3 weeks look ahead schedule which including
activity description, duration, start and finish date, actual start and
actual finish date, manhours/manpower for each activity, actual
manhours/manpower for in-progress activity. Weekly estimated completion q'ty
for each activity and weekly completed q'ty in past week for in-progress
activity.
Collecting actual manhours, completed quantity and spent cost information
and input them into primavera P6 to tracking them with comparison to
baseline in weekly basis.
Produce the threshold report to report about progress status and resource
consuming status of completed or in-progress activity such as over duration,
over budget, completion delay in weekly basis
Producing Planned-Earned-Actual Value Performance Report with S-Curve in
cost code basis to report the completion percentage of each code, each
commodity, report the cost performance evaluation and schedule performance
evaluation by CPI, SPI, VAC, ETC, EAC to report to client and project
manager about project status as per progress/schedule and cost
consuming/budget in weekly basis.
Having weekly meeting with client about progress/schedule to reply the
question about schedule and get the requirement from client to make
adjustment of construction sequence based on drawing issuing/revision, site
condition, material delivery.
Having weekly meeting with client about project performance evaluation to
check the estimated quantity/ upto-date q'ty, estimated manhours/consuming
manhours, estimated cost/consuming cost to ensure both party use the same
data to get accurate evaluation result.
Making monthly cost, equipment and manpower forecast as per base line in the
basis of cost code to help accounting, human resource and procurement to
organize the resource.
Adjusting the schedule and renewing the resource in Primavera P6 and
submitting new schedule assigned with renewed resource to client for
approval If there is change order or the estimated quantity do not match the
realistic condition and the change order or new estimated q'ty is approved
by client,
Establishing new baseline for activity, manhours, equipment hours, material
and manpower for further activity tracking, cost tracking and project
evaluation once the new schedule is approved by client,
AMC Mining Construction
Sask.
15 Apr. 2012 - 10 Nov. 2012
Project:
Mosaic Potash Mining (350 Million Contract)
Working position:
Project Planner and Scheduler Specialist
Duty in the project:
Make execution plan (schedule level 5) including engineering, procurement
and construction
Set up resource data, resource code, activity code, cost account, expense
category and CWP for the project.
Assigning the resource to the activity and make bottom up budgeted cost,
units and category the cost as demand.
Make budgeted unit and cost analyze by activity usage profile and resource
usage profile
Setting up the threshold warning system
Update and cost tracking based on decided data date.
Establish Earned Value Management system and make performance analyze
Issue project performance report and threshold report regarding cost
performance and schedule performance.
Performance the estimate to complete and estimate at completion and variance
at completion.
Make monthly cost forecasting as per total cost and difference category
Communicate delivery requirement of major equipment and material to
procurement
Understand subcontract to ensure cost, schedule and invoice compliance.
Estimate the cost of contract change
Work with project management to set period goal, objectives and success
factors and analyze the project status
Assessing progress measurement and developing / updating progress curve for
progress report
Chartrand Equipment Timmins, Ontario April 2011 until
April 2012
Specializes in the construction of the mining works, sewer & water, bridge,
infrastructure for both the public and private sectors in Canada
Project: Tailing Management Area in Detour Lake (20 Million Contract)
Working Lead Project Cost Controller and Scheduler in Detour Gold in
position: Ontario
Duty in the project:
Take part in the bidding work in the tendering stage including following
work
Research the tendering document and clarify the scope of work including the
deliverables, discipline, project phase and area
Advice the construction methodology including construction sequence,
equipment involved and labor involve.
Estimate the non labor units and labor unit for construction activity
Make different levels of schedule:
Create the project and set up WBS by primavera P6
Advise the construction methodology for estimate the labor and non labor
units for each group of the activity (WBS)
Calculate the summary man hours for each group of activity under WBS to
budget estimation.
Produce the level 3 schedule which include all summary of the duration,
resource units for deliverables and discipline.
Make execution plane level 4 including all the detail activity and assigned
resource and expense to each activity
Make close cost control of the project:
Create the resource and role for the project
Assign the resource and role to all the activity in the project to form
execution plan level 5 schedule based on level 4 schedule
Set up the cost account track activity costs and earned value according to
the specific cost account codes
Make resource usage profile to reflect the resource distribution trend for
the related activity
Make resource usage spreadsheet to reflect the detail resource distribution
for each related activity
Make progress and cost tracking and update schedule
Collect the all the site information including labor, non-labor, material
and equipment and completion q'ty and fill them into the active schedule to
update the schedule and make sure the resource % completion and activity %
completion
Make the judge progress status whether on schedule and on budget based on
the updated schedule information comparing with baseline
Use thresholds to analyze whether any problem occurred in the implementing
the schedule
Project performance analyze
Use schedule variance to analyze whether the progress is ahead or behind the
schedule
Use cost variance to analyze whether the cost is under or over the budget
Use EAC to estimate the final cost from the current day
Use ETC to estimate the remaining cost still need from the current day
Produce various kind of the report
Produce updated schedule regularly
Produce two week ahead schedule weekly
Produce three month ahead schedule monthly
Produce earn value report including EV, SV, CV, ETC and EAC
Produce resource loading report
Produce resource and expense cost report
Produce schedule/progress report including the duration % completion,
resource % completion and q'ty % completion.
China Grand Engineering Ltd Hongkong 2005-2010
Specializes in the design, supply and fabrication of structural steelwork,
bridge and viaduct construction equipment, gantry cranes and steel formwork
for both the public and private sectors worldwide.
Website: http://www.cgrand.com
Working Project Manager
position:
Duty in the project:
Organized the project management in the construction by safety plan,
construction methodology plan, construction activity schedule, resource
schedule, cost control and progress control by Primavera .
Prepare and submit construction project budget estimates
Prepare contracts and negotiate revisions, changes and additions to
contractual agreements
Establish and implement policies and procedures for quality control
Select trade subcontractors and co-ordinate their activities
Track and manage budgets
Manage day to day operational aspects of projects and scope
Effectively apply methodology and enforce project standards
Work closely with executive team to ensure corporate objectives are being
met
Project: NOVO Terminal Maritimo Da Taipa Macau (16 Million C$ Contract)
Project: Proposed Factory at Tai Po Town in Hong Kong (30 Million C$
Contract)
VSL International Limited, Hong Kong Hongkong 2002-2005
VSL operates through 34 subsidiaries as a world-wide network specializing in
the construction of viaduct spans, bridges, buildings, ground engineering
and industrial facilities
Website: http://www.vsl.com
Working Senior Project Control Engineer
position:
Project: TCC200-300 East Rail Extension HongKong (80 million C$ Contract)
Project: Tailing Management Area in Detour Lake (20 Million Contract)
Kumagai Gumi Limited (General Contractor), 1998-2002
Singapore
Kumagai Gumi, one of biggest civil construction company in Japan,
specialized in investigating, surveying, planning, designing, executing and
supervising construction works in aspect of subway, bridge, high way, port,
building as general contractor
Website: http://www.kumagaigumi.co.jp/english/tech/railways.html
Working Position: Civil Construction Manager
Project: MRT North East Line Contract 705 Sennett and Boon Keng Stations and
Tunnels, SINGAPORE
(160 Million C$ Contract)
Duty in the project
Organized the site construction activity by activity schedule, resource
schedule, cost control and progress control by MS project.
Make construction method design before executing the construction activity.
Cost control and progress control with construction method, activity
schedule, resource schedule, daily activity record
Coordinated interpretation of clients, consultants and all levels of
internal staff for construction.
Checked the technical quality of site work and resources allocated to the
project.
Managed the drawing, specification, contract and other documents to ensure
the updated information is implemented in the site
Manage the day to day work regarding construction activity, resource
allocation, safety and quality.
Prepared field change request to resolve the design issues
Prepared drawings and sketches to support construction work as required.
Made the construction method design of the top-down method in the station
and bottom up method in the cut and cover tunnel
Set up working permit system such as hot work permit, excavation permit,
lifting permit and deep slab concrete permit
Dealing with Land Transport Authority of Singapore about construction method
Dealing with traffic authority for road diversion and pedestrian access.
Dealing with utility authority for the utility protection and diversion
Designed construction methodology including as below
Road diversion construction
Diaphragm wall construction
Bored pile construction
King post and sheet pile driving
Trial trench for utility exposure
Suspension design for Utility protection
Excavation for the roof slab
Excavation for concourse slab under roof slab
Dewatering plan for the drainage in the construction site
Settlement monitoring
Diaphragm Wall Construction
Soil nail and shotcrete for slope stability
Jet grout for soil treatment and cavity fill
Excavation for base slab under concourse
RC construction for Roof, concourse and base slab
Column and Wall construction
Entrance construction
Sewer, drainage construction
Backfill and road construction
Water proofing
Excavation under Roof Slab
Gammon Construction Limited Singapore 1997-1998
The leading civil construction contractor in the field of civil engineering
in Southeast Asia for over 50 years. where headquartered in Hongkong
Website:
http://www.gammonconstruction.com/hk/eng/projects/projects_index12.html
Project: Bukit Panjang LRT in Position: Senior Site Engineer
Singapore
Duty in the project:
Designed the construction method of viaduct segment erection by launching
girder and mobile crane.
Designed traffic diversion and control design when the viaduct cross the
public road
Designed the construction method of segment precast
Designed the construction method of pier column construction including pier,
column and foundation
Deal with traffic authority and local government department for the traffic
arrangement and control when the viaduct crosses the public road.
Made the construction method presentation to the client.
Prepare the method statement including manpower estimation, equipment, tools
and material to be used, temporary works to be added, construction sequence,
traffic arrangement, working permit system safety and risk.
China Merchant Heavy Industry Limited HongKong 1990-1997
Position: Senior Project Engineer
Project experienced:
Steel structure for Macau Incineration Plant subcontracted from Mitsubishi
Heavy Industry
Steel structure fabricationof Tsing Ma bridge subcontracted from VSL
International. Organized the welder training for the qualification
Segment precast mould fabrication for West Kowloon Expressway -North Section
subcontracted from Kumagai Gumi Limited
Tunnel formwork fabrication for Route 3 and Cheung Ching Tunnel
subcontracted from
Dragages Hongkong
China National Offshore Oil Corporation China 1984-1990
Project: W10-3 oil field in north bay of
South China Sea
Project: Y13-1 gas field of South China
Sea
Position: Project Engineer
Involved in construction of offshore oil platform for the structure
Involved in offshore oil platform manufacturing including the structure and
module
Reference list
Name, Position, Company, Contacting Address, Phone no.
Rheal Project Chartrand 709-***-****
Charett Manager Equipment
e
Jim General China Grand Flat C&D, 33/F, Tower 8, +852-********
Chen Manager Engineering Grand Regenville 9
Wo Mun Street, Fanling, N.T.
HongKong
Pascal Project VSL 20/F 8 Commercial Tower, 8 +852 2590 22
Butte Manager International Sun Yip Street, Hong Kong 88
Ltd. Chai Wan
Hong Kong
K. Project Kumagai Gumi IOI Plaza #07-04/08, 210 +65 6338 5352
Mafune Manager Ltd. Middle Road (S)188994,
Singapore
Y.W. Technical Gammon 230 Orchard Road +65 67360883
Leuang Manager Construction #08-232 Faber House
Ltd Singapore 238854
Remark:
Mr. Y.W. Leuang have left Gammon and set up his own firm for bridge design.
Above contacting information is his office information in Singapore
Mr. Pascal Butte have moved to VSL headquarter in Switzerland
Education
Bachelor degree of Offshore Tianjin University in China
Civil Engineering Website:
http://www.tju.edu.cn/english/TandL/academic_sch
ools/
Master degree of business Fudan University in China
administration Website: http://www.fudan.edu.cn/englishnew
Certification of Primavera Certification of Primavera Project Management
Project Management Advanced Advanced Course.
Course
[pic][pic]