Project Manager Engineer

Location:
Saint-Symphorien-sur-Coise, RA, France
Posted:
November 15, 2013

Contact this candidate

Resume:

Adress: ** Impasse du Mont

Chassins

***** *******

Mobile : +336********

Further training:

IFP (French Petroleum Institute): Refinery

Offshore survival 2012

Environmental management

IFP Lecturer

Risk Awareness and Human Factor 2006

Opercap verifier 2001

Operguid Trainer

Opito Assessor 2002 ( D 32.33.D34) SQA registration 028378521

ICAPS 2004 ( Opercom)

ATEX Level 2 2009

Core Competency:

Over Twenty three years experience of erection management, commissioning

and start-up of industrial complexes -Onshore and Offshore project-

Strong organizational and able to manage a multi-disciplinary & multi-

cultural team up to 160 Staff.

Training of local and turnkey staff.

Responsible for overseeing the EPCC package contractor, manage the pre-

commissioning/ commissioning and execution activities.

Coordinate and manage the job with a selection of the most qualified

personnel to be recruited from the partners and contract personnel.

Prepare and manage a commissioning budget.

Review and monitor EPCC contractor pre-commissioning and commissioning

progress.

Coordinate and interface with all project members.

Ensure proper integration with operation department.

Large-scale Project approach on International EPCC contracts

Auditing & process optimization, methods, SIMOPS risk

Interface with other project specialists, co-ordination of technical

activities performed inside or outside the company

Tendering Evaluation & Proposals (commercial & technical)

Establishing, maintaining procedures/processes & reporting

Equipment inspections

Familiarity with process documentation (process simulations, P&IDs, PFDs,

Data sheet for equipment HAZOP etc)

Familiarity with piping/mechanical documentation (piping class, layout,

isometrics, painting, MTO)

Skills& Knowledge:

8 Years in Training

Project Manager (Training & Assessment)

Compiling training manuals and training of new employees.

Training Design and trainer in Oil Gas (Upstream & Downstream)

Civil Work (Project Engineer) From 1985 to 1992 (Building & Roads)

From 1975 to 1995 (Work oversea in Construction, Commissioning, and

Training)

Experience of Units:

- FPSO- Phenol Distillation- Butadiene - HDS - Atmospheric Distillation

-Amine-Sour Water-Effluent Treatment-Claus Unit- Dehydration-Tail Gas-

Sulphur Unit-Acid Gas- CCR- HDT- Hydrocracker- Gas plant & GPL- Utility-

Coal Fire-Cogeneration Unit- Dust Incineration -LNG Plant-Hydrogen -Storage-

Pipelines- Water Treatment-demine water-Boiler-Combine cycle-Nuclear

Treatment-gas turbine - Steam turbine (Condensation &back pressure)

Oil & Gas production onshore Offshore. Reverse Osmosis(Toray Membranes)

TOTAL TABK 06/12_06/13

TOTAL ACADEMY UAE (Emiratisation)

Offshore Training Coordinator

Participate in or coordinate and supervise the preparation and

implementation of the apprentices and the company's employees OJT programs

and its adaptation to prepared programs.

Organise meetings with supervisors and local management at regular

intervals to ensure follow-up and permanent evaluation.

Review and upgrade the technical training materials prepared by technical

trainers in accordance with field specifications.

Give assistance to the company's supervisors and mentors in the supervision

of the OJT activities on site

Provide the management and personnel with the necessary tools and resources

to prepare and organize training actions.

Supervise internal mentors and possibly external instructors and check the

performance of training programs.

Participate to daily work permit meetings. Schedule or modify where

necessary OJT activities in relation to the work on site.

Participate in or ensure training program execution coordination.

Organise training schedule.

Check continuously training activities according to the plan.

Assess trainee's performance with mentors and cross-check the level of

competencies.

Review and update the assessment sheets with the help of supervisors.

Collect from the mentors or supervisors the assessment sheets and verify

their quality content.

Safety training

Ref: Laurent Chiabotto, Jean Marc Aldebert, Laurent Dolmetta, Eric

Delattre, Mohamed Tamiemi, Maurice Loubet;

VEOLIA QARN ALAM (OMAN) 04/12-06/12

Commissioning Advisor

Logic Sequence (auto start and shut down)

De aerator (capacity 200M3/H)

Cartridges Filter, Median filters

RO Train (Toray Membrane)

Training and OJT

SIDEC WEST INDIES 04/2011-01/2012 (QUADELOUUPE MARTINIQUE)

Project Manager

Coal and bagasse power plant

Integration New Units: Crusher smoke treatment erection (Commissioning &

Start-up) new

Warehouse and administration building

Team (5)

Auditing & process optimization, methods,

Interface with other project specialists, co-ordination of technical

activities performed inside or

Outside the company

Tendering Evaluation & Proposals (commercial & technical)

Establishing, maintaining procedures/processes & reporting

Equipment inspections

Study Case

Process documentation (process simulations, P&IDs, PFDs,)

Prepare and manage budget.

THERMODYN France 01/2011 -Auditor la Colette JERSEY

Site Coordinator Energy from Waste

Commissioning Audit Steam Turbine

Involve on verification and application of Thermodyn Standard

Interface with the client

Pre Com / Com &Start-up Condensing unit steam turbine (Generator Andritz

12 MW)

Automate GE Fanuc /G60

Interface with PM regarding Back charge dossier

THERMODYN France 10/2010-12/2010-Dalkia Project Biomass station

Site Coordinator Start-up

Involve on Start-up of 2 steam Turbines

One at 43 MW Connected to a Biomass Boiler (Wood) Condensation steam

turbine

One at 21 MW Connected to a Black Liquor Boiler. Back pressure steam

turbine

GE Fanuc Automat and Woodward 505

Ensure Logic system is valid and software modification in the GE Fanuc

Writing Start-up manual

Performance test steam turbines

Following mechanical part of the steam turbine

SAMCCA France 01/2010-07/2010 Consultant Commissioning training &

resources

Developing Training Courses Oil & Gas

Developing Competences Assments

Developing Training Course in Commissioning

Commissioning Audit

Developing HSE Course

Redaction on MAQ for the company

LITWIN / GRT 07/09 -12/2009 Site Manager

Involve of end of Construction Commissioning and Start-up of Gas Station

Use Icaps and GRT spec

2 gas turbines with compressors SOLAR (Flow rate8 millions square cube of

gas at 75 Bars

Utility station including 20KWA, TBGT, Battery 24,120,400 Volts

ESD matrix

Pipeline

Redaction of performance test

Simops Operations including Risk assement

Preparation of documentation for the Mechanical acceptance

Ready for gas in and start-up

Review and monitor EPCC contractor pre-commissioning and commissioning

progress.

Coordinate and interface with all project members.

Ensure proper integration with operation department.

Technip France: F.P.S.O. AKPO Project offshore 2008/2009 Nigeria

Commissioning activities in line with required prioritization & schedule

for milestone handovers, introduction of first hydrocarbons (Methanol),

First Oil & First Gas. Liaising directly with Hook Up team, Field

Operations & UFR contractors (Saipem) during mooring activities,

installation of Umbilical's, Flow lines & Risers.

Commissioning Manager in charge preparation and commissioning. Total Team

included vendors 126 persons.

Different Vendors for packages to be commissioned

Sub Contractors HP leak test with Helium and Nitrogen Halliburton

Roll Royce 6 Gas Turbines with WHRU

Writing performance test procedure

Simops Operations

Hull: 350M/60/32 meters

Oil storage capacity: 2 million barrels

Scheme Production 235 kBLP + 530 MMSCFD

Export Condensate to tanker 185 kBOPF

Dehydration Unit, Gas Export 320 MMSCFD at 200 Barg to Amenam

Produced Water :150kBWPD

Water treatment

Water Injection : 420 kBWPD at 220 Barg

Gas Injection 185 MMSCFD at 400 Barg

Review and monitor EPCC contractor pre-commissioning and commissioning

progress.

Coordinate and interface with all project members.

Ensure proper integration with operation department.

TOTAL LEUNA 01/2008-08/2008 Commissioning and start up Manager

ADU/VDU REVAMP PROJECT & T&I 2008

TRM refinery plans to debottleneck its crude atmospheric/vacuum

distillation complex, with the following main objectives:

Reduction of Vacuum Residues (VR) production

Revamp the ADU Heater by installing a new pre-heater (APH)

Maximize kerosene production at the expense of Naphta

Installation of the new pumps around the section K1003 aimed to draw off

the HHGO side cut. This implies the replacement of existing trays, 41

thru 46, and installation of items associated with the new pumps.

Replacement of existing N 6 trays in the top section of K1003 and of the

existing reflux line distributor with new ones in Monel.

Installation of the new draw off HHGO"

Installation of an additional Kerosene product Heat Exchanger.

Installation of the new air-cooler

Revamping of the existing heater.

Simops Operation

Edit Sub System Marked-up PID'S

Redaction and Validation by Authority T V

Pre Com & Com Manual Execution Plan

Meeting with Authority T V

Preparation of documentation to be valided by T V

JSA

Lines Cleaning & gross Leak Test Procedures (Precom)

Pinch List Procedure

As Built Drawing Procedure

Intro to Opercom

Edit Check Sheet Pre Com & Com used for the Project

> Coordination Meeting with TRM

R f TOTAL : Nabil Lazrak Project Manager

ENI CONGO 07/2007-11/2007 TRAINING CONSULTANT

Train 22 new employee (Production Operators)

Thermodynamic, Chemistry of water, maintenance, Techno of different

materials

Fundamental process, PFD, PID, BFD

Process instrumentation

Unit Wells (PCI and Gas Lift, test Separator

Production Separator, Deshydratation

Glycol Unit, Amine Unit

Gas Lift Compressor,

Water treatment

Demin Unit

Hot oil system, Oil Stripping

HSE training + Work permits

Creation of one Work Book for trainees

Preparation and redaction on competence guide for OJT

Preparation and Validation on Assement Worksheet

Basic oil for none production

R f ENI : Alain Bourgeois

TECHNIP AUSTRALIA 01/2007-06/2007 Client WOODSIDE

COMMISSIONING ENGINEER

Review and monitor pre-commissioning and commissioning progress.

Coordinate and interface with all project members.

Precom and Commissioning 2 trains LNG,UTILITY

Writing commissioning procedure OTP & LTP

WIN PCS database

Meeting with Client

Simops Preparation

Risk Assement

Units 2 trains LNG

Review ESD matrix(Sub contractor)

Pipeline (Pre Com & Com)

Storage

Utility air, Instrument air,

Demin plant(Veolia)

Nitrogen License Kaevner

Amine Technip License CO2 Oxidizer

LPG/NGL Fractionation (Cryomax) Technip License

Mole sieve Unit with Mercury Guard Bed (CECA)

MEG Unit

Turbo Expander

R f TECHNIP : Jacques Tronche

TOTAL INDONESIE 12/2005-12/2006

SPDT PROCESS ENGINEER AND MECHANICAL

PROJECT TAMBORA 2 (3 GATHERING AND 2 MODIFICATION) & TUNU 10 (4 GATHERING)

Writing commissioning procedure OTP & LTP as per Opercom

ICAP database

Following punch List

Meeting with OPS

Risk Assement+Work permits

Pre Com Pipeline to CPU

ESD matrix &Instrumentation

Review and monitor EPCC contractor pre-commissioning and commissioning

progress.

Coordinate and interface with all project members.

Ensure proper integration with operation department.

TECHNIP (TURKMENISTAN) 02/2005-11/2005

DEPUTY COMMISSIONING MANAGER

DHT Gas Oil Licence Axens

Sour Water Treatment

Amine Unit

Claus and Tail Gas Licence KTI

Utility (Cooling Water, Demin Water, Nitrogen Plant, Offsites)

Ensure ESD matrix ready for Start-up

Responsible for overseeing the EPCC package contractor, manage the pre-

commissioning/ commissioning and execution activities.

Coordinate and manage the job with a selection of the most qualified

personnel to be recruited from the partners and contract personnel.

Compiling training manuals and training of new employees.

Prepare and manage a commissioning budget.

Review and monitor EPCC contractor pre-commissioning and commissioning

progress.

Coordinate and interface with all project members.

TECHNIP MALAISIE Client EXXON MOBIL05/2004 -12/2004

OTP WRITER EPC

Writing procedure pre commissioning and commissioning

Writing Operating pocedure for start-up and normal operation

Writing Operating Manual (molecular sieve et compressors HP)

Check sheets pr com et commissioning (Win PCS)

TOTAL GABON 8/ 2003-4/2004

PROJET MANAGER

Evaluation, recruitment 50 Operators

Training and validation by Opertrain methodology

Following budget and invoice

R f TOTAL: Marc Fourneraut

MARATHON OIL GABON 2003

PROJET MANAGER

Assessment 24 operators, mechanical, and electrical

Report and training plan

SHELL GABON2002-2003

TECHNICAL COORDINATOR

OPITO Hydrocarbon assessor PRODUCTION (65 candidates)

TOTAL CONGO 2002 ADCE

training instructor

Operguid procedures

Redaction procedures

Redaction Operating Manual

TOTALCONGO 2002-2001

PRODUCTION ENGINEER

In charge of plant failures technical analysis and identification of

solutions aiming at improving operations

Plant performances analysis and recommendations aiming at optimizing

operations

Existing operational procedures updating

Missing procedures writing with operators assistance

Follow-up and classification of site documents

Operators training "On the Job Training"

Meticulous preparation of large interventions: decomposition of those

interventions in controlled elementary tasks, means adequacy :

interventions quality and teams respect guarantee

Took care of the respect by the producers of provision and handing-over

at disposal

Procedures

Took care of plant optimal control and safety

Took care of the systematic edition of a report of each failure

Total Congo staff : 80 people including 60 operators

Oil output : 50 000 bbl/day

TECHNIP / MIDOR (EGYPT) 2001-2000

UNIT ENGINEER (DEPUTY START UP COORDINATOR)

Pre commissioning, commissioning and start-up

TECHNIP tools management updating for pre commissioning follow-up

Punch list follow up

UOP process hydrocracker

MKTI process hydrogen

MKTI process of Tail gas sulphur unit

UOP process HDT gasoil

Offsite

Water treatment+ demine Plant

Flare

GROUPEMENT TFT (ASSOCIATION SONATRACH / TOTAL FINA / REPSOL) 2000

Training Consultant

USINE DU CHAMP DE TIN FOUYE TABANKORT (ALGERIE)

Create job ticket of production ( shift engineer DCS operator chemist)

Elaboration training plan

Assessment production personnel

Redaction of training manual

Redaction of procedures and incident report

Training of lecturer

R f TOTAL : Jean-Marie PERDU

KREBS - KREBS - AKTABINSK (KAZAKSTHAN) 1999

START UP ENGINEER

Assistance to the client for tests and start-up of alcohol distillery

TOTAL SIRRI (IRAN) 1999-1998

OJT supervisor on Sirri E field

Commissioning, start-up offshore platform

OJT for iranian panel operators

Commissioning, operating, testing procedures

Pre Com,Com and Dewatering Pipeline

TECHNIP BONNY LNG COMPLEX PROJECT (NIGERIA) 1998

COMMISSIONING SUPERVISOR

Commissioning of Utility and Train 1 LNG Plant

BABCOCK 1998 CORBEILLES SUGAR MILL

Start-up head

Start-up of a 75 T/h, 65 bar boiler monitored with PLC Telemecanique

CNIM 1998 HOUSEHOLD WASTES INCINERATION PLANT, CHAUMONT

Supervisor

Preliminary tests and start-up of installations

CNIM furnaces - 2 x 5 T/H

CNIM boilers - 2 x 15 T/H, 40 bar

Turbine / alternator group

Smokes treatment Lurgui (milk of lime and bag filters)

Demin Unit (Degremont)

ALBEMARLE PPC 1998 THANN PLANT

Instructor

Preparation and realization of training activities in relation with BFC

(Bromine FineChemicals) service reorganization in order to improve the

skills of operators

TECHNIP / UFANEFTEKIM1998-1997

Supervisor

Technical assistance to Dual Forming unit (IFP) start-up with DCS Modumat

8000

TECHNIP / UZBEKNEFTEGAS 1997BUKHARA REFINERY (UZBEKISTAN) - 2.5 MT/YR

Shift Engineer

Commissioning and start-up of refining units with DCS Honeywell TDC 3000

Atmospheric distillation

Naphta HDS

Gas oils HDS

Kerosene sweeteing Merichem process

Reforming

Sulphur

ELF ANGOLA1997 OFFSHORE OIL FIELD (ANGOLA)

Supervisor

Maintenance of gas turbines turbomeca and Hispano

TECHNIQUES MODERNES DE COMBUSTION1997-1996 HOUSEHOLD WASTE INCINERATION

PLANT, DOULLENS Start-up head

Writing test and start-up procedures

Tests, commissioning and start-up

Fats HONEYWELL DCS

EGT 1996-1995 COGENERATION POWER PLANT, SOUSSE (TUNISIA)

Coordinator

Coordination of plant commissioning and reception works

Works planning preparation

Supervision of piping modification and works to comply specifications

Technical and commercial negotiations for provisional reception

Punch list clearing

STEIN INDUSTRIE 1995 HOUSEHOLD WASTE INCINERATION PLANT

Start up supervisor

Tests and start-up of the plant

Industrial running

Personnel training

Plant includes

Furnaces - 2 x 8 T/h

Boilers - 2 x 40 T/H, 38 bar

Smokes treatment LURGI

DCS FOXBORO

EGT / L'AIR LIQUIDE - ROSENBURG (THE NETHERLANDS) 1995

Start-up engineer

Test, start-up and operation of a cogeneration plant with DCS FOXBORO

Punch list clearing for provisional reception

Wiring, soft modification

Start-up

Operation personnel training on DCS FOXBORO operation

Plant includes :

2 STORK KETEL boilers

2 gas turbines EGT type 6000

Alternator ALSTHOM - 2 x 44 MW

Control-command Mark V GENERAL ELECTRIC

STEIN / NATIONAL POWER 1995-1994 THERMAL POWER PLANT, CAMBRIDGE (UK)

Commissioning and start-up engineer

In charge of boilers and water station commissioning and start-up in a

cogeneration power station

Automatisms sequences checking

Circuits preparation and verification

Instruments calibration

Start-up and tests-runs

Equipment

Boilers STEIN - 2 x 300 t/h, 120 bar, 540 C

Water treatment DEWIPLAN - 50 m3/h

Personnel training in boiler operation with DCS HARTMANN AND BRAUN

Education :

. 1985 Civil Engineer (CNAM)

Others :

. Nationality: French

. Statut: Married

. Date of birth: 03/10/1957

. Language(s) : French (Native language)- English (Fluent)- Spanish

Beginner

. Computer software: WORD, EXCEL, ACCESS, POWERPOINT, VISIO, LOTUSNOTE,

INTOOL'S, PHOTOSHOP, ILLUSTRATOR