Curriculum Vitae

Personal Details

Name: MICU

Surname: GHEORGHE

Date / Place of Birth: 17.09.1978 .BUCHAREST.ROMANIA

Nationality: ROMANIAN

Marital Status: MARRIED

Address: Aleea Florin Ciungan#3.BL67. flat #15.District

3

BUCHAREST

Mobile: 004 072******* - ROMANIA

E-mail: acaegc@r.postjobfree.com

Executive Summary

. A skilled operator engineer with 17 years of power plants experience

in performing steam turbines & boilers operations, start-up, shut-

down,

pre-commissioning,commissioning and erection procedures. Process &

BOP.

. Excellent interpersonal, communication, presentation & facilitation

skills especially with the customers and project engineer teams.

. Excellent team leadership and team building skills.

Career Objective

. Secure a challenging technical position where in my team player

attributes, experience, and communication skills can be utilized in

obtaining personal career goals and those of the employer.

. To advance technically in the science of Plants facilities and

contribute to industry by participation as a skilled Project Manager -

Commissioning Manager

Commissioning Supervisor

Bio Data

. Countries Worked In: Romania - Libya - Panama - Chile

. Countries Lived In Romania

. Foreign Languages: English (Good reading, writing and speaking)

Spanish (Good reading,

writing and speaking)

WORK EXPERIENCE:

Period: April 2011 - up to date

COMPANY: Tecnimont S.p.A.

LOCATION: Chile

PROJECT: Bocamina II Project,Coal- Fireing POWER PLANT & GE Turbine

POSITION: Commissioning DCS Operator

Desk Operator at Coal Fired stations.SES Tlmace Boiler 1200 t/h x 350MW

Steam Turbine General Electric units with biomass additional firing FGD &

Fabric Filters. Responsible for all Operation start-up & shut-down of Plant

and all associated auxiliaries as well, coordinating the field operations

and troubleshooting.Execute a power plant test program based on the

contractual requirements of the project.

Invensys Coal Fierd Boiler DCS Foxboro - Mark VI GE Steam Turbine DCS

Responsible for all tests included Boiler Operation and Steam Turbine

Operation as :

Steam Turbine : Efficiency Test,Reliability Run Test,Performance Test,Load

Rejection and Island Mode Test, Enthalpy Drop Test,Overloud Turbine

Generator,Overspeed Turbine Test, Syncronizad, Turbine Forward Flow,

Turbine Follow Mode,etc.

Boiler : Boiler Coal Firing - To reach 100% of load burning coal.530 C-

172bar

Automatic Boiler Stabilization - coal & diesel oil fiering

control system

ZGM113 Mill load - 1600 kN (Static Load) / 4800 kN (Dynamic

Load)

start-up & emergency shut-down/ functional testing of, Mill Auto Mode,

Boiler Master Controler, Boiler Follow Mode .Circulating Boiler Pumps,Air

& Flue Gas System/FDF/IDF/PF&RAH.SAH all in normal operation. Coal Handing

& Silo,Bottom Ash System,Flay Ash & pout the FGD & Fabric Filters In

Service.

BOP: putting into operation all BOP systems as Power Plant normal operation

1200t/h x 350MW, Master Controler Fallow,LP&HP Heaters Auto Mod Test,Vacuum System/Condenser & LP/HP Bypass. Auxiliary Steam & Gland Sealing.

Condensate Recovery System,CEP System/Deaerator/BFP & Boiler Feed Water

IA/PA compressor unit and Air dryer system,Sea Water System.

Sea Water Intake & Filtration System,Hypochlorite System. Fire Fighting

System, Closed Cooling Water System, Demineralized Water Unit, All

storage tanks .

RAW WATER System, Demi Water System,Waste Water Treatment Unit,Clean Water

And also all utilities system and Demi Plant.etc

Responsible for all Commissioning Operation project program:

Mill start-up,First COAL on Boiler, First Synchrotron STG,Steam Turbine

Synchronization - start with the rolling of the steam turbine and

synchronization of the plant with the national grid.

First Steam to Turbine, Bypass Operation Test, Condenser Vacuum Test

Steam Blowing: following next steps of the plant commissioning starting

with the Steam Blowing Piping as: Main Steam Piping System,Hot Reheat

Piping system,Cold Reheat Piping system,Auxiliary Steam Piping, HP Bypass

Valve, Extraction Steam piping system for HP Heatars, Extraction Steam

piping system for LP Heaters,Clean Drain System, Process drains&vents

HP Turbine, IP Turbine,LP Turbine,Condensing System, Steam Turbine by-pass

System Steam Generator Blow-Down (Boiler Blow-Down)Boiler Dry Out,Boiler First Firing,

Boiler Leak Test, Boiler Preservation, Boiler - Chemical Cleaning,

Permanent Energization

First Energization - Back-up transformer.

In the period September 2011 - January 2012, I worked as a replacement -

Commissioning Shift Supervisor :Responsible for all Commissioning

activities flushing/blowing, reinstatement of piping components and local

instruments, leak test, motor run, machinery run, static equipment

inspections, cleaning, internals installations, box-up according whit the

procedures, in conformity with the safety rules and the instructions of

Commissioning Manager .Fully responsible for the Operations of Power

Plant during duty shift periods, coordinating the DCS Operator and all the

Fild Operators. Issues PTW (permits to work) and responsible for the safety

condition to workplace also check the safe conditions for maintenance teams

before issuing the Permit to Work.

Period: Aug 2010 - November 2010

COMPANY: SADELMI S.p.A. Busi Power

LOCATION: Panama

PROJECT: Bahia Las Minas Repowering Project,Coal-Fireing POWER PLANT

POSITION: Commissioning Operator Shift in Charge

Summary :

Reporting to Power Plant Project Manager and Commissioning Manager, fully

responsible for the Operations of Power Plant during duty shift periods.

Responsibilities :

Fully in charge of power plant operations for duration of duty period

Manage and lead Operations Shift Group

In conjunction with Operations Superintendent ensuring the safe, reliable,

environmentally and commercially efficient operation of the plant

Proactively promote the continuous development of Operations Shift Group

technical knowledge and competencies during the mobilization, commissioning

and operational phases of the power plant.

Responsible for load Ansaldo Coal Boiler BMCR 500t/h. 95bar. 516 C -

Alstom Mills - DCS Symphony 7 ABB

Responsible for load of 3 STG - 40 MW, 91 bar MAIN STEAM, 120 flow - per

STG. Implement the preparation for BOP & Auxiliaries, signals check to DCS,

interlocks test. Boiler Start up & Turbine synchronized until 30% of

load(permissive condition to start coal firing) Alstom SM 18/11 Bowl Mills

with static classifier 23t/h. Instrument &signals to DCS check interlocks,

manual & auto start/shut down by sequence. Boiler starting and testing

with mixed firing,15% up to 100% of mill load. Mixed firing and transfer

from liquid fuel to coal fuel,3 mills in service. Running interlock manual

& sequence test for mills at minimal load. Full mill load testing &

measurements.

Adjusting the parameters of equipments, testing and adjusting the

parameters of process control according with logic description &diagram in

collaboration with DCS software engineers for BPS, BMS, Plant Coordinator

system 3 modes(Turbine follow, Boiler Follow, Coordinate ),etc.

Period: Mar 2010 - Aug 2010

COMPANY: SADELMI S.p.A. Busi Power

LOCATION: Panama

PROJECT: Bahia Las Minas Repowering Project,Coal-Fireing POWER PLANT

POSITION: Commissioning Control Room Operator

Ansaldo Coal Boiler BMCR 500t/h. 95bar. 516 C - Alstom Mills - DCS ABB.

Check logic controls and interlock according logic diagram and

modification.

Check all logic controls and interlock from DCS.

Confirm correct function of the system .Test for Protocol-Box-up : Air

Compressors, Cooling Water Pumps,Light Oil System Pumps, .BFP, Burners,

ID Fan, FD Fan, Primary Fan, Sealing Fan - Mills, Flame Detector Cooling

Fan, Coal Mills, Coal Feeder,lubrication and cooling pumps Mills system,

Hydraulic Pumps Mills System. Coal Handing, Bottom Ash System, screw,

chain & rubber conveyors, Over belt Electro Magnetic Separator, Dedusting

System,Flay Ash System, Electro Precipitator System. Cooling Water Pumps

for Webcam. Steam Air Heater, Dumpers Test %. All Control Valves Test %.

Dynamic effects during Blowing out. Boiler Start up for Blow Out procedure

several times according to the plate test result. Boiler Preservation,

Start-up and Shut-down Boiler procedure. DCS Symphony 7 ABB Coal Fierd

Plant

Boiler Start up with Light Fuel Oil firing in manual mode by sequence step

by step. Shift operation coordinator & Training the client's DCS & Field

Operators step by step according with the project planning.

Period: Feb 2009 - 2010 Feb

Position: Turbine Board Operator

Company & Location: BONATTI - DIETSMANN; Mellitah Gas Plant - Libya

Responsibilities:

Local consultant for the customer on issues of engineering, service on test

rig units, new product introduction, support of turbine control development

department.

Also, on the job I trained the customer Turbine Operators about start-

up/shut-down, operate the installation and physical phenomens.

-OPERATION ASSISTANCE

-WORKING AS A SHIFT INCHARGE ON STEAM TURBINE, Verta-Pro DCS

Operating three Steam Turbine Nuovo Pignone : 25 MW - capacity of 270 t/h -

41 BAR - 345 'C MAIN STEAM; OUTLET STEAM FLOW 270 T/H - 6 BAR - 158 'C.

Verta-Pro DCS

Ensuring the start up operations for the steam turbine s block after shut

down for repairing or accidental breakdown. Through knowledge of the start

up and shut down procedures in normal and emergency situations. Ensuring

the good functionality of the auxiliary installations: feed water, fuel,

steam units, etc. Controlling, during the shift, the entire plant, checking

status of the equipment, adjusting process parameters according to the

products quality. Start up designated equipment items to achieve normal

operating conditions, receiving instructions from shift supervisor to

perform field tasks. Regularly patrolling work area, observing operation

and performing routine and non-routine checks, inspections, instrument

readings, watching for irregularities such as leaks. Monitoring rotating

machinery, regularly checking bearing temperatures, vibrations,

lubrication, and noting standby machines in operation, reporting and

correcting abnormal startup and operating conditions to prevent damage to

equipment.

Period: 2007 FEB - 2009 FEB

Position: Turbine Control room operator

Company & Location: BUCHAREST - SOUTH POWER PLANT - ROMANIA

Responsibilities: at Oil&Gas Fiered Plant

Monitoring and recording the operating parameters, follow the normal

operating procedures FOR SKODA STEAM TURBINE 125 MW - 140 BAR -

530' C MAIN STEAM,25 BAR HOT REHEATER,530 TEMP,-0.8 CONSENSSER

VACC -DOING START UP & SHUT DOWN TURBINE OPERATIONS FROM

CONTROL DCS ( Ovation-Power plant DCS),MAINTAINING PARAMETERS

FOR GOOD OPERATION TURBINE IN LOAD, FOR ALL EQUIPMENTS IN

SERVICE AND STAND BY.SUPORT all emergency situations.

Period : 1996 DEC-2008 JUN

Position: Commissioning Turbine Mechanic &Operator

PROJECT: REVAMPING/REENGINEERING

Company & Location BUCHAREST - SOUTH POWER PLANT- ROMANIA

Responsibilities:

1996-2008 - DURING THE SUMMER, I ALSO WORKED AS DETACHED IN CAPITAL

MAINTENANCE & REVAMPING/REENGINEERING, ACHIEVING EXPERINCE IN MECHANICAL,

MAINTENANCE, PRE-COMMISSIONING, COMMISSIONING, STARTUP, AND OPERATION IN

POWER PLANT FACILITIES:

Involved in pre-commissioning, commissioning, startup in power plant

facilities: Piping system pre-commissioning works, air blowing, flushing,

cleaning, hydro testing, P&ID line walk, leak test, etc. Performing

commissioning activities for turbine (SKODA 125 mw - 140 bar - 530' c main

steam, 25 bar hot re-heater, 530 temp, -0.8 condenser vacuum). Inspecting

and commissioning new rotating equipments including vertical and horizontal

centrifugal pumps, centrifugal and reciprocating compressors, to verify

eccentric rotor & bearings, HP Thrust Position, making on rotary: no load

run test/load test/full load run test. Boiler feed pump (BFP) auxiliary

lube oil/main pump lube oil and hydraulic line flushing and commissioning.

Boiler, turbine-generator and feed water systems pre-commissioning,

commissioning works, hydro test, boiler chemical cleaning, steam purge,

floating safety valves, turbine lube oil flushing, condensate extraction

and LP-HP feed water system flushing, CEP, HP & LP Heater, Gland Sealing on

pumps and valves, cleaning and blowing the Condenser etc. Fire protection

system, water and waste water system pre-commissioning, commissioning and

operating throughout projects. Commissioning activities for instrument air

compressors type HAFI 100 t/h - 10 bar (compressor-receiver tank-dryers-

filters), 6 steam extractions, except # 2, regulated by one diaphragm, to

low pressure heat exchanger under vacuum and all auxiliaries equipments.

HAVING A GOOD BEHAVIOR WITH SUPERIORS IN CHARGE AND MAINTANING AN

PARTENERSHIP WITH THE COLLEAGUES

Period : 1996 DEC-2007 FEB

Position Turbine Operator

Company & Location BUCHAREST - SOUTH POWER PLANT- ROMANIA

Responsibilities:

. OPERATOR FOR - STEAM TURBINE SIDE TYPE SKODA 125 MW - 140

BAR - 530' C MAIN STEAM,25 BAR HOT REHEATER,530 TEMP,-0.8

CONSENSSER VACC,

. DAILY ROUTINE CHECK AND READINGS OF EQUIPMENT FUNCTIONING

AND STAND-BY,LIKE- Boiler feed pump (BFP),CONDESSATE

EXTRACTIONS PUMPS, COOLING WATER PUMP,,CONDENSSER VACUM PUMPS

&GLAND STEAM SEALING,HP & LP STEAM BY-PASS VALVES,

COOLING TOWERS,MECHANO-HYDRAULIC GOVERNOR SYSTEM, GEN-SEAL OIL

SYSTEM PUMPS, MOT(main oil tank),START-UP OIL PUMPS, LUBRICATION

OIL COOLERS, STATIONARY OIL PURIFIER, REGENERATIVE WATER

CIRCUIT LP-HEATERS AND HP-HEATERS, INSTRUMENT AIR COMPRESSORS

TYPE HAFI 100 T/H - 10 BAR (COMPRESSOR-RECEIVER TANK-DRYERS-

FILTERS), 6 STEAM EXTRACTIONS, EXEPT # 2,REGLATED BY ONE

DIAFRAGM,TO LP HEAT EXCHANGER UNDER Vacuum.& ALL AUXILIARES

EQUIPMENTS. WEEKLY CHANGE OVER EQUIPMENTS.TAKE DATA OF PLANT UNIT

AND EQUIPMENT CONDITIONS IN FIELD OPERATIONS, START/STOP AND

SWITCH THE ROTATING MACHINERY AS PER OPERATING SCHEDULE OR

MAINTENANCE SCHEDULE OR CHECKING-UP RESULTS.

COMMISIONING FOR UNIT AFTER ANNUAL MAINTENANCE, COOLING WATER

CIRCUIT AND PROTECTIONS TEST.FEED WATER CIRCUIT,ALL ROTATIVES

EQUIPMENT PROTECTIONS TEST,UNIT PROTECTION & INTERLOCK TEST,

PNEUMATHIC N.R.V TEST,BEARINGS LUBRICATION/GOVERNOR OIL

PROTECTIONS TEST,STEAM FREEDOM TEST, MECANO-HYDRAULIC GOVERNOR

SYSTEM TEST.

. TAKING INTO ACTION IN EMERGENCY CASES,AND BLACK OUT CONDITIONS.

. FOLLOWING THE SUBCONTRACTORS WORKS AND TAKING OVER OF

THE EQUIPMENTS AFTER MAINTENANCE

. THERMAL CIRCUIT FOR CITY HEATYING SYSTEM, LOW PREASSURE HEAT

EXCHANGERS UNDER Vacuum WITH STEAM SUPLLY FROM # 2 & # 3 TURBINES

EXTRACTIONS. WHIT 3 PUMPS FOR THE CONDESSATE. SUPPLY & BOOSTER PUMPS

STATION FOR CITY CIRCUIT OF HEATED WATER

. PUMP HOUSE STATION FOR FIRE FIGHTING WATER CIRCUIT OF THE PLANT

TRAINING : BUCHAREST SOUTH POWER PLANT

. 1997 - LOW PREASSURE BOILERS HEATING WATER - 1 year

. 2002 - MECHANICAL MAINTENANCE FOR VALVES ( gland sealing

),PIPES LINE CONNECTIONS HP & LP, PUMPS GLAND

SEALING,LUBRICATION OIL STRAINERS CLEANING OF BFP's - 1 year

. 2013 - Polytechnic University of Bucharest,

Faculty of Mechanical Engineering

and Mechatronics.

Construction and Operation of Boilers

to alternative fuels.

QA/QC - Operator responsible for the supervision and technical inspection

of facilities

. 2013 - National Company for Control of

Boilers and Hoisting

Operator for high pressure Boilers Diploma,Authorization Boiler license

Class A Group 3

EDUCATION: . Upway Consulting Grup Bucharest - Project Manager Diploma

2013

. SPIRU HARET UNIVERSITY OF SOCIOLOGY-PSIHOLOGY - BUCHAREST

2003-2008

GRATUATED DIPLOMA 2008

. ENERGETIC TECHNICAL preUNIVERSITY - BUCHAREST 1999 - 2001

GRATUATED DIPLOMA 2001

SPECIALIZATED IN ELECTROENERGETICIAN POSITION IN THE MINISTRY

OF EDUCATION PROGRAM EU PHARE - VET RO 9405

. ENERGETIC Technical College - BUCHAREST 1996 - 1999

HIGH SCHOOL - GRATUATED DIPLOMA 2000

. ENERGETIC Technical College - BUCHAREST 1993 - 1996

DURING THE YEARS OF PROFESSIONAL SCHOOL,I DID TRAINING FOR 3

DAYS/WEEK IN SEVERAL POWER PLANTS

SPECIALIZATED IN MECHANICAL MAINTENANCE OF STEAM & GAS

TURBINES

PROFESSIONAL SCHOOL - GRATUATED DIPLOMA 1996

Computer Literacy

Operating Systems : General & Graphics Applications . Microsoft Office

Word, Verta-Pro DCS, Ovation-Power plant DCS, DCS Symphony 7 ABB, Invensys

Coal Fierd Boiler DCS Foxboro - Mark VI GE Steam Turbine DCS, FGD Siemens

DCS.

Personal Nature: Dynamic, team worker as partnership, seeking to

improve skills experience in any work place

SIGNATURE OF CANDIDATE.

Micu Gheorghe