John L. Dorrell III
Wittmann, AZ 83561
Mobile 623-***-****
********@*****.***
Professional Summary
Over 25 years experience as a detail oriented self-motivated team player
while performing the duties of a planner/scheduler of engineering,
procurement, construction, start-up, and outage management. I have held the
following positions: Project Controls Manager, Senior Project Control
Engineer, Planner/Scheduler, Senior BOP System Engineer, and Start-Up
Engineer. Developed master project schedules, 4, 6 and 12 week rolling
schedules, schedule WBS and activity codes, performed earned value analysis
and mentored personnel in the use of Primavera. Developed and maintained
resource and cost loaded schedules, using the Critical Path method.
Skills / Certifications
Experienced using various scheduling software during performance of project
control duties. Scheduling software used has included Primavera Products;
(P6, P5, P3e/c, P3, and Suretrak), I have used Microsoft Word, Excel, and
Access software in support of scheduling systems.
Employment History
CBI -Stone & Webster
5/28/13 - 6/14/13
San Onofre Nuclear Generation Station (SONGS) Project scheduler
for PMO. Developed a schedule for Future Force activities and developed a
schedule for the Temporary Aux Boiler Removal. Power plant was shut down for retirement Scheduling software used was P6.
Entergy at Arkansas Nuclear One Russellville, AR
Mar 13 - Apr 13
Outage scheduler assigned to Siemens as night shift scheduler for the
stator exchange project.
Scheduling software used was P6.
Entergy at Waterford3 Killona, LA
Oct 12
- Nov 12
Outage night shift war room scheduler during the 1R18 refueling outage.
Entered schedule updates and changed logic as needed and requested by
management. Produced 12 hr. look ahead plots for both day and night crews.
Scheduling software used was Primavera P6
Shaw - Stone & Webster
Mar 10 - Feb 12
San Onofre Nuclear Generation Station (SONGS)
Jun 10 - Feb 12
Project scheduler developing schedules from estimates and the input of
craft superintendents. Updated schedules on a daily basis. Attended daily
status meeting held by the client.
Callaway Nuclear Plant
Mar 10 - May 10
Outage scheduler during RF-17 Responsible for gathering status for the
various Shaw crafts and ensuring that updates were entered correctly in
Primavera Activities Update Module (PAUM). Generated the status reports
which were used by the Shaw crafts for the updates. Updated the Ameren
bulk work manager on a nightly basis. Was the Shaw Outage Command Center
(OCC) relief, coordinating work as required.
TXU - Luminant Mining - Martin Lake Mines, Tatum, TX (Under contract)
Feb 08 - Sep 09
Senior Planner/ Scheduler Responsible for the creation and maintenance of
drag line outage schedules at the following mines; In 2008 Beckville
(D31, D33), Tatum (D35), Oak Hill (D34, D36). In 2009 Beckville (D31,
D32, D33), Oak Hill (D34), Tatum (D35), and Big Brown (D11) Mines. WBS was
developed for the outage schedules. Daily status meeting were held during
the outages. The schedule was updated on a daily basis and a 4 day look
ahead was produced and distributed. Schedule developed using the CPM,
Scheduling software used was Primavera P5.
San Onofre Nuclear Generating Station, SONGS, (Under contract)
July 07 - Jan 08
Senior Planner/Scheduler assigned to the outage group for the 2RC15 outage.
Responsibilities included the creation of schedule activities for the CW,
FW, SW systems, and the Turbine/generator related work which included an
exciter replacement. This required validating the resources and duration
as listed in Mosiac. During the outage was responsible for updating the
schedule with status as provided by the various work group general foremen.
Scheduling software used was P3/E
Louisiana Energy Services, National Enrichment Facility Eunice, NM
(Under contract) Jan 07 - Jun 07
Project Control Engineer - planner/scheduler. Duties include the
maintenance of the schedule for the new switchyard, developing the
excavation work for the site. Developed the civil/structural, & mechanical
construction & erection schedules for the two main buildings. Developed
the underground utilities schedule for the site. Scheduling software used
is Primavera P3.
Hoffman Corporation, Hoffman Construction Chandler, AZ
Mar 05 - Jan 07
Project scheduler for the Intel Fab 32 project. Developed the Programming
schedule, which evolved into the project schedule. Maintained the EPC
schedule and added activities with correct logic as design changes and new
scope were approved. Maintained the project scheduler for Intel's Fab12C
300mm conversion and for Post Fab12 Added Scope. Monitored and updated the
schedule. Produced 4-week lookahead schedules for the CM's. Notifying
management if activities were slipping and which items were on or near
critical path. The critical path method was used for this schedule.
Scheduling software used was Primavera P3E/C.
Omaha Public Power District - Fort Calhoun Station (Under Contract)
Jan 05 - Mar 05
Planner / Scheduler during the condenser tube replacement outage. Primary
duties included verifying status of the craft personnel by walking down the
work activities several times a day. Chaired the evening status meeting.
Notifying management if activities were slipping and which items were on or
near critical path. The critical path method was used for this schedule.
Scheduling software used was P3E/C.
Duke Energy Moss Landing Power Plant, Moss Landing, CA (Under
Contract) Nov 04- Nov 04
Developed & maintained the schedule for Gas Turbine compressor disassembly,
inspection & repair for 4 unit GE frame-7 co-generation power plant. Units
2, 3 & 4 were dissemble, inspect & reassembly while unit 1 was a complete
disassembly and rebuild the gas turbine. This was a short term contract
assignment (2 weeks) which lasted thru the reassembly and back on line for
units 2, 3, & 4.
AmerenUE, Callaway Nuclear Plant, Fulton, MO (Under contract)
Aug 04 - Oct 04
Assigned to DCS Project as lead scheduler for the following projects;
Plant Computer Upgrade, Group 2 & 3 of Control Room Simulator, Portland
River Water Sampler, Supervisory, and Fiber Optic Backbone. All schedules
are updated using CPM and are resource loaded. Scheduling software used
was P3.
Kansas City Power & Light (Under Contract)
Feb 04 - Aug 04
La Cygne Generating Station, La Cygne, KS Developed and maintained MS
Project schedule for the unit one spring 2004 outage. This schedule was
maintained using the critical path method. Developed the unit two fall
2004 outage schedule, using Primavera P3. This outage was cancelled due to
budget restraints.
Irwin Industries, Long Beach, CA (Under Contract)
Dec 03 - Feb 04
Navajo Generating Station, Page, AZ Developed an outage schedule for
the hot reheat pipe replacement and a separate schedule for the economizer
replacement.
Shaw Constructors Inc, (Under Contract) Sep 01 - Jun
03
Harquahala Generating Plant, Harquahala Valley, AZ Developed the
detailed construction and startup schedule for a 1500MW 3 x 3 x 3 combined
cycle electric generating plant utilizing Siemens/Westinghouse 501G
combustion turbines and NEM HRSG's. Interfaced with construction
management; Siemens-Westinghouse, subcontractors and the client on a daily
basis. Held weekly progress status meetings updated and maintained the
schedule. Schedule was maintained using the Critical Path method and new
activities added as necessary. Produced 12 week, 6 week and 3 week look
ahead schedules. Schedule has been resource loaded as necessary.
Titan Constructing & Leasing Co. (Under Contract)
May 01 - Sep 01
Perryville Power Station, Perryville, LA Cost & Scheduling
Engineer during the mechanical construction
of a two x one GE Frame 7 combustion turbines and NEM HRSG's.
American National Power, Houston, TX (Under contract)
Oct 99 - April 01
Hays Energy Limited Partnership, San Marcos, TX Project Controls Manager
during the construction of a four (4) unit gas fired $550M electric
generation facility and a zero liquid discharge plant. Duties include the
schedule analysis of the construction schedule, developed the detailed
schedules of 5 interface contracts and the coordination between owner
contracts and the prime contractor. Developed the commissioning /start-up
schedule and fully integrated this schedule into the construction/erection
schedule. CPM used for all updates and analysis. Produced grafts and
charts as required by project management. Scheduling software used for
this assignment was Primavera P3, & MS Project.
Phillips, Getschow Co., Colquet, MN (Under contract)
Jun 99 - Aug 99
American Crystal Sugar, East Grand Forks, MN Project Scheduler for
mechanical contractor during the 1999 overhaul campaign. Developed and
maintained the outage schedules for four separate sugar production plants
and produced man-hour (earned value) plots/curves during their maintenance
overhauls. Scheduling software used was Sure Trak.
PSE&G, Salem Nuclear Power Plant, Salem, NJ (Under contract)
Apr 99 - Jun 99
Senior Scheduler assigned to the on-line scheduling team for Salem Nuclear
Power Plant during the spring 1999 outage. This schedule was a 10-week
rolling schedule. Scheduling software used was P3.
Perry Nuclear Power Station, Unit 1, Perry, OH (Under contract)
Mar 99 - Apr 99
Outage Scheduler during RF07 outage. Maintained and updated the mechanical
contractor portion of the outage schedule on a daily basis and developed
detailed fragnets of major work activities. Scheduling software used was
P3.
Kiewit Industries, Omaha, NB
Nov 98 -
Jan 99
Tenaska Frontier Generating Station, Shiro, TX
Project Scheduler: Responsible for development and maintenance of the
master EPC Schedule of a 3 x 1 cogeneration project. Included in this
schedule was the Engineering, Procurement, Construction & Start-up
scheduled through commercial operation. This schedule was resource and cost
loaded. The Critical Path method was used for all schedule updates.
Furnished plots and curves and earned value reports as required by
management. Scheduling software used was P3.
Millstone Nuclear Power Station, Waterford, CT (Under contract)
Sep 98 - Nov 98
Sr. Scheduler: Unit #2 Work Planning & Outage Management, Outage Recovery
Team, Responsible for development and maintenance of the Licensing and
Regulatory Commitments portion of the master schedule. Interface with
various department heads and obtaining data required for the weekly update.
The Critical Path Method was used for all updates of the schedule.
Scheduling software used was P3.
Clinton Power Station, Clinton, IL (Under contract)
Aug 98 - Sep 98
Sr. Outage/Maintenance Scheduler: Responsible for the Main Control Room
Deficiency and the mechanical portion of the master schedule. Scheduling
software used was P3.
Westinghouse Electric Corporation PGBU, Orlando, FL (Under contract)
May 97 - July 98
Sr. Project Control Engineer Responsible for the development of proposal
schedules and the development and maintenance of project schedules from
conception through completion of the project. Developed and maintained the
outage during two 501F combined cycle plant outages, and the integrated
project schedule from conception to Completion of the project
(Engineering/Design, Procurement, Construction, Start-up & Commissioning
through turnover to the client) using the CMP for a Multi-Million dollar
project. Scheduling software used was P3 and MS Project.
Millstone Nuclear Power Station, Waterford, CT (Under contract)
Feb 97 - Apr 97
Sr. Planner/Scheduler: During the unit #1 shutdown. Responsibilities
included tracking the status of all water system work activities. Work on
unit #1 was stopped and all moneys diverted to unit #3. Scheduling
software used was P3.
Jacob's Engineering Group, Inc. Portland, OR
Jul 96 - Feb 97
Project Planner/Scheduler: SEH - America, Phase II, and Vancouver, WA
Produced and maintained the integrated Master Schedule (EPC) for the
Construction of the $350M+ Phase II Project.
This integrated schedule consisted of over 25 separate construction
contracts (subprojects), the procurement of all
Equipment and the engineering design activities required for completion of
construction. Scheduling software used
was P3, Sure Track and MS Project.
Technology Design & Construction Co. Portland, OR
Aug 94 - Jul 96
Project Scheduler: Fujitsu GMD Fab 2, Gresham, OR
Oct 95 - Jul 96
Produced schedule for the various sub-projects and integrated them into the
master schedule using the CPM. I produced spreadsheet to track the
equipment and system startups. I was responsible for the maintenance of
the Site Observation Report. Scheduling software used was P3 and MS Project
Startup Scheduler: Intel's Fab 12, Chandler AZ
Apr 95 -Oct 95
Produced various spreadsheets and produced graphs showing the plan of
record vs. the actuals for mechanical and electrical startup schedules in
the FAB and CUB buildings. Produced spreadsheet and developed graph
showing the Final room sign-off schedule.
Project Scheduler: Intel's Fab 11, Rio Rancho, NM
Aug 94 - Apr 95
Produced schedules using the CPM for various team leaders (Ultra Pure
Water, VOC Abatement, Solvent Waste,
HF Waste Treatment and KD100). Integrated these schedules into the master
schedule and responsible for the maintenance of the Central Utility
Building portion of the master schedule. Software used P3 and MS Project.
Public Service Electric & Gas of New Jersey (Under contract)
Oct 93 - Apr 94
Senior Scheduler: System Maintenance Division, Hope Creek Nuclear
Generating Station. Spring 1994 refueling outage, developed the turbine
overhaul (including all related loaded schedule using the CPM. Integrated
this schedule into the master schedule and maintained the schedule
throughout the outage. Scheduling software used P3.
Dow Chemical, USA, Houston TX (Under contract)
May 92 - Mar 93
Senior Scheduler: Engineering & Construction Services. Produced the
engineering design and development, the procurement schedule, and the
construction schedule for a $259M project using CPM. Produced bar charts
and time-scale drawings as required by the project engineer, the project
manager and construction management. Scheduling software used was Open
Plan.
Nelson Industrial Steam Co., Westlake, LA (Under contract)
Oct 91 - Apr 92
Senior Scheduler: Maintained and integrated 23 different sub-contractors'
schedules into the master schedule, using the critical path method.
Prepared reports and graphics, as required, during construction of a two-
unit $250M coke and limestone fired co-generation electrical power plant.
Scheduling software used P3 & FH.
Texas Utilities, Comanche Peak Steam Electric Station (Under contract)
Apr 91 -Sep 91
Senior Planning/Scheduling Engineer: Developed detailed fragnets for
engineering design group and integrated them into the project schedule,
which contained the construction and start-up schedules, (both resource
loaded) using CPM. Provided reports, charts, and plots to assigned groups
ensuring accurate reflection of department completion status. Prepared and
distributed the Design Modification Package for the weekly management
meeting. Scheduling software used PRIMUS.
Houston Lighting & Power (Under contract)
Sep 90 - Mar 91
South Texas Project, Bay City, TX Senior Scheduler/Planner (Engineer A):
Planned and maintained the LLRT, ILRT, ST and turbine overhaul
schedules, utilizing CPM for the 1st refueling outage of Unit #2 and the
2nd refueling outage on unit #1. Produced graphs and charts as required by
the engineering dept., maintenance, and management. Scheduling software
used was Primavera P3.
Arizona Public Service Co., Phoenix, AZ
Oct 81 - Sep
90
Palo Verde Nuclear Generating Station Planner/Scheduler, Outage System
Engineer, and Startup Engineer: Planned, scheduled, and reviewed input and
logic ties for accuracy using the CPM. Outage planner/scheduler during
several refueling outages. Evaluated work requests and produced
maintenance work orders and reports. Generated plots, charts and time-
scale drawing as required by project demands. Startup engineer on unit #1,
responsible for all water and chemical systems. Scheduling software used
was PRIMUS.
Magma Copper Co., Superior, AZ
Apr 80 - Oct
81
Lead Maintenance Machinist: Directed and coordinated maintenance personnel
(machinist, boilermakers) in the repair, manufacture and maintenance of all
mechanical related equipment in support of underground mining operation.
Eberline Instrument Co., Santa Fe, NM
Feb 79 - Apr 80
Journeyman Machinist: Manufactured and assembled-machined parts for
radiation detection devices ensuring parts
were machined to blueprint specification. Trained new employees to operate
engine lathes and milling machines and how to read and understand
blueprints.
Union Electric Co., St. Louis MO
Aug 76 to
Feb 79
Plant Mechanic/Machinist: Labadie Power Plant, Labadie, MO. Repaired and
maintained mechanical equipment at a four unit 1520MV fossil (coal) fired
electric generating plant.
McDonnell Douglas Corp., St. Louis, MO
Jun 63 to Aug 76
McDonnell Aircraft Corp. Journeyman All-Around Machinist: Served a four-
year (8000 hr.), machinist apprenticeship operated all machine shop
equipment, producing finished machined parts in the aerospace and
commercial industry. Lead machinist, inspecting, testing, approving or
rejecting new numerical controlled tapes and direct numerical controlled
manufactured parts.
Military: Served four years in the United States Navy. Earned an
Honorable Discharge.