R.M.J.S.B. Rathnayake, March **, ****
Randenigama,
Nikaweratiya,
Colombo,
Sri Lanka
Mobile: 009**-*********/009*-*********
Email: ac8whc@r.postjobfree.com
Dear Sir/Madam,
APPLICATION FOR THE POST OF Sr. QUANTITY SURVEYOR
I would like to submit my application for the above post in your esteemed company and your kind perusal and consideration. I attach here with the particulars of my resume and look forward to receiving a favorable response as I’m looking for an opportunity to get well set in the carrier for long term. I am holding Engineering Council Graduate Diploma which is comparable to Level 6 Graduateship (GCGI) and Associateship (ACGI) in Civil Engineering conducted by the Engineering Council, UK and the National Diploma in Technology (NDT) in Civil Engineering which is conducted by the University of Moratuwa, Sri Lanka. Further Advance Level has been completed in Mathematics. In particular, I have now been completing more than Thirteen (13) years of comprehensive professional experiences in Quantity Surveying and Engineering fields including around Eight (08) years of working experiences in Middle East as a Quantity Surveyor. I would appreciate, if you could grant me an opportunity to discuss further with you and to provide further information on my particulars. If I am selected, I assure that I shall endeavor with my best in performing my duties to the utmost satisfaction of all my superiors and to the organization. I am an effective team player and a capable professional who is able to perform the duties with minimum supervision. I can be reached any time via the above mentioned cell phone and/or email. Thank you for your consideration.
Yours Sincerely,
R.M.J.S.B. Rathnayake,
Page 1 of 4
R.M.J.S.B. Rathnayake Sr. Quantity Surveyor
N2443495
CURRICULUM VITA
POST OF Sr. QUANTITY SURVEYOR
R.M.J.S.B. RATHNAYAKE Mobile: 009********** / 009*********** Address: Email: ac8whc@r.postjobfree.com
Randenigama,
Nikaweratiya,
Colombo,
Sri Lanka.
1- PERSONAL DETAILS
Full Name : Rathnayake Mudiyanselage Jeewantha Samansiri Bandara Rathnayake N.I.C. Number : 801553222V
Passport Number : N2443495
Date of Birth : June 03, 1980
Nationality : Sri Lankan by Decent
Sex : Male
Marital Status : Married
CARRIER PROFILE
The above 13 years of working experiences in Quantity Surveying (Civil & MEP) and Engineering in Sri Lanka and Middle East.
2-PROFESSIONAL QUALIFICATIONS
2.1- Engineering Council Graduate Diploma which is comparable to Level 6 Graduateship (GCGI) and Associateship
(ACGI) in Civil Engineering conducted by the Engineering Council, UK. 2.2- National Diploma in Technology (NDT) in Civil Engineering, conducted by Institute of Technology, University of Moratuwa, Sri Lanka.
2.3- Advance Level Examination (2000) in Mathematics. 3-SKILLS & STRENGTHS
Experiences in Civil & MEP in the field of Building construction, Road Construction, Grid Substation, Mini Hydro Power plant, Water Supply and Oil & Gas projects including Pipe lines, Steel Structures & Fireproofing.
Knowledge of conditions of contract, specifications etc... & their implementation.
Preparation of Monthly Valuation.
Take off & preparing of Quantity sheets.
Evaluation of additional Works and arranging the all substantiation documents.
Finalize the Final Account with all required contract documents.
Reviewing, negotiation, assess and certifying of the Contractor’s payments and variations.
Preparation of reports for the uncertified value incorporating the Engineer’s comments and resolve the issues affected for the payments.
Preparation of internal cost/value & Budget reporting.
Preparation of Cash flow forecasting and S-curve.
Managing of project insurances, Bonds, Warranties.
Drafting the Contract letters.
Conduct and attend to the meetings.
Managing of construction material with Procurement plan, Approved vendor list, MAR & MIR.
Monitoring the project progress with master program. Additional Skills & Strength;
Familiar with the Conditions of contract for construction of UAE (FIDIC-1999) & Oman (WHITE BOOK).
Familiar with the Principle of Measurement, SMM7,NRM.
Multi lingual (English and Sinhalese), good communicator both in writing and oral with negotiating skills.
Well-developed computer skills in MS Office and Auto CAD-2D-3D & SAP System. Page 2 of 4
R.M.J.S.B. Rathnayake Sr. Quantity Surveyor
N2443495
4-PRESENT EMPLOYMENT
4.1- Organization : Arabian Construction Company in Abu Dhabi Duration : 09 Months - July-2018 to Up to date.
Position : Sr. Quantity Surveyor
Project : Al Dabb’iya Surface Facilities Phase III (Oil & Gas Project) Project Value : USD 322.49 Million.
Client : Abu Dhabi Company for Onshore Petroleum Operations (ADCO) Ltd. Main Contractor : Tecnimont Spa
Description of the Project;
EPC Contract; Construction of Central Processing Plant and the Works consisted with Civil, Structural steel, Fireproofing, Electrical, Mechanical, Instruments & Pipe lines etc.. 5-PREVIOUSEXPERIENCES
5.1- Organization : Arabian Construction Company in Abu Dhabi Duration : 39 Months - June-2014 to Up to August 2017 Position : Quantity Surveyor
Project : Strategic Water Storage/Recovery Project Project Value : AED 1,611 Million
Client : Abu Dhabi Water & Electricity Authority ('ADWEA') Consultant : Deutsche Gesellschaft fur Internationale Zusammenarbeit (GIZ) GmbH / Dornier Consulting GmbH (Dco).
Description of the Project;
EPC Contract; Engineering Design, Supply of materials and Equipments, Construction, Installation, Testing, Pre-commissioning, Commissioning, Handover & Warrant the Works during the Maintenance period for the following Works.
Infiltration & storage of 5,936 MIG of Desalinated Sea Water in a shallow dune sand aquifer located in the Western region of the Emirate of Abu Dhabi, and subsequent recovery of the infiltrated DSW for emergency supply of Abu Dhabi.
The Works consisted with Civil, Steel Structures, Electrical, Mechanical, Instruments& SCADA monitoring system including Infrastructure Works such as Pipe lines, Infiltration basins, Recovery Wells, Monitoring Wells, underground & above ground Tanks, Asphalt concrete road works with drainage system and Pumping station’s building works.
5.2- Organization : Sierra Construction Co. Ltd. In Sri Lanka Duration : 18 Months - December-2012 to June-2014
Position : Quantity Surveying cum Engineering
Project : Grid Substation
Project Value : USD 17.0 Million
Client & Consultant : Ceylon Electricity Board
Main Contractor : Siemens Eng.
Description of the Project;
Turnkey Project; Construction of Grid Substation project and Works consisted with the Equipment foundations, Retaining walls, Control building, Steel Structure Building, Guard house, Earth filling by approved gravel, Drainage system, Cable trenches, Chain link fence, Barbed wire fence, Asphalt Concrete road works etc... 5.3- Organization : VV Karunarathna Construction Company in Sri Lanka Duration : 09 Months - April-2012 to December-2012 Position : Quantity Surveying cum Engineering
Project : Road Construction Project at Kandy
Project Value : LKR 765.0 Million
Client & Consultant : RDA
Description of the Project;
Re measure Contract; Asphalt road project and the Works consisted with Bridges, Culverts, Embankment, Retaining structures, Drainages, Shoulders, Sub Grade, Sub base, ABC, Binder course, etc... Page 3 of 4
R.M.J.S.B. Rathnayake Sr. Quantity Surveyor
N2443495
5.4- Organization : Al Amur QS Consultants in Muscat-Oman Duration : 31-Months – Nov. 2009 to March-2012
Position : Quantity Surveyor (Civil & MEP)
Project – 1 : New Palace Staff Clinic at Bausher
Project Value : OMR 16 Million
Client : Royal Court Affaire (RCA)
Consultant : National Engineering Office (NEO)
Project – 2 : New Villa at Al Alam Heights
Project Value : OMR 14 Million
Client : Royal Court Affaire (RCA)
Consultant : Al-Hatmy Consultant Engineering
Description of the Project;
Actual and Correct Contract; The Clinic project for the Palace staffs and High luxury Villa project of Royal Court Affaire in Muscat, Oman. The Works consisted with Building Works including high luxury finishing items and Medical system. And also infrastructure Works with landscape & Irrigation system, Drainage system, Water supply system and Road works etc...
5.5- Organization : Al- Suwaidi scaffolding services & and solutions in Saudi Arabia Duration : 10-Months - Sep. 2008 to July-2009
Position : Quantity Surveyor
Location : Head office
Description of the Project;
Scaffolding services for the construction projects. Work in head office; Monitoring of progress and maintaining the materials flow to the projects. Review of Contract’s payments and Certifying. 5.6- Organization : Carillion Alawi LLC (UK Plc) in Muscat-Oman Duration : 18-Months - Feb. 2007 to Aug. 2008
Position : Quantity Surveyor
Project : New complex guest palace at Qasr Al Alam Project Value : OMR 80 Million
Client : Royal Court Affaire (RCA)
Consultant : Cowi LLC
Description of the Project;
Re measure Contract; High luxury Palace Project of Royal Court Affaire in Muscat, Oman. The Works consisted with Building Works including high luxury finishing items and infrastructure Works with landscape & Irrigation system, Drainage system, Water supply system and Road works etc... 5.7- Organization : Wakachiku Construction Co, Ltd in Maldives Duration : 06-Months - May 2006 to Oct. 2006
Position : Site Engineer
Project : Recovery and Development of Causeway
Project Value : USD 50 Million
Funded by : Japan International Cooperation System (JICS) Description of the Project;
Turnkey Project; Causeway project by connecting Three Islands and the Works consisted with road works (DBST method) including Pile Bridge, Culverts, Laying of Geo-textile & Rubble packing for the embankment of roads, Guard blocks, Light poles, Center medium etc... 5.8- Organization : Fumhiko Engineering Company (pvt) Ltd in Sri Lanka Duration : 16-Months - Feb 2005 – May 2006
Position : Site Engineer
Project : Trincomalee – Pulmudai Road Project
Project Value : SRL 35 Million
Client & Consultant : Road Development Authority
Description of the Project;
Re measure Contract; Asphalt road project and the Works consisted with Bridges, Culverts, Embankment, Retaining structures, Drainages, Shoulders, Sub Grade, Sub base, ABC, Binder course, etc.. Page 4 of 4
R.M.J.S.B. Rathnayake Sr. Quantity Surveyor
N2443495
6-Experiences in Apprentice period
6.1- Organization : Squire Mech Engineering (Pvt) Ltd in Sri Lanka Duration : Months-08 - July 2004 – Feb 2005
Position : Technical Officer
Project : Guest House of 100MW Power Plant Project. Project Value : SRL 16 Million
Client & Consultant : Lanka Transformer Ltd (LTL
Description of the Project;
Re measure Contract; Guest House for the Power plant project. The Works consisted with Building works.
6.2- Organization : Road Development Authority
Duration : Months-05 - Feb 2004 – July 2004
Position : Technical Officer
Project : Kotte-Bope Road Project
Project Value : SRL 30 Million
Client & Consultant : Road Development Authority (RDA) Description of the Project;
Re measure Contract; Asphalt road project and the Works consisted with Bridges, Culverts, Embankment, Retaining structures, Drainages, Shoulders, Sub Grade, Sub base, ABC, Binder course, etc.. 7-INTERESTS
Music and Seclusion
8-NON-RELATED REFEREES
1- Mr. Ranjith Gopallawa, 2-. Mr. Daniel Van Heerden, Chief Executive Officer, Sr. Commercial Manager,
Sierra Construction Co. Ltd, Arabian Construction Company, Electrical Division, Abu Dhabi, UAE
Colombo. Tel: +971-********
Tel: +947********
I hereby certify that the aforesaid particulars given by me are true and accurate to the best of my knowledge and belief. R.M.J.S.B. Rathnayake March 26, 2019
Signature Date