Post Job Free

Resume

Sign in

Piping fbricator

Location:
Pakistan
Salary:
70to 80 thousand
Posted:
August 16, 2018

Contact this candidate

Resume:

MUHAMMAD IMRAN

Mob: +971-********* (UAE)

+92-305*******, 313-***-**** (PAK)

Email id:ac6oz2@r.postjobfree.com

CAREER’S OBJECTIVES

Being a committed team player as (PIPING FABRICATOR), want to be a part of a renowned organization, to contribute towards the growth of the organization, based on my expertise and to further my personal capabilities by learning from the new exposure within the structured framework of the organization. Preferred: Oil & Gas Sector, Petro Chemicals, Fertilizer, Piping, Gas processing and production AREAS OF EXPERTISE

1 Project Execution

• Structure Fabricator (CS, SS. FRP)

2 Oil And Gas Sector

3 Planned Maintenance • Rotating Equipments

• Steel Structure & Tanks • Static Equipments

PROFESSIONAL EXPERIENCE

Start carer in Pakistan As Structure Fabricator in February 2005. Working as (Structure Fabricator) in Descon Engineering, Abu Dhabi U.A.E since October-2009.Descon Engineering serves its customers in a wide range of business activities including Engineering, Procurement, Construction, Manufacturing, and Plant Operations & Maintenance. Total Experience: More than 11 years

(More than 05 years in Gulf & 04 years Pakistan)

Previous Project:

Organization National Petroleum Construction Co. Abu Dhabi -UAE Tenure from 09-04-2017 to 10-05-2018

Position Fabricator (Mech) (Piping

Project Process Structure Erection ADMA.

.

Project 7rd:

Organization Dynamic Equipments control company Lahore Tenure From 15, October, 2015 to 05-03-2017

Position Fabricator (Mech) (Piping)

Project Process Piping Erection For NTP Mureed k Lahore.

. Lahore

Project 6rd:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From 8, October, 2014 to 2, August, 2015.

Position Fabricator (Mech) (Piping)

Project Process Piping Erection For Po Project Borouge1-2-3 poly olefin Ruwais

. UAE

Project 5rd:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From 13,April, 2012 to 6, August, 2014.

Position fabricator (Mech) (Piping)

Project Process Piping Erection For Po Project Borouge 3 poly olefin Ruwais

. UAE.

Project 4nd:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From 13,February, 2012 to 12,April,2012.

Position fabricator (Mech) (Piping)

Project Takreer Shutdown 2012.

Client Takreer Oil Refinery Ruwais, Adnoc Group of Company UAE. Project 3nd:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From November, 2010 to january 2012.

Position fabricator (Mech) (Piping)

Project AMW Workshop(Piping Fabrication (Project #1900) Client Takreer Oil Refinery Ruwais, Adnoc Group of Company UAE. Project 2st:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From December, 2009 to April, 2010.

Position fabricator (Mech) (Piping)

Project Piping Modification and erection. (Project #1314) Client Abu Dhabi gas liquefaction company, DAS island. Project 1st:

Organization Descon Engineering http://www.descon.com (Abudhabi UAE) Tenure From October 2009 to December 2009.

Position fabricator (Mech) (Piping)

Project Piping Modification and erection. (Shutdown 2009) Client Abu Dhabi gas liquefaction company, DAS island. Major Responsibilities during Descon:

1 Inform of the progress, work priorities and anticipated delays; Prepare critical path analysis; and to suggest timely corrective action/revisit execution strategy in consultation with execution team for achieving of project objectives. Validation and reporting of progress.

2 Responsible for CS & SS Piping System Installation. 3 Responsible for following the Method Statements in execution. 4 Directly communication with Client, Vendor & line management and all the relevant departments involved in project execution.

5 Responsible for additional work and changes in the scope and schedule of work. 6 Support the team members and motivate them time to time. 7 Identify and share knowledge of best practices gained from past projects with team members to promote the quality of product.

8 Responsible for Sea Water and Utility System Piping Installation including 9 Fire Water, Instrument Air, Cooling Water and Nitrogen Purging Air Line. 10 Responsible for Installing and Routing of Steam Traced and Condensate lines. 11 Working on LINDE Factor system and Invoicing against achieved factors. 12 Responsible for Laying and Routing of Steam Traced and Condensate lines. 13 Responsible for installation of Fire Water & Sea Water System 14 Worked in Commissioning of Revamping unit.

15 Take ownership of QHSE policy, Company Values and ensure their implementation. 16 Review the Isometric Drawings as per plan and P&ID, inspection of fabrication and erection of piping and modify the Isometrics as per site.(as built drawings) 17 Familiar with National & International Codes & Standards

{Experience In Pakistan}

Organization Dewan Petroleum Limited (DPL-Pakistan) Project Piping fabrication & Erection.

Designation fabricator (Piping) (January 2007 to December 2008) Consultant Great wall Engineering & drilling, China. Responsibilities Worked as fabricator (Piping) at Salsabil Gas Field, Dhodak (Pakistan) My responsibilities were as follows:

1 Fabrication of piping, spools, skids supports P5, P11, Alloy steel, Duplex in Fabrication Shop.

2 Erection of piping, spools, skids supports and P5, P11, Alloy steel, Duplex including arranging for welding and testing till final release. 3 Laying and Commissioning of Pipe Lines

Organization Dewan Salman fibre (Hattar Industrial Estate, Haripur-Pakistan) Project Piping fabrication & Erection,.

Designation Pipe Fabricator (May 2006 to December 2006) Consultant Ekl Engineering Kinetics limited Lahore Pakistan. Responsibilities Worked as fabricator (Piping)

My responsibilities were as follows:

4 Fabrication of piping, spools, skids supports and P5, P11, Alloy steel, 5 Erection of piping, spools, skids supports and P5, P11, Alloy steel, Duplex including arranging for welding and testing till final release. 6 Laying and Commissioning of Pipe Lines

Organization Ravi Green Engineering

Project Piping fabrication & Erection,.

Designation Pipe Fitter 01, February,2005 to 17,March,2006 Consultant Zimmer Co., Germany.

Responsibilities Worked As Pipe Fitter (Piping)

My responsibilities were as follows:

7 Kept up-to-date record of daily progress.

8 Fabrication of piping, spools, skids supports and, Alloy steel, Duplex 9 Erection of piping, spools, skids supports and Alloy steel, Duplex including arranging for welding and testing till final release.

STANDARDS KNOWLEDGE

Having good knowledge of API, ASME, ASTM, DIN, ANSI, AISC and BS PROFESSIONAL COURSES & AFFILIATIONS

1 4 Days Training on Project Management Professional by Cambridge Institute Abu Dhabi UAE.

2 2 Days Training on FIDIC Contracts and Its Management by Dubai Institute of Business Management.

COMPUTER PROFICIENCIES

Excellent in computer software’s such as Microsoft Office Package (Excel, Word, Power Point, Access),

EDUCATIONAL BACKGROUND

• GOVT HIGH SCHOOL Chak No.515/EB, Pakistan

Matriculation (Science) 2nd Div. 2004

PERSONAL

Full Name: Muhammad Imran

Father’s Name: Muhammad Islam

Date of Birth: 17,January,1989

CNIC No. 36601-9298887-5

Passport No. BM1228873

Domicile: PUNJAB

Religion: Islam

Marital Status: Married

Nationality: Pakistani

Pakistan Cell # 0092-305-***-**** / 0092-308-***-****-2

.

REFERENCES

1 Reference will be provided upon request



Contact this candidate