Profile Summary

Contract Administration

Project Management

Tendering

Installation & Commissioning

Operations & Maintenance

Budgeting

Training & Development

Performance Management

Team Management

Result-oriented professional with nearly 16 years of experience in Contract Management, Project Management, Tendering, Client Relationship Management, Cost Control and People Management

Presently associated with Airmech W.L.L. as a Project Manager (MEP)

Skilled in study of Architectural/ Structural / Mechanical contract drawings/ contract specification of projects considering ASHRAE, BS, ASME codes

Expertise in preparing, submitting, discussing MEP Shop drawing layout/ MEP co-ordination layout/ builder’s work layout for approval to consultant

Acknowledged for MEP services subcontract of The Avenues mall, Sami-Al-Jasmi Villas, & BDF Hospital at 3 sites across Bahrain from Aug’17 to till date.

Prepares plans and layouts for Switchgears (MV, SMBD, DB, and MCC Panels). Develop controlling system for 3-phases' electric motor.

Coordinate manufacturing, construction, and installation and maintenance projects for engineering team to complete per customer requirements.

Perform detailed calculations to establish manufacturing, construction, and installation standards and specifications and maintains 100% accuracy rate, Interpret drawing mark-ups and implements drawing revisions provided by clients.

Soft Skills

Education

2015: Executive MBA in Materials Management & Project Management from NIBM, Chennaiuniversity

2002: B.Tech. (Mechanical) from JSS Academy of Technical Education, Noida, Dr. B.R. Ambedkar University, Agra

Career Timeline (2006 to till date)

Technical Expertise:

Electro-Mechanical (MEP) Engineering, Value Engineering, Material & Drawing review, Quantity Survey & Costing, Installation, Inspection, Power Quality and Pollution Control on Electrical Network, Testing & Commissioning procedures, Organization of Building Operation & Maintenance, Contracts, Claims, Data & Document Management, Defect Management and Building Services Assets & Energy Management system. All civil & structural works coordination related to MEP installation. All Pre & Post Construction Project Management system. Preparation of RFP & Project reports. ISO 9001- 2008 quality process / procedures etc.

SKILLS

Leadership, Motivation, Diagnostic, Problem solving. With will to succeed regardless of difficulties.

Ability to work as an effective member of team of managers, engineers & tradesmen.

Sound knowledge of in engineering & construction methods of MEP services

Broad outline knowledge of civil & architectural works.

COMPETENCIES

Leadership

Exhibits confidence in self and others; Effectively influences actions and opinions of others

Provides vision and inspiration to peers and subordinates, gaining respect and trust

Give and receive feedback and recognition; Motivates others

Managing People

General

Include staff in most planning, facilitation and decision making processes; Develop subordinates skills, providing regular performance feedback; Easily accessible; Seeks and applies customer feedback (internal and external); Improve supervisory skills; Getting others to focus on quality

Delegation

Delegate work assignments according to skill and responsibility of the person

Set expectations and monitors activities; Provide recognition of results

Teamwork

Balance team and individual responsibilities; Build morale and a positive team spirit and climate; Gain group commitments to goals; Encourage openness to other’s views

Judgement

Willing and able to make sound, accurate judgements, leading to timely decision making

Support and explain reasons for decisions; Involve others where appropriate

Communications

Excellent verbal & written skills; Ability to gather data,compile information & make presentations

Excellent writing skills, from emails to reports; Effective in public presentations

Knowledge about technical report writing; Understands proposal writing; Able to write memos under deadline

Problem Solving

Methodology

Identify problems speedily; Researches information effectively; Develops alternative solutions and decides on the best one; Can work as an individual and as part of a group; User reasoned, logical and balanced approach, even when dealing with emotional issues.

Cost Effectiveness

Work within agreed budget; Debates exceptions to the above; Initiates effective cost saving methods

Develops ideas contributing to profitability; Conserves resources

Organizational Leadership

Understand organizational mission, culture and ethics; Demonstrate ability in conflict management and dispute resolution; Understand how to acquire needed resources; Able to gather and synthesize information on internal and external environments.

Management

Able to analyse and design organizational structures and processes

Understand variety of approaches to decision making; Understand task analysis and job design

Demonstrate skills in team building and management

Innovation

Able to manage change; Understand creative processes; Capable of systems thinking

Adept at framing issues, Comfortable with risk taking

Interpersonal Abilities / Personal Characteristics

Able to work well in teams; Self-motivated; Understands conflict management

Able negotiator; Confident in handling new projects; Flexible in assignments

Attentive to detail; Able to work under tight deadlines; Able to network effectively

Planning & Organisation

Prioritise and plan activities and schedules for self and for others

Develop realistic action plans; Able to do strategic planning; Understands system analysis and design

Knowledge about project design and planning

Technical Ability

General

Have detailed technical knowledge of the construction process

Have ability to manage the activities of several projects concurrently

Quality

Promote and improve quality, through accuracy, thoroughness and new incentives

Work Experience

Since Mar’16 to Jul’17 with Darwish Mechanical & Electrical Co. W.L.L. an Electro-Mechanical Contracting company in Qatar.

Divisional Head (MEP)

Role:

Calculated applicable mechanical engineering fluid and airflow of engines

Handled the tasks of assisting senior engineers with dust collection, design of utilities, material handling and HVAC systems and equipment

Performed responsibilities of developing equipment specifications, vendor proposals, data sheets and technical studies

Handled the tasks of reviewing contractor and vendor equipment submittal bid analysis

Prepared and coordinated engineering projects, calculations, studies and drawings

Performed code compliance interpretations, computation, development of specifications and other miscellaneous engineering tasks.

Providing direction and conceptual input to designers for development of new generator sets

Developing cost-effective generator set products

Designing and developing generator set mechanical systems like cooling systems, fuel systems and chassis frames engine filtration

Providing direction and support to technicians in testing prototypes and in hardware production

Developing plans for the design, development, qualification and new generator sets and associated components

Coordinating with manufacturing, purchasing and suppliers by using concurrent engineering methodologies for optimizing designs for cost and manufacture

Ensuring complete and accurate documentation of technical data

Providing support on engineering standard work (ESW) and design practice (DP's)

Monitoring construction & estimation with contracts management of multi storey flats & buildings, villas, hotel & mall at more than 9 sites across entire Qatar and maintenance of water & electrical supply system for the projects.

Provided on-site management, technical guidance and quality control to ensure projects met time and budget requirement, and were built in accordance with contract documents.

Worked closely with engineers in reviewing drawings, specification, material submittals and schedules in addition to this I endeavoured to establish general arrangement drawing based on MEP, structural & architectural drawings.

Prepared budgets, estimate the bids & finalization of orders.

Negotiating for subcontract agreements, appointing sub-contractors, oversaw cost control and check / preparing variation claim.

Coordination with infrastructure contractors for external incoming and outgoing services.

Conducted and participated in project meetings. Generated / Monitored daily, weekly and monthly reports.

Implementation of Health and Safety plan throughout the site.

Working knowledge of MOWE, KAHRANAA, MOH, DEWA, SEWA, ADWEA, ASHGAL, TECOM, EHS, Civil Defence regulations and requirement

Collaborating with the engineers and draftsmen in the Structure/Architecture team while also taking inputs from others in the group and externally from the Interior Designer, architect and others,

Seeking inputs from Electrical Team for space planning, Space planning for HVAC, Plumbing, Fire Fighting, Sewage Treatment Plant, Swimming Pool and other infra work

Formalizing a technical brief for MEP consultants on all projects under Company (mixed use developments)

Testing & Commissioning of HVAC system as per approved Method Statements & Standard Engineering practices & codes from ASHRAE, BS, ASME, Elite Software - Mechanical, Electrical & Plumbing Software, Trace-BIM Software etc.

Reviewing:

Plumbing/Drainage System Design Documents

Fire Fighting System Design Documents

HVAC System Design Documents

Ensuring proper tender documentation and to ensure the draftsmen are doing drawing documentation

Preparation of the baseline execution program according to contractual requirements, Value engineering for design issues, Monitoring schedule for design packages delivery, Coordination between specifications, contract and other documents, Prepare / provide weekly report to management

Generation of early warning reports for missed/delayed activities

Execution and updating of the baseline programs on weekly and monthly basis

Preparation of Extension of Time Claims & Variation Orders

Generation of reports regarding cash flows, S-curves, manpower and equipment histograms on weekly and monthly basis.

Highlights:

Took several measures such as pre-contractual (planning),contracting (bidding and awarding of contract),contract administration (after the contract is awarded),post-contractual (close out, warranty and audit) to ensure that contract was in line with requirements

Reporting to the Head, Project Management team and leading a group of 15 people, which includes Architects, Draftsmen and engineers, I was responsible for Planning and monitoring of projects, managing clients, managing contracts, checking the adequacy of drawings, design coordination and management, preparation of bid documents & suggesting as well as implementing value engineering options.

The key responsibilities included Preparation of tender documents which includes Estimates, Rate analysis, Specifications and Bid Documents of client

Accountable for project planning, evaluation of technical and price bids, Responsible for design co-ordination and value engineering option evaluation, Verification of the drawings and co-certification of contractor’s bills

Evaluation of contractor’s schedules, progress reports and claims

Communicated with Project Managers for effective implementation and monitoring of Look-Ahead-Schedule including the project actual accomplishments

Undertook initiatives such as the procurement planning documents, the requisition and any amendments, the solicitation documents, bid evaluation plan and resulting evaluation documents, professional and specialist's advice, risk identification, assessment and mitigation, environmental considerations, impacts, and mitigation to ensure that tendering was in place

Overcame contract conditions, contract amendments, work schedule, including milestones and deliverables challenges during pushing Contractors / Subcontractors / Consultants for timely completion of works

Created important documentation such as payment schedules, invoices and payments, other correspondence (written and email), records of phone discussions, formal records of meetings, including minutes, records of decisions, warranties, management reports, including audit reports, and contract closeout documents on behalf of the company

Attained In-house Design Awards for Best Example of Internal Collaboration within the Business, creating the campaign - as well as the research, teamwork, tenacity and care taken to get it right for our Partnersinitiatives.

Feb’15 to Mar’16 with BSC -C&C ‘JV’, Kabul, Afghanistan

Project Manager - MEP

Role:

Monitored study of architectural/ structural/ mechanical contract drawings/ contract specification of project

Construct ability study, analyse drawings, prepare realistic plans, Initiate, develop and monitor the planning and progress procedures to ensure that each element of the project performs the processes timely and consistently.

Review scope change requests for the impact on schedules and the critical path of the project.

Supervision of all infrastructural activities including sewerage, drainage, water supply, Irrigation, Fire fighting, Landscaping & Mechanical works.

Review the Contractor’s shop drawings against the design [tender] drawings for compliance with the design intent and return with appropriate comments / approval within the specified contractual period.

Review and approve the material submittals & samples according to the project specifications & codes.

Review Contractor’s installation method statements and site inspections of equipment for MEP systems prior to installation.

Review the Contractor’s proposed sub-contractors associated with the engineering works from a technical standpoint.

Whenever required prepared technical clarifications to the tendered design to suit specific on-site construction and co-ordination issues.

Liaising with local authorities and their requirements and submission of information for obtaining NOC& approvals.

Witness on-site inspection for all type of tests (Pressure test, Water leak test, Visual inspections) as per the approved ITP.

Attending site progress & technical meetings with contractor and client.

Continuous review of the contractor’s construction schedule during the progress of site works with regards to MEP services and report to the project Manager on the same.

Monitoring and promoting health and safety on the site. Record and report any breaches to the Project Manager / Safety Department. If required stop the construction works if unsafe practices are being followed.

Manage the day to day work of the MEP team. Work with Superintendent on project logistics and temporary facility plans.

Review and approve Contractor’s as-built drawings. Preparing the final project MEP snag list of defects for Contractor’s action.

Witnessing the performance of final testing & commissioning of MEP services.

Review Contractor references, Operation & Maintenance manuals and Warranties for handing over the project. Managed allocation of work to Engineers & Draftsmen

Supervised Site installation Team for MEP installation as per approved MEP Co-ordination layout

Prepared:

Engineering submittals such as HVAC and Plumbing shop drawings, Static Pressure Calculation, Pump Head Calculation, Material submittals, Method Statements and so on for approval to consultant

Weekly tracking schedule of MEP Materials and Shop drawing for submission and commitment to main contractor

Discrepancy report on HVAC/ plumbing and fire-fighting system

Instituted equipment selection for all HVAC equipment & accessories as per contract specification

Performed QA/QC review on MEP Shop Drawings prepared prior submission to consultant

Prepared and issued RFI (Request for Information) document to consultant for any conflict in contract/ tender drawing design.

Liaised with Main Contractor & other Package Contractor for Interface with other services. Perform HVAC, Plumbing and Fire Fighting coordination with Main contractor/ Consultant regarding technical problem encountered both Engineering / installation on site problems and in getting approvals

Reviewed, controlled and regulated approval of MEP sub-contractor work procedures

Collaborated with the QA engineer, MEP inspectors and relevant staff

Ensured that the MEP sub-contractor provides and adheres to the necessary QA control documentation in an orderly and organize manner

Supported activities of the Project Program HS&E Plan and procedures and attends toolbox meetings

Provided support to H&S Officers on the site

Pushed Contractors / Subcontractors / Consultants for timely completion of works

Controlled Quality / Progress / Cost and safety of works

Tracked of Site progress as per Program on Daily basis

Attended subcontractor coordination meetings, operating company coordination meetings and other related meetings.

Project Managed:

Construction of Afghanistan Parliament, Indian Chancery Building, and 11KVa Substations at Indira Gandhi Hospital at Kabul” Afghanistan for MEP works worth 54 million USD for Afghanistan Government under Ministry of External Affairs, Govt. Of India from Feb’15 to Mar’16. Total Project Contract Value: - 176 Million USD.

Previous Work Experience

May’14 to Feb’15 with Sobha Engineering & Contracting LLC, Dubai

Senior Mechanical Engineer - MEP Department (ON CONTRACT Six Months -- Extendable)

Role:

As a senior Mechanical engineer my responsibilities were to handle the executions of all Mechanical, Plumbing & Fire fighting services.

Preparation of Mechanical, Plumbing & fire fighting Shop drawings and Submittals as per the specifications, standards, codes and authorities regulations.

Leading a team of site engineers, QA/QC engineers, supervisors, foreman, technicians, plumbers & subcontractors.

Ensure the MEP work carried out as per approved shop drawing and within the time frame and progress of the approved construction program.

Ensuring that RFI’s are raised and they are followed-up with consultant.

Ensure that the installation, inspection and testing of all the M&P equipment, fittings and work implemented meets the specification and the consultant requirements.

Attending project weekly meetings to discuss the site execution issues related to quality, progress and safety.

Ensuring that the Mechanical & plumbing services commissioning activities are on schedule, following the construction team to close & clearance of all outstanding issues, NCR and Snag list prior to handing over the project.

Projects Managed:

Construction of Meydan Heights Villas (504 Nos.) for Emirates Airlines in Dubai, UAE, MEP works @ Medallist Tower (G + 32 Residential Apartments), Interior & Fit Out Works in Sobha Sapphire GF, !6th & 5th floors simultaneously along with WTP for Almarai Foods in Dubai

Sep’09 to Mar’14 with BSC -C&C ‘JV’, Afghanistan

Senior Engineer - MEP Department

Role:

As a MEP Senior Engineer, I was involved in technical details of installations and dealing with all MEP subcontractors for site coordination.

Lead the project construction team during tender and construction phase; Review and response process for the contractor’s technical queries during tender; Review and approve the contractor’s pre-qualifications, key personnel during tender; Review the design to identify any potential VE elements along with consultants and contractors; Review and approve the contractor’s project construction programme in line with the overall project completion plan.

Monitor site progress and contractor’s resources against the resource load programme and highlight any non-conformance; Manage contractor’s mobilization and logistic issues at hand to ensure it doesn’t impact the project completion programme; Review the design to identify any constructability, commission ability, operability issues during construction; Assist in developing the risk register with help of TA, contractors and agree on the mitigation measures;

Lead LDC consultant, technical advisors and 3rd party consultants through the commissioning to the project handover; Monitor and manage the performance of resident engineer, contractors and advise Project Director on key issues; Conduct periodic audits and inspections to ensure the consultants and contractors performance is fully compliant with contractual obligations;

Resolve any conflicts between the consultants, contractors and mediate resolutions as required; Ensure that all technical aspects of the projects are strictly complied with and in conformity with conditions of contract, specifications, contract drawings & BOQ; Review of construction drawings, material submittals, technical submittals and product samples etc. as per project requirements; Review of construction methodologies, including risk assessments and ensure the contractors abide by the approved methodologies; Implementation of standardized construction management procedures & quality management process to achieve financial targets on assigned projects;

Conduct regular meetings and technical workshops to report progress, also to resolve technical issues at hand;

Conduct periodic site walks to inspect completed installations and observe the functional and performance tests to ensure conformance to design; Manage the process of testing & commissioning of various systems and equipment and ensure the contractors achieve the intermittent program milestones;

Provide program planning inputs including interfaces, risks analysis and develop action and recovery plans to support program delivery on time; Implement QA/QC procedures and ensure the project delivery team understands the requirements; Liaise with local statutory authorities for NOCs construction phase inspections, including T&C and issuance of building completion certificate; Ensure that the health and safety requirements are provided and that they comply with statutory regulations and code of practices; Oversee the implementation of safe working procedures i.e. ESSW and MSSW in line with local and international standards;

Review the operation and maintenance manuals, training manuals, as-built drawings, warranties and maintenance service agreements; Manage the snagging and de-snagging process for completed works and monitor any non-conformities; Handover the completed works to clients’ operations team and manage the client’s training programme; Recommend the client to issue TOC following the receipt of BCC upon completion of the project;

Monitor the performance of completed projects during defect liability period and liaising with the client for rectification of defects and issuance of DLP completion certificate.

Projects Managed:

Construction of Afghanistan Parliament and Indian Chancery Building, Fit-out works of Habibiya School at Kabul” Afghanistan for MEP works worth 234.67 million USD for Afghanistan Government under Ministry of External Affairs, Govt. Of India

Jan’06 to Sep’09 with Sterling & Wilson Ltd, Noida (U.P.)

Project & Estimation Engineer (MEP Services)

Role:

Handling the project independently, however the company had in-house plumbing departments and we were giving HVAC works to subcontractors. My position was fully responsible to successfully manage, execute, complete and handover the projects within approved budgets on cost, resources without compromising on Quality & Safety.

Ensure all technical aspects of the projects are strictly complied and are in conformity with Conditions of Contract, Particular Specifications, General Specifications, Contract Drawings & BOQ.

Dealing with local government authorities departments for approvals & Inspections.

Attending regular meetings (on work progress, coordination, design, etc.) with Main Contractor and Consultant to discuss key issues related to the project and take effective corrective actions. Leading the construction team for Installations & inspections on daily basis. (Site engineers, Draftsman, Supervisors & Subcontractors).

Monitoring QA/QC implementation and documentation. Follow up with suppliers and procurement department for delivery of materials, equipment’s and other related activities with project manager and field staff. Work with Superintendent on project logistics and temporary facility plans.

Prepare periodic reports for management including status of budgets, variance/change claims, schedules, disputes, up-coming activities & safety records.

Follow-up & coordination of all Mechanical and Plumbing services with main contractor on site progress, handovers and clearance for 1st/2nd/final fix in building finishes. (CHW pipe routing, FCU locations, Fire fighting/sprinkler pipe work, Water supply pipes, Drainage piping system, Sanitary ware fixtures & Accessories).

Monitor and review final handover procedures, testing & Commissioning, final inspections and defect liability periods along with warranties/guarantees.

Projects Managed:

Providing Air- Conditioning & Fire Fighting Works for a newly constructed 5-star (Ista Hotel An Oberoi International Enterprise) with Alpha-One Shopping Mall, Celebration Mall & Raja Sansi Airport Building in Amritsar from Jul’06 to Jan’08

Providing Air – Conditioning & Fire Fighting system for Airport Services Building & Terminal – 3 Complex under GMR Group & L & T Ltd at Delhi International Airport from Jan’08 to Sep’09

Aug’03 to Jan’06 with Prem Engineering Works (P) Ltd., Noida (UP)

Maintenance & Site Engineer

Jul’02 to Jul’03 with K.L. Steels (P) Ltd, Ghaziabad (U.P.)

Production Engineer (Trainee)

Additional Skills

MS Office, MS Excel, AutoCAD, MEP Revit Architecture, MS PROJECT, TCP/IP configurations and Internet Applications, McQuay-Duct Sizer, McQuay-Pipe sizer, Beta-Air terminal distribution devices selection software for HVAC applications, Thermal load calculation, static pressure calculation, pump head calculation,

HVAC duct design as per Carrier Design Data Hand book

Personal Details

Date of Birth:4thAugust 1980

Passport No.: Z2622467 valid up to May’23

Driving License GCC: 800869133 Valid up to Jan’2023

Contact Address: C/o Mrs. Upasana Singh Flat No. 405A, Divyansh Fabio Apartments, Crossings Republic, Near ABES Engineering College, NH-24, Ghaziabad, U.P., 201001, India

Permanent Address: House No: B-227,Lohia Nagar, Ghaziabad –201001, India

Languages Known: English and Hindi

Contact Details:- +91-956******* & +91-981*******



Contact this candidate