CURRICULAM VITAE

MOHAMMAD ZUBAIR ALAM

QA/Q MANAGER/LEAD AUDITOR

Contact in Saudi : 009**-********* E-mail : ac5g7f@r.postjobfree.com

Saudi Driving License

Mechanical Engineer (B.E)

IRCA ISO 9001:2015 CERTIFIED LEAD AUDITOR

(QMS) QUALITY MANAGEMENT SYSTEM (CERTIFICATE NO-EDU/QMS/LA/17/00104)

OBJECTIVE

To have a challenging career in QC Manager,QA/QC Piping Inspection Engineer,Mechanical QC Supervisor/ Supervising Engineer and become an integral part of a reputed organization where I can prove my capabilities to build up its strength.

SUMMARY OF SKILLS AND EXPERTISE:

THIRTEEN (14.03) years of extensive experience as Mechanical,Piping, Material Inspection/Material Prevention in Laydown Area or site area/ Structural QA/QC Inspector & QC Supervisor in Mechanical field of construction in various projects like Oil & Gas Industries, Petro chemicals, Chemical Plants, high rise building and infrastructure sector.

I would like to enroll in your esteemed organization as a candidate for an opening in the field of QA/QC Manager . I expect to here from your end in near future.

Excellent planner and strategist with proven abilities in surveying the projects of all kinds of earth works, power plant, chemical plant, water treatment plant, oil & gas plant etc.

Strong analytical and Organizational abilities with skills to plan and implement.

in the field of construction supervision, erection, installation and alignment of rotating equipment, pipes, valves, static equipment, vessels and engineering systems and other industrial equipment for Oil and Gas, Petrochemical, Industrial and Utility industries.

Outgoing and used to working in teams as well as individually. An attention for detail combined with an agile and analytical mind, I looked forward to challenges and aspire to achieve them.

Lead Audit/QMS System ISO 9001:2015 CERTIFIED

Review, Evaluate & Audit the effectiveness of the Quality Management system to ensure compliance of work output with, or identify Areas of non conformance to specification.

Developing Quality Management system Procedures including Quality Assurance Procedure & Quality Control Procedure.

Implementing Quality Management systems.

Developing Quality Manuals, Co-ordinate and obtain approval for QA/QC Manual from clients Representative.

Develop Inspection and Test Plans for various work phases.

Review of material requisition and purchase orders for compliance with applicable standards, drawings and specification.

Organizing and establishing the agenda for pre-inspection meetings, issuance and co-ordination of source inspection assignments and review of manufacturer / Vendor Quality Plans.

MY KEY SKILLS

Software: Microsoft Office, Excel, Power Point, Basic Auto Cad 2009

Skilled in piping general arrangement drawing and piping tie-In schedule

Strong familiarity in equipment and nameplate data list

Knowledgeable in detailed piping isometrics

Conversant with Codes and Standards such as ANSI, ASME, API, ASTM

Equipment erection, installation and alignment. Inspection and testing.

PROFESSIONAL WORKING EXPERIENCE:

Company : AL KIFAH CONTRACTIONG & HOLDING CO. LTD ( PACK-1)

Project : SOUTH DHAHRAN OWNERSHIP HOME PROGRAM(ARAMCO)

Position : QA/QC MECHANICAL SUPERVISOR

Duration : SEP 2017 TO TILL NOW

Duties & Responsibilities: AS A QA/QC MECHANICAL SUPERVISOR

To lead the team of QC Inspectors for monitoring the on going daily construction activities.

Reviewing the construction method statements and making comments per project specifications, procedures & ITPs.

Regular site visits for foreseeing the potential deficiencies based on his physical experience to share with construction crew and guidance to QC Inspectors.

Coordination with NDT agencies for inspection & testing requirements. Ensuring the availability of QC Inspector during any operations.

Initiating internal Log Book Entries/NCR’s to construction crew for effective implementation of project quality plan, ITP’s, written procedures, project specifications, IFC drawings etc.

Coordination with Clients inspectors for getting the feedback for open log book entries and - preparations of corrective actions to close those violations.

Emphasizing on the control of documents and records by advising the document controllers, QC Inspectors.

Conducting routine internal meetings with QC inspectors for further vigilance to the potential- al problems which must be tackled accordingly to avoid non conformities.

SECONDARY DUTIES AND RESPONSIBILITIES:

Complies with the highest level of safety during all stages of work to avoid any type of incidents and or accidents. Take reasonable care of own health and safety and that of others in the workplace

Complies with all statutory requirements connected with the implementation of project. WORK EXPERIENCE: OTHER SKILLS AND COMPETENCIES:

Familiarity with ISO 90001 quality control system and Minimum 10 to 15 years

PROFESSIONAL WORKING EXPERIENCE:

Company : CHINA COMMUNICATION CONSTRUCTION CO. LTD

Project : INFRASTRUCTURE OF JUBAIL-2, STAGE-3,(SWC) (RC)

Position : QC MANAGER

Duration : NOVEM 2016 TO TILL NOW

Duties & Responsibilities: AS A QA/QC MANAGER

Implement the QA/QC management system at site (QMS).

Coordinate with quality inspections with all the site sub-contractors and vendors coordinate all non-destructive testing on site

Coordinate with the customers representative on all quality matters

Coordinate all receipt inspections

Distribute relevant QA/QC documentation to site subcontractors

Verify that the quality related site activities are in accordance with the applicable codes and standards

Participate in the site internal and external site audits

Coordinate all the quality site inspections through the site QC inspectors

Ensure all quality control documentation is compiled and competed for as-built hand over through the QC turnover engineer

Control all nonconformance reports and undertake remedial action

Compete site quality control instructions and action remedial responses

Review the customers specification and undertake relevant training to the site QC inspector

Monitor the implementation of the approved site QC Plan

Complete and coordinate the approval of the sites QC technical submittals to the customer

Coordinate with the site construction manager on all quality issues Coordinate and chair the QA/QC site weekly meetings with the projects subcontractor’s QC personnel

Elaborating inspection and test programs,Ensure the safety is adhered to at site. Assure all technical documents relative to site quality

Taking care of QA/QC Document Project.

Responsibility for closure of NCR and preservation control of lay down Yard Area.

Responsibility of quality and workmanship of every Activity.

Carry out internal Audit at site as Schedule PQP.

Monitor all activity to QMS.

Coordinate with site in charge for Inspection.

Meeting about Quality Problem and solution.

Carry out Inspection and checking for all quality related procedure.

Project quality plan, ITP & checklist of Document Construction.

Hand over Project to Client.

Inspection Plan submitted every Months to the Project Manager.

Company : TECNICAS REUNIDAS GULF (Spain Co.)

Project : SADARA CHEMICAL PLANT III (AL JUBAIL-2)

Position : SR.QA/QC PIPING INSPECTOR/ENGINEER

Duration : FEB 2014 to SEP 2016

Duties & Responsibilities: AS A SR. QA/QC INSPECTION ENGINEER

Job Description

Involved in the preparation and development of construction and testing procedures, hydro test packages and all relevant project procedure preparation.

Responsible for company provided engineering documents, review of sub-contractor prepared engineering documents, ensuring engineering schedules are maintained, resolution of engineering site queries, coordinating resolution of engineering procurement issues, support of systems completion and turnover activities.

Establish and maintain a good working relationship and communication with other site team members, advise areas of concern and take an active role in implementation of necessary actions.

Participate in design reviews, Risk Assessment and HAZOP studies associated with design changes for operating facilities as part of project development.

Responsible in reviewing and approval of sub-contractor mechanical construction activities, system testing and commissioning procedures.

Coordinate with the sub-contractor Engineers and Project Manager to ensure that all works are carried out in accordance with project procedures, safely with due considerations to quality.

Plan and organized vendor specialist mobilization and demobilization, review daily progress reports, oversee the overall work activities base on project look ahead planning, liaise with operations personnel for the system commissioning and system handover after commissioning.

Coordinate with the client representative for any change order & revision in the field for proper documentation.

Hands on supervision on erection of steel structures/installation, leveling & alignment of static equipment such as vessel, drum, exchanger, column, and tower including internal installation such as chimney tray collector, trough distributor, feed pipe assembly, flashing feed gallery, flex type packing, demister, orifice deck distributor and internal trays and rotating equipment alignment.

Attend to progress and safety management meeting

Duties & Responsibilities: AS A QA/QC PIPING INSPECTOR

Ensuring that all mechanical construction activities and assembly of components including preservation of equipment for the Central Processing Facility Project (CPF) are carried out in accordance with Client approved Project Specifications, Project Procedures, Method Statements, and relevant Codes & Standards.

Witnessing and monitoring of all site static/rotating equipment, package equipment and skid mounted vessels/machinery inspections including structural steel erection

Ensure that all inspection reports are accurate and relevant documents are current status.

Review all inspection reports for compliance.

Prepare nonconformance reports to the QA manager and assist in developing corrective actions.

Coordinate with the client QC inspectors for the resolution of site problems.

Completion of QC site instructions and coordinate their closure and review of inspection test packages during the course of construction activities.

Compliance with the site’s health and safety regulations.

Attend weekly QC meetings.

Ensure all the equipment inspection activities are performed to approve procedures, codes and standards.

Executes the specific inspections on materials, equipment and construction/installation activities on site.

Issues the relevant Quality records and, when necessary, writes and sends to QC Manager Non-conformance reports.

Controls equipment installation, alignment and leveling. Performs functional checks and mechanical completion checks.

Witness the test, controls and inspection, authorizing the acceptance at quality control completion, obtain the relevant documentation and ensure the correct implementation of the approved Inspection Test Plan according to Client’s requirements.

Monitor the construction activities of subcontractors to ensure that the works are safely performed according to good engineering practices and standards.

Inspection and witnessing of testing and commissioning of rotating equipment and related documentation in accordance with project procedures.

Assigned as quality assurance inspector for manufacturing operation of wires and cables, establishment of quality control circle and process inspection point, materials inspection and acceptance, and assists production supervisor in production planning.

Responsible for achieving total quality excellence within the Department, through appropriate product/process inspection and testing; thus ensuring that quality functions and the QC Procedures are implemented in accordance with set goals.

Responsible for First Article Inspection and released QA documents.

Conduct regular in-process inspection/testing in all stages of production for the purpose of monitoring quality non-conformances in all areas of production.

Coordinate with the concern Departments regarding with the corrective action that should be taken on any reported non-conformances.

Monitor and follow-up on the proposed corrective actions and the stage of implementation thereof.

Assist the QC Manager in the development and implementation of Quality Work Procedures and Instructions; documents revisions, issuance and retrieval, filing and storage, and updating documents register.

Assume full responsibility and accountability for customer complaints; interact with all personnel who manage, perform and verify work affecting quality and provide/recommend solutions to problems relating to product, process or quality system. Obtain and maintain records of national and international standards thereby ensuring that the standards are regularly updated. Conducts internal calibration of in-house equipment.

Company : HYUNDAI-KCC ENGINEERING LTD (KOREAN Co.)

Project : JUBAIL POLYSILICON (WORLEY PERSON)

Position : QA/ QC SUPERVISOR

Duration : APR 2013 TO OCT 2013

Duties & Responsibilities: AS A QA/QC SUPERVISOR

Review and approve Sub contractor documents for compliance with Total specification and International standards.

Vendor Assessment and review of deliverables for status quo.

Co-ordinate site inspection activities with all disciplines enabling all site related Quality issues are sorted out in a timely manner.

Attend weekly meeting with sub-contractors and discuss issues related to QA/ QC and enforcing the implementation of raised memos.

Raise Non-conformance reports and follow ups for the issues not in compliance with

the project specifications.

Provide Project deviation request related to QA/QC after careful analysis of justification by the sub-contractor

Review and approve PQR, WPS and witness welder qualification tests. Inspection for

consumable handling, IMTE list tracking and implementation of calibration requirements as per contract specification.

Prepare site welding performance data sheet and monitoring of day-to-day welding production and prepare history sheets.

Witness field erection of piping, pipeline, equipment’s and structures per approved drawings.

Witness Peaking, Banding, Plumbness, roundness and settlement tests for the field

erected Oil storage and Fire water storage single skin Fixed roof tanks.

Painting, Polypropylene coating and Polyken wrapping inspection of Pipelines.

Witness profile checks, DFT and holiday for field painting and coating applications.

Witness Hydro tests, Gross air leak tests and Nitrogen purging for piping, Pipelines and

Equipment’s.

Perform conformity checks for reinstatement and pre-commissioning thereby enabling

smooth handover to start up team.

Review films and monitor NDT activities in site for compliance with established codes and

specifications.

Company : SK ENGINEERING &CONSTRUCTION (EPC#2)

Project : YANBU ARAMCO SINPOPEC REFINING COMPANY(YASREF)

Position : QA/QC PIPING INSPECTOR

Duration : DEC 2012 TO MAR 2013

Duties & Responsibilities: AS A QA/QC MECHANICAL INSPECTOR

Areas of expertise are Preservation, Installation, Inspection & Verification of Rotating Equipment, Static Equipment, Vessel Internals, Air fin coolers, Surface condensers, structural, etc.

Experienced in preparation/verification of ITP, QCP, Method Statements, NCR, DR, ITR etc for the Installation & Inspection of Equipment.

Familiar with code & standards - API, Aramco, Borouge, QP, Shell DEP, PIP VEFV, Tema etc.

Familiar with Piping Test Pack review, Line walk down and Punching, Pressure Test, documentation.

Inspection for Preservation of Equipment include N2 pressure, Sacrificial Anode installation, Desiccants / VPCI Powder, Telltale hole grease lubrication, Paint Damage, Closed condition of Flanges/openings, Grease lubrication of machined parts, Bearing housing oil level, Periodic shaft turn, Storing of Plunger & valve components, Space heater energize of motor, Storing of spare rotor & parts, etc.

Installation & Inspection for Rotary Equipment include Padding, Elevation, Position, Orientation, Levelness, Pre.shaft alignment, Run-out, Void, Surveillance inspection during erection and welding of Piping, Pipe Strain, Motor / Turbine solo run, Final shaft alignment, Prep. of Graph, P&ID Verification, Lube oil Flushing Inspection, Mechanical Running test, Completion of inspection records etc.

Installation & Inspection for Static Equipment include Padding, Elevation, Position, Orientation, Verticality, Levelness, Platform & ladder, Vessel Internal work, Leak Testing, Loading of catalyst, chemicals, Support balls, Vessel Box-up, etc.

Installation & Inspection of Air Fin Cooler & Air cooled surface condenser include Alignment of setting plate, structure, tube bundle, louver, shaft, pulley, Blade Angle, Tip clearance, Belt tension, pressure testing / Dew point inspection for tube bundles, solo run of motor, Completion of inspection records etc.

Supervise and witness inspections, check reports and documentation issued by inspectors and collect the required Quality Records

Ensure that all sites activities are carried out according to reference documentation for parts of the plant within his area of responsibility, authorizing their acceptance at quality control completion

Ensure that material and equipment are correctly received, stored, preserved and handled, identified and traceable

Implement the inspection, control and test notification process

Check, insofar as within remit, the test packages provided for the final checks

Ensure calibration of measurement instruments and related certifications

Check procedures and equipment to be used in tests, controls and inspections and agree on the applicable operating procedures with the organization in charge of the works

Ensure that the tests, controls and inspections are carried out according to Quality Control Plans/Inspection Test Plans, obtain and collect the relevant documentation also for the purpose of approvals of mechanical completion of plant systems and ensure that personnel have access to all required project documentation

Make site personnel aware of and trainee them on quality topics relevant to Mechanical works

Ensure, whenever necessary, the update of site quality control plans / control procedures

Ensure the preparation of the Quality Mechanical works dossier for final handover to the Client

Company : SUNG CHANG ENGINEERING & CONSTRUCTION CO.LTD

Project : OFFSITE AND UTILITIES PACKAGE # 3 PROJECT –ABU- DHABI(TAKREER)

Position : QA/QC PIPING INSPECTOR

Duration : JAN 2012 TO AUG 2012

Company : BADAR AL MULLAH & BROTHERS & COMPANY W.L.L

Project : KUWAIT NATIONAL PETROLIUM CO. (KNPC -0028)

Position : QA/QC PIPING ENGINEER

Duration : Dec 2009 to Feb 2011

Duties & Responsibilities: AS A QA/QC PIPING INSPECTOR

Job Description:

Ensuring that all mechanical construction activities and assembly of components including preservation of equipment for the Central Processing Facility Project (CPF) are carried out in accordance with Client approved Project Specifications, Project Procedures, Method Statements, and relevant Codes & Standards.

Witnessing and monitoring of all site static/rotating equipment, package equipment and skid mounted vessels/machinery inspections including structural steel erection.

Ensure that all inspection reports are accurate and relevant documents are current status.

Review all inspection reports for compliance.

Prepare nonconformance reports to the QA manager and assist in developing corrective actions.

Coordinate with the client QC inspectors for the resolution of site problems.

Completion of QC site instructions and coordinate their closure and review of inspection test packages during the course of construction activities.

Compliance with the site’s health and safety regulations.

Attend weekly QC meetings

Ensure all the equipment inspection activities are performed to approve procedures, codes and standards.

Executes the specific inspections on materials, equipment and construction/installation activities on site.

Issues the relevant Quality records and, when necessary, writes and sends to QC Manager Non-conformance reports.

Controls equipment installation, alignment and leveling. Performs functional checks and mechanical completion checks.

Witness the test, controls and inspection, authorizing the acceptance at quality control completion, obtain the relevant documentation and ensure the correct implementation of the approved Inspection Test Plan according to Client’s requirements.

Monitor the construction activities of subcontractors to ensure that the works are safely performed according to good engineering practices and standards.

Inspection and witnessing of testing and commissioning of rotating equipment and related documentation in accordance with project procedures.

Attend all necessary inspections as identified in the approved Inspection and Test Plan (ITP).

Inspect the production quality to establish if the client requirements are being achieved.

Shall perform a variety of inspection functions under supervision

Record and document any and all deviations from the Project Quality Program (PQP) and the Company Integrated Management System (IMS).

Update the system with any and all deviations from the Project Quality Program and the Company Integrated Management System (IMS).

Coordinate with the client representatives to ensure that inspections are carried out expediently.

Generate client Requests For Inspection (RFI) where required providing sufficient notice for hold, witness and inspection points.

Carry out inspections on Exception Items (EI) as documented and sign off a closed when activity is complete.

Continually carry out surveillance inspections on the project recording and documenting any and all deviations from the (PQP) and the company Integrated Management System (IMS).

Review the calibration status of any test equipment being utilized on the project ensuring the equipment is within calibration prior to use.

Provide support and advice to the construction personnel in relation to the Project Quality Program and the Company Integrated Management System (IMS)

Maintain a good working relationship with all Client personnel.

Maintain good record keeping of activities carried out and inspection reports, surveillance reports, etc.

Comply with all Project HSE requirements i.e. PPE, work Permits etc.

Any other duties as assigned from time to time

Company : SAUDI OGER LTD W.L.L ( RIYADH)

Project : PIPELINE NORTHEN PROJECT (1000km) & POTABLE WATER SYSTEM

Position : PIPING QC INSPECTOR

Duration : Feb 2007 to Dec 2009

Company : PUNJ LLOYD LTD

Project : DABHOL – BANGLORE PIPELINE PROJECT( INDIA)

Position : PIPING ENGINEER

Duration : Aug 2003 to Jan 2007

Duties & Responsibilities: AS A PIPING INSPECTION ENGINEER

Packages, inspecting the water to be used for Hydro Test as per the ASME B-31.3 St

Ensure the Inspection & Test Plan of each activity is fulfilled and "hold points" of the company are completed in due time.

Ensure all the personnel employed and operating in welding and NDE activities is duly skilled and qualified in accordance with the applicable specifications, codes and regulations.

Monitoring daily QC activities of Sub Contractors, To ensure erection is in compliance with contract specifications, review of inspection and test plans and erection procedure to ensure the implementation of the project approved QA/QC procedures and standards are followed.

Perform routine surveillance, inspection, monitoring, auditing & assurance of Sub-Contractor's site activities (Fabrication and Welding, NDT, Coating and Painting) in accordance with the Project and Contractors Specifications, ITP and Quality Plans.

Identifying the test medium to be used for Hydro Test for Piping Lines in the Test Packages, inspecting the water to be used for Hydro Test as per the ASME B-31.3 Standards.

Piping line check, witness hydro testing and review hydro test packages to verify the completion of NDT requirements, gauge calibrations, verifying that pipe supports, hangers and guides have been installed in accordance with the piping drawings and the pipe support details, analyze the requirement of temporary supports for above ground piping during hydro test, reinforced pads leak testing.

Assure that all joints are exposed for examination during pressure test. Ensure that isolation or disconnection of equipment not to be tested. Check vents are open when filling and draining lines.

Making Punch List with client and attained the same Hydro Test witness with client. All the inspection report making and taking the signature from the client

Receiving Incoming materials from vendors and preparing inspection reports for Fit-up and welding.Co-ordinate with client quality Engineer for final Punch listing.

Control of quality Control documents and maintain its status list. Inspection of deliveries of Materials to assure that they are within tolerance, grade in quality as specified. They are properly stored and handled, and that they have been not damaged.

Raising RFI’s for each item of work completed and at site for witness. Orientation checking, Identification of Radiography joints, taking NDT clearance from Clients, Repair attending of joints, Documentation maintenance for ISO records.

Control of management and execution of all activities as per specification codes, approved procedure.Familier with Hydro test knowledge of Plant piping and Fittings.

Valve testing RFI rising with Construction team Coordination. Valve inspection and testing arrangements and witness with EPC/Client Inspectors as per API 598.

Duties & Responsibilities: AS A INTERPRET AND EVALUATE NDT,WITNESS HYDRO TEST, PNEUMATIC TEST AND POST TEST REINSTATEMENT:

Ensure that all required NDE shall be performed prior to final system hydro/ pneumatic testing unless otherwise specified by engineering, reviewing all the NDT reports with coordination of NDT Personnel & Third party Inspectors.

Identification of risks to the quality of work and the completion programs and associated solutions.

Trouble shooting, Maintain day-to-day liaison with Contractor's site QA/QC staff. Prepare daily reports of all site QC activities performed

Valve drawings and calculations, including outline dimensions, weights, section drawings, part lists and materials for approval.

Trim shall include the nozzle, the disc holder, stem, guide, blow down ring, ring pin, bushing and all internal parts, except the body, in contact with the process fluid.

The nozzle and disc shall be forged / bar stock SS 316 with machined stainless steel guide and spindle.

The valve spring design shall permit an adjustment of +/- 5 % of the set pressure as a minimum. Spring materials supplied shall be suitable for the relieving temperatures given on the data sheet.

Alloy steel shall be used for temperature below 230 C. Plain lifting levers shall be provided on all valves for steam service unless specified otherwise on the data sheet.

Caps shall be provided over the spring adjusting screws on all valves. The cap and bonnet shall be provided with a wire seal to prevent unauthorized adjustment.

Only safety relief valves incorporating adjustable blow down rings shall be offered for protecting process equipment. Safety / Relief valves shall be painted in accordance with manufacturer standard unless otherwise specified.

The safety or relief valve shall be of adequate size to relieve the capacity at the specified pressure and temperature conditions and fluid physical properties regardless of any preliminary sizing calculations or orifice designation shown on data sheet.

Accumulation used in calculating size of relieving devices shall be 10%. The valves shall be suitable for continuous operation under the operating conditions indicated in data sheets.

For very low capacity applications, if API orifice is offered, vendor shall provide mechanical stop to prevent lifting. Vendor shall also arrange for witnessing capacity test of such valves.

A permanently attached (with drive pins or equal) stainless steel tag (s) stamped with the following information shall be provided on each valve.

Tag Number Manufacturer's Name. Trademark Model Number.

Serial Number and Year of manufacture Size of Valve with flange rating for inlet and outlet Body Material. Body and Trim Material Set pressure Set Pressure Range Orifice description Code stamp

Each valve shall be factory set and tested in accordance with the appropriate code Procedures. When the valve is subjected to the specified set pressure, destructive chattering shall not occur when raising the pressure to the popping point and then lowering to below the closing pressure.

Set pressure tolerances shall be as required by the appropriate code. Operational tightness test - the valves shall be bubble tight when tested at 90% of set pressure in accordance with the appropriate standard.

Test & Test Certificate The supplier shall issue with each valve test certificates confirming that it complies with the relevant codes for: Hydrostatic pressure test, Seat leakage test, Relieving set pressure, Functional test, Material test certificate for pressure-containing parts.

Material test certificates with detailed chemical analysis from the foundry for each casting Certificate of radiography / X-ray for valve casting. Certificate in form III C for all valves covered under IBR certification

Factory Inspection The complete valve and actuator assembly shall be inspected by the owner and third party prior to dispatch unless otherwise advised. Owner/MMCI shall be informed at least 6 weeks in advance for the inspection and FAT.

Vendor shall provide as a



Contact this candidate