Ferdinand F. Par [pic]
#** ********* **.,*** ****** Hts.Subd.,
Binangonan Rizal, Philippines
Contact No.+639********* ( Phil. No.)
Email: ************@*****.***
***.*********@*****.***
Educational Attainment
BACHELOR OF SCIENCE IN ELECTRICAL ENGINEERING
Eulogio "Amang" Rodriquez Institute of Science and Technology
Nagtahan Sampaloc Manila,
Philippines
March 21,2000 (Year Graduated )
Objective:
To continuously develop my skill in my chosen field of profession as
Electrical Engineer
Interconnectivity with other profession and to attain versatility and
adequate engineering technical
Knowledge as my instrument to render satisfactory service and performance.
Employment History:
. HYUNDAI ENGINEERING CO.LTD
. HYUNDAI 41 TOWER
. 917-9.MOK-DONG, YANGCHEON-GU, SEOUL.158-723,KOREA
. Tel:82-2-2166-8114
Project Assigned:
Electrical Supervisor: TACE ETHANE CRACKER AND PE/PP PLANT PROJECT
Engineer TURKMENISTAN REPUBLIC
FEBRUARY 14,2016 TO
DECEMBER 27,2017
Duties and Responsibilities:
. Responsible to analysis layout drawing and supervision for
installation of cable tray for power and control cable
. Responsible to monitor of electrical priority activity specially in
cable pulling of HV, MV and LV cable also control cable
. Responsible to supervision of meggering test of power and control
cable
. Responsible to supervision and monitoring of cable termination for the
interconnection diagram for power cable and control cable
. Responsible to check of daily work report of the subcontractor
specially cable pulling and termination to monitor daily percentage
accomplishment report
. Responsible for supervision of installation of heat tracing cable and
termination
. Responsible to check electrical equipment layout and cable routing
layout form internal to external to avoid mismatch layout of
architectural and civil layout
. Responsible to supervision of lighting from installation of units,
termination of cable and final checking of testing of normal and
emergency lighting
Project Assigned:
Electrical Supervisor: UZ-KOR GAS CHEMICAL PROJECT
Engineer UZBEKISTAN REPUBLIC
SEPTEMBER 24, 2013 TO
JULY 10, 2015
Duties and Responsibilities:
. Responsible for supervision of electrical activities at Oil Type
Transformer installation 35kv,33.25MVA and 6.3kv,transformer, MV
Switchgear GIS,LV Switchgear, MCC panel installation and also to
check mechanical layout for electrical
. Responsible to analysis layout drawing and supervision for
installation of street lighting, area lighting,fire alarm,paging
system and communication
. Responsible to monitor of electrical priority activity specially in
cable routing activities
. Responsible to supervision of Cathodic protection installation for
tank and pipe line
. Responsible for supervision installation of conduit for lighting, fire
alarm units horn, beacon, bell, manual call station and local fire
alarm panel and cable pulling with megger test
. Responsible to check of daily work report of subcontractor and weekly
report to monitor daily activities and also weekly plan
. Responsible for supervision of installation of battery charger panel,
UPS panel, EMCC panel, LCP, Protection panel, CB panel, patch panel
Electrical control system(ECS),bus duct, Dry type Transformer
installation and VSDS panel Inverter
. Responsible to check electrical equipment layout and cable routing
layout form internal to external to avoid mismatch layout of
architectural and civil layout
. SAMSUNG SAUDI ARABIA CO.LTD
. P.O BOX 35816 - JUBAIL IND.CITY 31961
. Kingdom of Saudi Arabia
. Tel:+966*********
Project Assigned:
Electrical Supervisor: WASIT CO-GENERATION PROJECT (ARAMCO)
Jubail Industrial City
Dec, 02, 2012 to April,17,2013
Duties and Responsibilities:
. Responsible for prepare daily work permit in pre-commission test of
13,8kv Switchgear LV Switchgear motor control centre and Oil Type
Transformer 230kv,
. Responsible to prepare pre-commission document for pre commission test
230kv oil type transformer 13.8kv Switchgear LV Switchgear and MCC
PANEL
. Responsible for supervision of pre-commission test.
. Responsible to check and analysis fire alarm lighting communication
and paging system layout and diagram for power and control cable
schedule.
. Responsible for supervision of cable tray installation, MCT(multi
cable transit) conduit, fire alarm units horn, beacon, bell, manual
full station and local fire alarm panel
. Responsible to check of daily work report of subcontractor and weekly
report to monitor daily activities.
. Responsible for supervision of installation of battery charger panel,
UPS panel, MV Switchgear, LV Switchgear, MCC panel, EMCC panel, LCP,
Protection panel and preparation of pre-commission document for
equipment.
Electrical Supervisor: SOCC - ALUMINUM ALKYLS PROJECT (BY SABIC
STANDARD)
Jubail Industrial City
April,17 2012 to Dec.01,2012
Duties and Responsibilities:
. Responsible in the supervision of installation of 34.8 kva transformer
. Responsible in the supervision of installation of cable tray, lighting
units
LP panel, LCS,CCTV camera, Fire alarm units.
. Responsible in the supervision of Installation of Switch gear, MCC
panel EMCC,
UPS panel, Battery charger chloride, SF6 PNL,LV VSD
panel(Rockwell) and Power Capacitor(ABB).
. Responsible in the supervision of cable pulling for power cable and
control cable.
. Responsible in the supervision of cable testing megger of power cable
and control
. Responsible for supervision of installation of battery charger
panel, UPS panel, MV Switchgear, LV Switchgear, MCC panel, EMCC
panel, LCP, Protection panel and preparation of pre-commission
document of equipment.
. Cable supervision of HI-POT test of medium Voltage cable.
. Responsible in the supervision of motor solo run test for motor
winding test and
Vibration monitoring test
. MEEDCO & HYUNDAI PROJECT ( ARAMCO STANDARD)
. DaemYoung GEC Co.,LTD.
. DaemYoung Bldg., 125-B Yangjae- dong-gu,Seoul,Korea.
. Tel:82-2-2182-3900
Project Assigned:
Electrical Supervisor: Karan Gas Field Development Project(ARAMCO)
Engineer Jubail Saudi Arabia K.S.A
June 24,2010 to June 25,2011
Duties and Responsibilities:
. Prepare weekly work permit every week for a daily work activity
. Prepare Electrical drawing for detail installation of all cable tray,
lighting
Fire alarm.
. Responsible in the supervision of installation of the LCS, MCC panel,
EMCC panel
and UPS panel.
. Responsible to prepare work shop drawing for approval of additional
cable tray
Support at pipe rack and substation.
. Responsible to request of additional materials and tool needed
controller
. Responsible to review electrical drawing and prepare technical queries
for any
Discrepancies that need some clarification and confirmation.
. Responsible to daily work progress report .
. CARLO GAVAZZI SAUDI ARADIA CO.& BONATTI S.P.A
. Kazakhtan Branch
Project Assigned:
ELECTRICAL SUPERVISOR: Gas Plant Carabatan Project(Europe Standard)
Engineer Kazakhtan Republic
May,2009 to Nov,2009
Duties and Responsibilities:
. Responsible in supervision of installation of the control panel
. Responsible in the supervision of cable pulling for power cable and
instrument cable.
. Responsible of the installation of temporary power panel and
termination of power cable.
. Responsible the electrical layout of new building of Bonatti office.
. Responsible to daily work progress report at construction manager
Responsible for supervision of installation of battery charger
panel, UPS panel, MV Switchgear, LV Switchgear, MCC panel, EMCC
panel, LCP, Protection panel and preparation of pre-commission
document of equipment.
. Cable supervision of HI-POT test of medium Voltage cable.
. Responsible in the supervision of motor solo run test for motor
winding test and
Vibration monitoring test
. CARLO GAVAZZI ARABIA CO.LTD
. Jeddah,Saudi, Arabia 21444
. P.O Box 15291
Project Assigned:
ELECTRICAL SUPERVISOR Shaybah CPF Project GOSH-4 (ARAMCO PROJECT)
Engineer Shaybah, Saudi Arabia
May, 2008 to March,2009
ELECTRICAL SUPERVISOR Rabigh Petro-Chemical Project ( ARAMCO PROJECT)
Engineer Rabigh, Saudi, Arabia
August, 2007 to May,2008
Duties and Responsibilities:
. Responsible in the supervision of electrical works such as fabrication
and installation of cable tray & runways, lighting poles and control
panels.
. Responsible in the supervision of installation of the control cabinet,
switch gear, LCS motor,
Communication rack runway and conduit.
. Responsible in the supervision of cable termination in switch gear
panel, MCC panel to motor supply and communication patch panel
(modular and fiber Optic patch panel).
. Responsible in the installation of horn and beacon for H2S and gas
detector.
. Responsible in the supervision of installation of the telecom copper
cable & fiber optic cable
In under- ground installation and aerial installation.
. Responsible in supervision of the termination of copper cable and
transition splicing of fiber
Optic cable
. Responsible in the installation of UTP CAT 6 & CAT 3 cable and plenum
cable.
. Responsible in the installation of telecom rack, data & telecom
cabinet equipment
Installation.
. Responsible in the Plant paging system installation of the junction
box and call station, acoustic booth and speaker in Internal and
External
. Responsible in the supervision of termination of paging system cable
from call station, speaker, junction box to main panel of paging
system
. Responsible in the installation of junction box of CCTV and CCTV
camera units in external.
. Responsible in the supervision of installation of power cable,
dressing and termination of CCTV camera supply.
. Responsible in the supervision of Fiber optic cable dressing and
splicing for the CCTV camera.
. Prepare As-built drawing.
. Review and recommend solution to revise drawing for cable and lighting
for both electrical and communication.
Site Electrical Maintenance: Steel Centre Philippines
Amang Rodrequez Ave. Manggahan,
Pasig City, Philippines
February 07, 2003 to June 30 2007
Duties and Responsibilities:
. Responsible to conduct of inspection in maintenance power supply for a
daily work in proper procedure for safety.
. Prepare electrical drawing and supervision in the actual electrical
construction.
. Prepare cost Estimate.
. Set up the temporary power cable supply for mobilizing electricity in
the project site.
. Installation of temporary cable wire from main panel to the
distribution power supply.
And termination of 500mcm cable and 95mm cable wire from
distribution power supply.
. Installation of temporary transformer three phase step down with 440v
to 220v with AC machines.
. Operate the generator with capacity of 1500kv and maintenance.
Cadet Engineer: Well Constructing Corp.
1954 Campillo St. malate, Manila
Dec.05,2001 to Feb.04 2003
Duties and Responsibilities:
. As cadet Engineer purchaser of all electrical material and equipment
requested by project engineer with the management, my responsibility
is to conduct and attend bidding of material and equipment from 3 to
more supplier and select suitable prices commensurate to quality
required by the company.
. Received and inspect the material delivered in accordance to the
required material specification.
. Compile all receipt and document of the material received for monthly
inventory.
Cadet Engineer: Flores Construction and Electrical Corp.
617 J.P.Rizal Makati City, Philippines
March 2000 to Nov.2001
Duties and Responsibilities:
. Responsible to present the company proposal and company profiles into
the establishment and company's need electrical and mechanical
maintenance services.
. Responsible to conduct inspections of defective equipment for
maintenance problem of building to estimate cost of damages and
suggest the possible solution in maintenance .
. Responsible to present company profile with working procedure and
warranty of the job.
Seminars and Trainings:
. February 16,1999 Wiring Design Calculation
Short Circuit Calculation and
National building code
. September 10,1999 Motor Control, Instrumentation and
Control System
. December 01,1999 Grounding
Extra Curricular Activity:
. Public Relation Officer, IIEE - SEES Chapter (Earist) 1999 - 2000
Special Skills:
. Computer literate, Microsoft Word / Excel and auto cad
. Ample knowledge in the analysis of Structural Design Architectural
design and Civil Design
. Ability to make Electrical Design
Personal Information:
. Birthday : May 31, 1974
. Birthplace : Infanta, Quezon
. Age : 43 years old
. Height : 5' 7"
. Weight : 175 Lbs.
. Civil status : Married
. Spouse : Michelle T. Par
. Religion : Roman Catholic
FERDINAND F. PAR
Applicant