Joseph W. Jones
Keller, TX 76244 US
Phone: +1-817-***-****
Cell: +1-425-***-****
ac4jzf@r.postjobfree.com
Manufacturing Engineer
Boeing Space Division
January, 2016
SLS (Space Launch System) develops, implements and maintains various manufacturing plans, Bill of Materials, work instructions and illustrations to define and document as-built configuration
Develops manufacturing concepts and strategies to support business objectives
Develops and integrates suppliers, processes, materials, data and technology to meet manufacturing
Develops tooling requirements based on manufacturing and engineering requirements
Resolves manufacturing related issues
Performs producibility assessments for part or product designs
Provides producibility input to design, manufacturing processes and manufacturing technologies to meet cost and schedules
Develops integrated work statements and sequencing of events to support delivery commitments.
Manufacturing Engineer
GKN Aerospace
September, 2015 January, 2016 (4 months)
Analyzes engineering design documents to establish manufacturing methods and processes to manufacture a component, including creating conceptual sketches and initiating the design and building of required tooling within established budgets and submits for appropriate approvals
Provides program management for individual parts, develops and maintains all production plans including sequencing of events for efficient, cost-effective manufacturing and coordinates all phases of manufacture, including process planning, tooling, and components manufacture assuring compliance to customer and company requirements
Maintains accurate files on parts
Welding Process for 767 Tanker and 737 Exhaust for Boeing Program
Prepares changes to meet revised customer requirements
Reviews progress with the customer, including design errors, proposed part rework and manufacturing problems.
Manufacturing Engineer
Zodiac Aerospace
April, 2014 July, 2015 (1 year 3 months)
Support manufacturing process in fab assemblies, projects, interface with liaison engineering, tooling department
Support foam shop and plastics to make sure they have the most current engineering changes and Experience in Root Cause Analysis
Drive continuous improvement culture for DFM, to protect quality in cost, weight and cycle time reductions
Build methodology, value trade studies, advanced MBOM'S, tooling concepts, planning details, sub-assemblies and installation work instructions for production needs
Minimize the needs for MRR and Scrap analysis, closed loop RCCA for design, process and better products
Also support final line assembly and all the sub-assembly shops
Computer systems QMS, MAPICS, ProE, Pro Link and other systems
Able to lead teams towards defined objectives, with on time production.
Manufacturing Engineer & Contractor
(company name not available)
February, 2012 May, 2013 (1 year 3 months)
Bell/Textron Helicopter Manufacturing Engineer (Contractor) Assisted the BSM configuration team in the execution of Bell System Modernization conversion
This project consists of several tasks: Part Serialization, Time sensitive material, Bill of material validation, and configuration, and also the SAP conversion of all parts to the new paperless system
Used ENOVIA system to convert plans into the CAMS system per Engineering (NAV BOM).
Manufacturing Planner
Lockheed Martin
October, 2009 January, 2012 (2 years 3 months)
Checked Manufacturing Plans for Level II Planning on the F-35 program for areas of planning, current engineering incorporated, Correct MBOM vs
EMOM (parts list), Docs correct to planning/engineering and launch, then check for all effectivities accounted for via master, limit a card as needed, hot box or SOM
Analyzed, determined, planned, and ordered the processes operations, tooling, assemblies and installations required for F-35 fabrication per PDM, SAP and CAPP
Created and maintained necessary planning paperwork for F-35 engineering documents
Interfaced with liaison planning, liaison engineering, manufacturing engineering and design engineering organizations to incorporate engineering changes into efficient manufacturing plans
ITAR.
Detail Planner
Vought Aircraft Industries
January, 2008 September, 2009 (1 year 8 months)
Created and maintained planning and shop paper work for detail, fabrication, and sub-assemblies support for the 747-8 Program, Blackhawk program and Redline shop paper work as required
Possess extensive experience of working in PDM environments such as Team Center, VMCSII, and ACIS
Specific activities include obtaining of Engineering through Team Center, creation of plans in VMCSII, interface with other PDM system such as ACIS, and MES to finalize build packages
Additional responsibilities include Redlining floor plans, creation of Deviations, Interface with production floor, liaison planning, liaison engineering and Vendors, Training, Report generation, and active involvement in the resolution of parts shortages and audit errors.
Manufacturing Planner
Lockheed Martin
April, 2007 January, 2008 (9 months)
Analyzed, determined, planned, and ordered the processes operations, tooling, assemblies and installations required for F-35 wing planning fabrication per PDM, and CAPP
Created and maintained necessary planning paperwork for F-35 engineering documents
Interfaced with liaison planning, liaison engineering, manufacturing engineering and design engineering organizations to incorporate engineering changes into efficient manufacturing plans
ITAR.
Manufacturing Engineer
Global Aeronautica
July, 2006 April, 2007 (9 months)
Pre-Integration 787 Program for Boeing Company: Create Installation Plans per engineering documents by using CATIA V5, DELMIA V5, and ENOVIA for the Pre-Integration 787 program
Interfaced with liaison planning, liaison engineering, tooling design, liaison tooling and design engineering organizations to incorporate engineering changes such as DCN, EDCN and EO.
Production Engineer
Vought Aircraft Industries
September, 2004 June, 2006 (1 year 9 months)
Created and maintained planning and shop paper work for installation, fabrication, and support for the Blackhawk Program, 747, 767 sub-assemblies and Redline shop paper work as required
Possess extensive experience of working in PDM environments such as Team Center, VMCSII, and ACIS.
Manufacturing Planner
Lockheed Martin
June, 2003 August, 2004 (1 year 2 months)
Analyzed, determined, planned, and ordered the processes operations, tooling, assemblies and installations required for F-16 fabrication
Created and maintained necessary planning paperwork for F-16 engineering documents
Interfaced with liaison planning, liaison engineering, manufacturing engineering and design engineering organizations to incorporate engineering changes into efficient manufacturing plans.
Manufacturing Engineer
Boeing Company
August, 1992 May, 2003 (10 years 9 months)
Created and maintained planning paperwork, O&IR, Planning Action Requests, and other shop floor paper for tooling, fabrication, assembly, and functional tests
Used various on-line systems, including DCAC/MRM, CAPP, and PDM
Interfaced regularly with liaison planning, liaison engineering, tooling design, outside vendors, and design engineering organizations
Areas of expertise included Assembly (747, 767, 777 structures, panels), Systems Production (control surfaces, hydraulics), and Functional Test and Tooling (structural fab, seat tracks, floor beams).
Team leader & Manufacturing Planner
McDonnell Douglas Aircraft
September, 1986 August, 1992 (5 years 11 months)
Manufacturing Planner As a team leader, produced planning documents and shop floor paper for MD-80 nose section, horizontal stabilizer, floor panels, and seat tracks
Used on-line systems to assure proper interface with QA, Manufacturing, Tooling, Engineering, Liaison Planning and Liaison Engineering
OTHER AEROSPACE EXPERIENCE ;
Structure Mechanic & Assembler
Douglas Aircraft
January, 1979 January, 1986 (7 years)
Employers included
Douglas Aircraft: Sheet metal fabrication, drilling, & installing fasteners
Northrop: Sheet metal fabrication, missiles, and support equipment
Ford Aerospace: Sergeant York Tank
ASTECH TRE: Ship stacks & 757 Exhaust Outer Assy OTHER AEROSPACE EXPERIENCE Employers included: DOUGLAS AIRCRAFT: Sheet metal fabrication, drilling, & installing fasteners. NORTHROP: Sheet metal fabrication, missiles, and support equipment. FORD AEROSPACE: Tanks ASTECH TRE: 757 Exhaust and Ship stacks
Structure Mechanic
Installed seat
January, 1984 January, 1986 (2 years)
tracks in over wing section and slant panel in the wheel well of the MD-80 aircraft
Performed layouts and installed rivets and other fasteners
Achieved certifications in torqueing, crane operations, and blueprint reading
Received recognition for quality jobs performed on time.
Education
Community College
Associate Degree