Jack Perkins

*** ****** ***** *****

Weatherford, TX 76087 US

Phone: +1-817-***-****

ac2yze@r.postjobfree.com

QUALIFICATIONS

I offer 46 years within the construction industry of which over 35 are in management of heavy industrial, oil and gas turnarounds, civil, commercial construction, and custom residential projects with 12 years exclusively in project controls of which the last 7 in management rolls fulfilling project specific contract opportunities in oil and gas upstream, offshore, downstream, as well as mineral processing in addition to 11 years of petrochemical turnaround and power outage management field experience supervising multiple contractors and craft with excellent communication skills.

ROLES

Claims Consultant, Primavera Consultant, Project Controls Manager, Project Controls Advisor, Master Scheduler, Turnaround Scheduler, Lead Scheduler, Scheduler, Project Manager, Site Superintendent, General Forman, Fabrication Shop Forman, Forman, Pipe Fitter, Welder, and Heavy Equipment operator.

SOFTWARE

Primavera Project P5.0; P6.2; P6v7 P6v8

Primavera Project Planner P3.1 (Limited)

MS Projects: (Limited)

MS Office Products (Access, Excel, Word, Power Point)

DEGREE / CERTIFICATIONS

Primavera P8.3 Master Scheduler Baytown TX,

Primavera P5; P6; P6.7; P8.3 Advanced Certification, Houston TX

Primavera P5 Certification, Martinez CA

TWIC Certification Martinez CA

Bachelor, Construction Management, Humble TX

Bay Area Safety Training, Martinez CA

Bay Area Safety Counsel, Houston TX

Advanced Supervisor Training Wichita Falls TX

EMPLOYMENT HISTORY

Self Employed

Investment Property Renovation

October, 2016 Present (12 months)

Remodel personal investment property

Project Controls Manager / Master Scheduler / Mitigation Consultant

Meccon Industries Inc.

August, 2015 October, 2016 (1 year 2 months)

Steam Methane Hydrogen Unit, (25 MMSCFD) 35.1 MM - Husky Refinery, Lima OH / Lansing Ill

Manage Project Controls, Cost, Schedule, and Progress reporting

Develop client approved Baseline P6v8.3

Maintain weekly, and monthly Progress reports for submittal to Linde Engineering

Proof all contractual communications with client

Provided mitigation assistance and documentation to successfully support change order submittals, and delay claim due contractor

Self Employed

Investment Property Renovation

February, 2015 August, 2015 (7 months)

Remodel personal property

Project Controls Advisor / Primavera Consultant / Master Scheduler

TEPCO (Team Enterprise Project Controls Organization)

April, 2013 February, 2015 (1 year 10 months)

Project Controls Advisor - Chevron

Primavera Consultant / Master Scheduler - Monroe Energy

Project Controls Advisor

Chevron South African Strategic Business Unit

March, 2014 February, 2015 (11 months)

Subsea Pipeline and Platform Modifications 2.5B - Houston TX, Katy TX, Paris France, Pointe Noire ROC (Republic Of the Congo), Cabinda Africa, Malongo Africa

Consult best Primavera scheduling practices for baseline schedule development and approval with Chevron and contractor

Develop and maintain daily, weekly, and monthly Progress reports for Chevron SASBU corporate management for Topside Platform Modifications, Well Development, and Subsea Pipeline Installation.

Review and approve monthly contractor invoicing, contractor Schedule, and Forecast

Provide SASBU Management with Monthly Schedule Forecast to Complete prefabrication

Primavera Consultant / Master Scheduler

Monroe Energy

July, 2013 March, 2014 (8 months)

Asset Library Development and Implementation Trainer PA

Developed WBS structure utilizing existing accounting system database for direct data importation enabling the client to streamline turnaround scheduling process

Implementation of a complete resource loaded, logic driven equipment asset library consisting of 31.5k activities in Primavera P6v8

Contract Mitigation Consultant

JR Knowles Consultancy, Hill International

January, 2014 February, 2014 (1 month)

Vale Long Harbour Contract Mitigation 12MM

Remotely Consult details of contractor claims against client through Mitigation process

Project Mitigation Consultant

Contract Mitigation Consultant

August, 2013 August, 2013 (1month)

Vale Long Harbour Contract Mitigation 12MM

Remotely Consult details of contractor claims against client through Mitigation process

Claims Consultant / Master Scheduler

Bearing Sea Environmental

November, 2012 March, 2013 (4 months)

H Power Expansion Project Kapolei Hawaii 4.25 MM

Post Construction Schedule Development for successful mitigation of claim by subcontractor to prime contractor.

Contract Mitigation Consultant

JR Knowles Consultancy Hill International Canada

November, 2012 December, 2012 (1 month)

Vale Long Harbour Contract Mitigation, Houston TX, 12MM

Initiated audit resulting in discovery of over billing and charges outside contract

Remotely Consulted details of client claims against contractor throughout mitigation and settlement process

Consult details of contractor claims against client throughout Mitigation process

Master Scheduler EPCM

Fluor Daniels South America

September, 2012 November, 2012 (2 months)

Beachfield Upgrade Project 250 MM, Port of Spain, Trinidad and Tobago

Developed client approved EPCM Schedule for a natural gas metering station regulating offshore production P6v7

Developed Client Approved Baseline

Advised in the development and integration of the Turnaround Construction Schedule

Project Mitigation Consultant

JR Knowles Consultancy, (Hill International Canada)

August, 2013 August, 2013 (1month)

Vale Long Harbour Contract Mitigation 12MM

Remotely Consulted details of client claims against contractor throughout mitigation and settlement process

Project Controls Manager

Fluor Canada

May, 2011 February, 2013 (1 year 9 months)

Vale Long Harbour Processing Plant Modular Fabrication Facilities 265 MM, Long Harbour Newfoundland and Labrador CAN, Corpus Christi TX, New Iberia LA, Brewer ME, Argentia NF, Vancouver CAN

Project Controls Manager over all Schedule and Cost reporting for 4 modular assembly facilities and Project Alignment with site. P6v7

EPCM Site Schedule Development, Review and Approval

EPCM Modular Schedule Development, Review and Approval

Baseline review and approval for site and all modular facilities

Progress reporting, risk analysis, for site schedule and all modular facilities

Alignment of material deliveries, module, and barge deliveries to modular facilities and site

Final quantity resolution, Contractor Audits

Claim Initiation, Contract mitigation, and Close-out

Management of 7 schedulers, 2 estimators, 1 cost control lead and 1 project controls technician.

Senior Turnaround and Capital / Projects TA Integration Scheduler

TEPCO LLC (Team Enterprise Project Controls Organization)

April, 2010 May, 2011 (1 year 1 month)

Capital Projects Turnaround Integration Scheduler

Senior Turnaround Scheduler

Capital Projects / TA Integration Scheduler

Frontier Refinery

January, 2011 May, 2011 (4 months)

Refinery Turnaround Schedule 44.5 MM Frontier Refinery, Cheyenne WY

Develop, Baseline, and Implement Turnaround Schedules for Capital Integration in Alkylation, FCCU, Gas Con, Scanfiner, and Butamer Units

Update Schedule and Generate Status reports twice daily P6v7

Senior Turnaround Scheduler

Tesoro Refinery

April, 2010 September, 2010 (5 months)

Plant-wide Refinery Turnaround Schedule Development and Implementation, 34.5 MM, Kapolei Hawaii

Develop, Baseline and Implement schedule for Hydrogen Regeneration Furnace re-tube, Flare stack section replacement, Hydrogen Compressor Rebuild

Update Schedule and Generate Status reports twice daily

12.5K activities P5.7

Lead Scheduler

Global Project Services (GPS)

May, 2009 April, 2010 (11 months)

Turnaround Schedule Development and Implementation, 81 MM Tesoro Refinery, Martinez CA

Crude Unit, 6 Boiler turnaround

P5 Integration of Flare, I&E PHA

50 Unit Turnaround Schedules

Daily 3 shift look ahead’s and management reports

P3 to P5 Integration 8.5K activities

Scheduler / Scope Change Coordinator

Innovative Turnaround Controls (ITC)

February, 2008 May, 2009 (1 year 3 months)

Hydrocracker and Reformer Turnarounds 62 MM Tesoro Refinery, Martinez CA

Turnaround Schedule Development and Implementation

Scope Change Coordinator

Project Superintendant

Bearing Sea Environmental

November, 2007 December, 2007 (1 month)

Emergency Refinery Turnaround - 12,600 man-hours 30 employees - 1.76 MM Kapolei, Hawaii

H-501 & H502 Heater emergency re-build

General Foreman

Bearing Sea Environmental

September, 2007 November, 2007 (2 months)

General Piping Improvements - 12 employees 475K - Tesoro Refinery Kapoli Hawaii

Analyzer Equipment Installation and Jet Flexibility with Miscellaneous piping packages

Scheduler

CCSC, Inc.

May, 2007 August, 2007 (3 months)

Remote Development of EPA Construction Delay Claims P5

Scope Change Coordinator / Scheduler

KAP Project Services

October, 2006 May, 2007 (7 months)

Refinery Block Turnaround, 125 MM, Hovensa Refinery St Croix US Virgin Islands

Assist in Development and Implementation of Turnaround Schedule

Scope Change Coordination P5

Superintendent

P2S (Plant Performance Services, LLC)

September, 2005 October, 2006 (1 year 1 month)

Refinery Maintenance - 25,000 man-hours (10 employees) .75MM - Tesoro Refinery, Kapolei, Hawaii

General Maintenance Plant wide

Superintendent

P2S (Plant Performance Services, LLC)

March, 2005 September, 2005 (6 months)

Plant Wide Turnaround 2.75 MM Tesoro Refinery, Kapolei, Hawaii

Planned and executed turnaround,

Replaced Crude Distillation tower head,

Rebuilt and replaced Vertical heater,

180 piping packages,

Miscellaneous Code vessel repairs

45,000 man-hours (150 employees)

Superintendent

P2S (Plant Performance Services, LLC)

February, 2005 March, 2005 (1 month)

Boiler Outage, .5 MM Texas Municipal Power Agency, Collage Station TX

Dissimilar Dutchmen pendant replacement

28,000 man-hours (50 employees)

Planner / Estimator

P2S (Plant Performance Services, LLC)

January, 2005 February, 2005 (1 month)

Tesoro Refinery - 2.75MM - Kapolei, Hawaii

Plan & Estimate forthcoming turnaround

Superintendent

P2S (Plant Performance Services, LLC)

November, 2004 December, 2004 (1 month)

Boiler Outage - 14,000 man-hours (50 employees) 250K - City Public Service, San Antonio TX

Unit 2 Corner tube replacement

Reheat dissimilar weld Dutchmen

Superintendent

Plant Performance Services, LLC

October, 2004 November, 2004 (1 month)

General Boiler Maintenance - 95K City Public Service, San Antonio TX

Coal pipe Replacement

4,500 man-hours (12 employees)

Superintendent

P2S (Plant Performance Services, LLC)

September, 2004 October, 2004 (1 month)

Emergency Crude Tower Repair- 2,500 man-hours (8 employees) - Tesoro Refinery, Kapolei, Hawaii

Repair Crude Distillation Tower Head

Superintendent

P2S (Plant Performance Services, LLC)

February, 2004 March, 2004 (1 month)

Boiler Outage - 14,000 man-hours (50 employees) 250K City Public Service, San Antonio TX

Unit 1 Corner tube replacement, Reheat dissimilar weld Dutchmen

Superintendent

P2S (Plant Performance Services, LLC)

January, 2004 February, 2004 (1 month)

Boiler Outage - General Plant Maintenance - 6,500 man-hours (24 employees) - Nebraska Public Power District, GGS, Sutherland, NE

Reheat spacer cane replacement, General Piping

General Foreman

P2S (Plant Performance Services, LLC)

October, 2003 January, 2004 (3 months)

Boiler Outage - 9,000 man-hours (24 employees) - Garland Power & Light, Nevada, TX

Expansion joint replacement, minor tube replacement, fuel oil piping, acid piping, elevated floor in stack, de-aerator repairs

General Foreman

P2S (Plant Performance Services, LLC)

September, 2003 October, 2003 (1 month)

Boiler Outage - 12,500 man-hours (48 employees) - Santee Cooper, Grainger Station, Conway SC

Secondary superheat and reheat pennant replacement, steam drum internals, coal nozzles.

General Foreman

P2S (Plant Performance Services, LLC)

July, 2003 September, 2003 (2 months)

Boiler Maintenance - 5,000 man-hours (8 employees) - Garland Power & Light, Nevada, TX

Platform & ladder design, fabrication and installation.

Superintendent

P2S (Plant Performance Services, LLC)

April, 2003 July, 2003 (3 months)

Boiler Outage - 9,500 man-hours (42 employees) - Nebraska Public Power District, GGS, Sutherland, NE

Superheat inner loop replacement, reheat inner loop replacement, and view port installation

General Foreman

P2S (Plant Performance Services, LLC)

March, 2003 April, 2003 (1 month)

Boiler Outage - 5,600 man-hours (38 employees) - Southern Companies, Plant McIntosh, Savannah, GA

Economizer change out.

Superintendent

Phillips Services, Inc

January, 2003 March, 2003 (2 months)

Partial Refinery Shutdown, General Maintenance - 3,500 man-hours (8 employees) - Tesoro Refinery, Kapolei, Hawaii

Crude tower repair, sulfur vessel fabrication, hopper liner, tanker station fabrication

General Foreman

Phillips Services, Inc

September, 2002 January, 2003 (4 months)

Boiler Outage - 12,000 man-hours (48 employees) - Garland Power & Light, Nevada, TX

48'' NOx system fabrication & installation, R1 & R3, intake pump grating replacement, expansion joint replacement

Replaced lower 8' of 80' stack.

General Foreman

Phillips Services, Inc

July, 2002 August, 2002 (1 month)

General Refinery Maintenance - 13,500 man-hours (4 employees) Tesoro Refinery, Kapolei, Hawaii

Re-pipe oil & steam, 4 heaters, valve replacement, misc pipe & code vessel repairs.

General Foreman

Phillips Services, Inc

April, 2002 May, 2002 (1 month)

Boiler Outage - 12,400 man-hours (48 employees) - Savannah Electric, Plant Craft, Savannah, GA

Economizer change out, install new casing, re-vamp 2 air pre-heaters, basket replacement, arch replacement, front wall replacement, misc tube replacement.

General Foreman

Phillips Services, Inc

March, 2002 April, 2002 (1 month)

Boiler Outage - 12,500 man-hours (48 employees) - Garland Power & Light, Nevada, TX

60'' NOx duct fabrication & installation, acid wash.

Superintendent

Phillips Services, Inc

January, 2002 March, 2002 (2 months)

Refinery Boiler Outage - 40,000 man-hours (168 employees) - Ultramar Refinery, Martinez, CA

Precipitator collector plate replacement, steam drum internals removal & replacement, duct modifications & repair, valve replacement, code vessel repairs.

General Foreman

Phillips Services, Inc

September, 2001 January, 2002 (4 months)

Boiler Outage - 17,000 man-hours (48 employees) - Garland Power & Light, Nevada, TX

Complete arch header tube replacement, corner fired burner replacement.

General Foreman

Phillips Service Corporation

June, 2001 September, 2001 (3 months)

Refinery Turnaround - 6,000 man-hours (48 employees) Tesoro Refinery, Kapolei, Hawaii.

Alloy tube replacement (heater), code vessel repairs, valve replacement, and misc pipe work.

General Foreman

Phillips Service Corporation

March, 2001 June, 2001 (3 months)

Boiler Outage - 18,300 man-hours (48 employees) Garland Power & Light, Garland & Nevada, TX

Complete burner replacement (6), 60'' NOx system fabrication and installation, 48''x 120' header fabrication & underground installation, 300 LF 48'' underground pipe replacement, 20% super-heat section replacement, misc water wall tube replacement.

General Foreman

Phillips Service Corporation

December, 2000 March, 2001 (3 months)

EPCM assistance to Fluor Daniels, - 12,000 man-hours (48 employees) OG&E McClain, Newcastle, OK

Specialty team to assist in new construction of Power Plant, misc valves & piping, 2'' - 66''

General Foreman

Phillips Service Corporation

October, 2000 December, 2000 (2 months)

Boiler Outage - 18,300 man-hours (36 employees) - Garland Power & Light, Nevada, TX

Fabricate & install economizer inlet header, misc valve replacement, expansion joint replacement, steam coil removal, acid wash piping, air pre-heater re-vamp, cold & hot basket replacement, fabricate & install lower 30' of 100' stack.

General Foreman

Piping Engineering

August, 2000 October, 2000 (2 months)

Refinery Turnaround General Piping - 7,500 man-hours (48 employees) - Tesoro Refinery, Kapolei, Hawaii

Fabricate and install 10'' - 12'' stainless pipe, valves, fittings, miscellaneous piping system modifications & valve replacement.

General Foreman / Superentendant

P2S, (Plant Performance Services, LLC)

August, 2000 October, 2006 (6 years 2 months)

P2S, Plant Performance Services, LLC (formerly Philips Services, Inc, PSC and Piping Engineering)

President, CEO & Project Manager

Perkins Construction, Inc.

August, 1983 August, 2000 (17 years)

Commercial, Residential Construction Management, Concept through Completion

Designed, estimated & managed construction of custom homes & commercial projects from $40K to $1.5MM $3.5MM average annual budget

Project Manager

Better Living Corporation

September, 1980 August, 1983 (2 years 11 months)

Tract Home Subdivision Development and Custom Home Construction

Managed 7 track home subdivisions, 3 custom subdivisions ranging ranging from $300K to $1.5MM $3.75MM average annual budget.