Post Job Free

Resume

Sign in

Project Management Construction

Location:
Noida, UP, India
Salary:
150000
Posted:
October 31, 2017

Contact this candidate

Resume:

CURRICULAM VITAE

a. Name of Person : ATIN KUMAR BISWAS

b. Date of Birth : 14 SEPTEMBER 1955 ( AGE- 62 YEARS )- 100% physically fit, strong, dynamic, dedicated, hardworking and competent person to take care of the responsibility to fulfil your engineering/construction needs. Diversified experience in conceptualization/survey- soil investigation/design/preparation-finalization of tender document/short-listing bidders-open tendering/tendering/evaluation of technical & priced bids/award of job/conducting kick-off meeting/ taking up construction of civil / other infra works. Following are briefly my work domain in the last 36 years of my career in different capacities :

(i) INDIAN INSTITUTE OF MANAGEMENT KASHIPUR- 2 years 8 months Responsible for setting up new campus of Indian Institute of Management, Kashipur in a plot measuring 200 acres with following facilities : a. Architectural drawing / finalization of layout / design of foundation-building / construction / development of 1,18,500 M2 of floor area of buildings as under – i. Land development

ii. Academic building – 17500 M2 floor area in 3- floors iii. Administrative building – 4000 M2 floor area in 4- floors iv. Library building – 6000 M2 in 3- floors

v. Dining building – 4000 M2 in 2- floors

vi. Student hostels – 6- clusters each consisting of 4- nos 4-storey buildings each having floor area of 821 M2

vii. Faculty accommodation – 4 clusters, 5- buildings in each cluster, having floor area of 750 M2 with 3- floors

viii. Staff housing – 3 clusters, 5 buildings 3- storey each ix. Guest house complex – 2 storey building having 24 rooms x. Sub-station building

xi. Hvac building

xii. STP

xiii. Wtp

xiv. Pipelines for HVAC

xv. Pipelines for water supply

xvi. Sewerage system

xvii. Storm water lines

xviii. Horticulture/ gardening

xix. Roads

xx. Boundary wall & gates

xxi. IT network

xxii. Audio-visual system in class rooms

xxiii. Furniture for class rooms

xxiv. Furniture for dining hall

xxv. Equipment for dining kitchen

xxvi. Surveillance system along boundary / gates

(ii) SLR Engineering, Mumbai – for 2 years

a. In setting up real estate property for client in Thane. b. In setting up Bitumen Filling Plant in Bhiwandi

(iii) SAGA GLOBAL Consulatnts, Mumbai – for 2& 1 2 years a. In implementing following projects :

i. Construction of Oil storage terminals in Mozambique (Moputu & Beira cities) ii. Construction of Housing township for ADNOC in Ruwais, Abudhabi. iii. Construction of civil pumping stations along the cross-country pipeline route of British Petroleum in Georgia.

(iv) CUGL (Central UP Gas Limited), Kanpur- for long 6 years b. In setting up CNG / PNG infrastructure in the cities of Kanpur & Bareilly. c. Laying gas pipelines within the city and outside for intake. d. Setting up CNG stations

e. Setting up PNG network for house-hold supply of cooking gas. f. Setting up maintenance team with procurement of spares, technicians for immediate service when needed.

g. Maintaining emergency spares in stores and updating the list based on past consumption history.

h. Maintaining maintenance regular spares as per past consumption figures.

(v) Bharat Petroleum – for the long 30 years

i. in setting up infrastructure viz lpg bottling plant, oil storage depots, import terminal, jetty in JNPT Port, Mumbai, cross-country pipelines in India, ware-houses, staff housing colonies, maintenance of LPG plants/ bitumen plants/Lubricant Filling plants/equipment spares procurement, inventory control/Annual Maintenance Contract for machines/compressors etc

j. Maintenance/ upkeep/spares/fire drill etc for Fire Fighting set up incl maintaining adequate storage of water for fire fighting purpose. c. Total Experience in design/ project management/quality control/monitoring & site supervision, of setting up civil engineering infrastructure : Competent person with 36 Years of experience in project management, construction, procurement, quality control, site supervision, project monitoring, fortnightly review of progress, generating progress reports for higher management perusal, cost control and safety in civil engineering construction for setting up buildings / roads / water supply / drainage / utilities / yard lighting / landscaping / horticulture / furniture / IT backbone with server & networks / surveillance system / security house / gate / boundary wall / deep tube well / de-watering for deep excavations etc. d. Professional Qualification:

1) BE ( Civil) from JADAVPUR UNIVERSITY, KOLKATA in 1980 2) Well versed with MS Word, MS Excel, Power Point Sr

No

Name of University Date From Date To Degree obtained 1 Jadavpur University,

Kolkata

1976 1980 BCE ( Honours )

e. Key Domain Area / Responsibilities :

Planning Scheduling& Controlling Site Activities

Timely project completion with Quality control.

Ability to liaise with contractors and consultants Able to act on own initiative and in proactive way Good communication skills

Cash flow management

Business Development

Other Roles :

• Monitoring / Checking of materials and machinery utilization for construction activity planned / scheduled.

• Construction of road construction activities like Earthworks, sub-base course, base course, BM, PM etc in Flexible pavements, DLC, PQC in Rigid pavements of highways, runways, apron works, Bridge Foundation. Sub structure, PSC girders, Deck Slab

• Infrastructure developments like sewerage system, storm water drainage, Water line, etc. in proper mobilization as per the programme, BOQ & Technical Specifications

• Quality Control & Assurance at site.

• Co-ordination with consultant, architects, designer, contractors, sub- contractors, suppliers, labor contractors, etc

• Progress reviewing periodically with all stake holders.

• Quality assurance of construction as well as quality of materials supplied.

• Safety at site.

• Ensuring Monthly project report 1st week of following month.

• Appraising higher authorities at every stage of progress in comparison with bar-chart of progress planned vs actual including financials. f. Specialization and Expertise:-

1) Soil & foundation engineering

2) Working knowledge in computer application viz. MS Word, MS Excel, Power Point g. Professional Experience:

SR.

NO.

YEAR

ORGANISATION

POSITION

TYPE OF WORK DONE

FROM

TO

1

May 2014

31 Jan

2017

IIM KASHIPUR

Chief

Engineer

(Project)

• Planning, Budgeting &

Scheduling New Campus

of the Institute at earst-

while escort farm land.

• Appointment of Project

Management Consultant

for the project.

• Appointment of Architect-

cum- Campus Designer.

• Engagement of Contarctor.

• Soil investigation / survey

of the plot of land.

• Preparation/ approval of

Master Plan for the

project.

• Due diligence of design

of facilities as per Design

Basis Report finalized

finalized in consultation

with owner.

• Preparation of contract

document &

tendering/awarding/executio

n/contract administration/

site supervision/monitoring

/review

• Daily evening meeting

with all stake holders to

sort out any technical/

other problems affecting

progress.

• Ensuring supply of all

related materials required

as per bar-chart of daily

activities planned.

• Ensuring adequate labor

and their camp for

execution as per

schedule.

• Ensuring supply of

seasonal materials viz

bricks with advance tie-

up with brick kiln owners.

• Ensuring quality check of

materials being supplied.

• Ensuring construction

quality by proper training

to supervisors / project

engineers etc.

• Progress review with bar-

chart and analyzing delay

if any to find out reasons

for delay and action need

to be taken to over come

the short comings.

• De-watering issues to be

tackled as per procedure.

• Engagement of TPIA

services wherever

necessary.

• Installation of HVAC system

with procurement/installation

of chillars/ heat

pumps/piping/fittings/valves/pu

mps/filters etc

• Installation of solar heating

system of water to be used

for hostels / family quarters

• STP

• WTP

• SUB-STATION

The project of IIM Kashipur new

campus was divided into 2-phases.

Phase-1 costing 450 crores was under

execution under my leadership.

Following facilities was envisaged :

1) Academic Building

2) Administrative building

3) Library building

4) Dining building

5) Student hostels in 6- clusters

6) Faculty quarters in 4- clusters

7) Staff housing in 3-clusters

8) Utilities

9) Furniture for class rooms

10) Audio visual for class rooms

2

10th

March

2012

19th May

2014

SLR Engineering

Pvt Ltd

Chief

General

Manager

1. Business development.

2. Bidding for projects in civil

infrastructure sector.

3. Taking up projects.

4. Checking of design / drawings.

5. Execution, monitoring till

completion.

6. Measurement & Billing

7. Follow up for payment.

Projects handled are :

a. Setting up Housing

township in Thane,

Mumbai

b. Setting up infrastructure

for Bitumen Plant in

Bhiwandi, Maharashtra.

3

5th

August

2011

28th Feb

2012

SAGA GLOBAL

Consultant

Roles and Responsibilities

include :

1. Guiding the team in

project management.

2. Carrying out design by

design experts in the

field.

3. Preparation of BoQ &

scheduling of activities.

4. Progress review

5. Corrective actions

6. Ensuring safety / QA&QC

at construction site

Project :

1.Office complex, staff

housing for ADNOC,

Abudhabi.

2. Pumping stations for BP in

Georgia.

3. Oil Storage/ distribution

terminal in Mozambique

4

Feb 2005

31st July

2011

CUGL, Kanpur

Head-Project

Roles and Responsibilities

include :

1. Planning.

2. Budgeting.

3. Scheduling

4. Appointment of PMC

5. Rolling out project

execution including

obtaining all necessary

NOCs from gov etc

Achievement :

• Set up infrastructure for

CNG facilities in the cities

of Kanpur & Bareilly.

• Laying pipelines for

transportation of gas

from Bareilly to its

industrial hob.

• Construction of CNG

stations within Kanpur

and Bareilly cities incl

approach road,

installation of heavy

compressors, dispensing

units, odorisers, metering

system etc.

• Taking up pipeline works

for connecting house

holds in Kanpur and

Bareilly.

• Reduction of Air

Pollution in Kanpur.

• Connecting gas

pipelines to IIT, Kanpur

for its canteens.

5

11 th May

1981

Feb 2005

BPCL ( in its Civil

Wing )

Procurement

Leader

&

Project

Manager

• Designing of facilities.

• Cost estimation of

project based on market

databank for rates of

works/ materials.

• Budgeting materials

requirement after

obtaining feed back from

various project wings.

• Floating tenders for

works/ procurement.

• Contract administration.

• Preparation of SOR for

materials/ repetition

jobs.

• Execution of contracts

based on

design/drawings/tech

specifications.

• Monitor/update the progress

of work as per the schedule.

• Commissioning of units

and handing over

• Listing mandatory spares

and maintenance spares.

• Listing OEM agencies for

procurement.

Achievement :

1. Construction of

staff quarters for

officers ( 5- 8 storey

buildings in Noida )

2. Construction of jetty and

approach trestle at JNPT

Port, Mumbai.

3. Construction of import

terminal at JNPT.

4. Construction of staff

quarters in Mahul refinery

complex in Mumbai.

5. Materials procurement

using SAP in Noida office.

6. Constructed approach road

to airport runway in

Kolkata.

7. Constructed cross-country

product pipelines from

Manmad to Indore in M.P.

8. Construction of storage

terminals all over the

country incl all allied civil

works.

9. Maintenance of the

facilities.

10. Operation of LPG plant in

Uran

11. Maintenance of plant

12. Conducting fire drill with

neighboring industries

13. Managing work force

14. Dealing with trade unions

Training Course And Workshop Attended:

TRAINING

SL

NO Subject Period Venue

1. Basics of Computer Education 7-

days

ACE, Kolkata

2. Basics of Project Management 5-

days

Project Management Associates, Noida

3. Seminar on Paradigm Shift in Project Management 5- days

India Habitat Centre, Delhi

4. International Seminar on Concrete Technology 3- days

Hotel Taj Palace, Delhi

5. Project Management 3-

days

Project Management Associates

6. Managerial Effectiveness 5-

days

Administrative Staff Collage of India ( ASCI), Hyderabad 7. Team Building 5-

days

HR Consultant, Bhubaneswar

8. Supply Chain Management 5-

days

MDI, Gurgaon

Professional Membership

1. Member of Institution of Engineers, India ( MIE ) 2. Chartered Engineer

h. Languages:

Language Read Write Speak Understand

English Excellent Good Good Good

Hindi Excellent Good Good Good

Marathi Excellent Good Good Good

Certification:

1. I am willing to work on the project and I shall be available for entire duration of the project assignment and I will not engage myself in any other assignment during the currency of his assignment on the project. 2. I, the undersigned, certify that to the best of my knowledge and belief, this bio- data correctly describes myself, my qualification and my experience. 3. I also confirm that I shall work in a transparent manner with integrity, honesty and goodwill, as a team leader of Project Team. 4. I shall also guide juniors to deliver as per Institute’s expectation. Signature of the Member

(Resident of Greater Noida) Place : Greater Noida

e-mail id- ac2151@r.postjobfree.com Date : 21.10.2017 Cell no. 967-***-****

989*******



Contact this candidate