Name : Rajarama Rao
Profession : Marine Civil Engineer/Coastal engineer/ Maritime Engineer/ Port & Harbor Planner/Waterfront
engineer.
Total years of experience : 12 years
Presently working : Egis India Pvt. Ltd
Contact Details
: Email : ac1m24@r.postjobfree.com
Date of Birth : 15th March 1981
Nationality : Indian Passport
Area of Specialization : Marine / Structural Engineering International work experience : 2 years, UAE
Driving License : UAE, Valid till 2020
Key Qualifications:
Mr. Raja has twelve years of experience in Design of maritime structures, Pile foundations and Coastal engineering. Work Experience includes, Detailed Design of Port and Harbor Structures. He has extensively involved in Preparation of Techno Economic Feasibility Reports, Preliminary Project Reports and Detailed Project Reports. He has effective knowledge of structural design software’s like STAAD-PRO confirming to "Limit State Design" for British (BS 6349, PIANC), American (API, AISC, CEM) and Indian standards. His present assignments in planning of underground metro tunnels, defence terminal and refinery expansion projects. CURRICULUM VITAE RAJARAMA RAO
Page 2 of 12
EDUCATION AND QUALIFICATION
Professional History:
Degree Name of University Year
B.E (Bachelor)
Civil
Visvesvaraya Technological University,
India
1998-2002
M. Tech (Master)
Marine Structures
National Institute of Technology, Karnataka.
Surathkal. India
2004-2006
April 2016- Till date
Feb.2011- March 2016
March 2009- Jan.2011
July 2006 – Feb 2009
Sept 2004- June 2006
June 2002 - August
2004
July 1998- May 2002
Egis India Pvt. Ltd
Sr. Specialist – Marine
Manager-Ports & Terminal
Essar Engineering Ltd,
Sr. Marine Design Engineer
Parsons International Limited.
Abu Dhabi, UAE
Sr. Engineer (Maritime Division)
Haskoning India Pvt. Ltd., a Royal Haskoning Company, India Masters (Marine Structures)
National Institute of Technology, Surathkal, India Engineer- Shilpa Constructions, Mangalore.
Degree (Civil Engineering)
V.T. U, Karnataka
Detailed Employment
Record:
Client List
Sr. Specialist – Marine
Egis India Ltd
JNPT, Fisheries dept.
PWD Mumbai.
Tender preparation for JNPT 4th container terminal. The work involves review of geo-technical investigations, dredging, design basis, tender documents evaluation.
Gujarat Fisheries department project. Detailed project report for Viraval, Okha and porabunder ports.
Technical review of shivaji project reports.
CURRICULUM VITAE RAJARAMA RAO
Page 3 of 12
Essar Ports Ltd, Essar
Projects Ltd.
Manager-Ports & Terminal
Essar Engineering Ltd,
Feb.2011 – March
2016
Beira Coal Terminal
Prepared TEFR report for coal and iron terminal at Beira port. Responsible for preliminary design and delivery of drawings for coal jetty at Beira port, The design includes analysis of piles, fender panels, beams and slabs of jetty.
Beira Iron ore Terminal
Preliminary analysis of iron ore jetty at Beira port. The work involves analysis of soil report, preparation of design basis. Pile design, pile cap, beams and slabs. Production of tender drawings for the same work. Preparation of dredging drawing and calculation of dredging quantities for iron ore Terminal. Green field port at Savane
Preparation of master plan layout for green field port at Savane. The tasks include study alternative locations for the port project. Review mathematical model specifications, dredging Quantities and layout of breakwater for the same project.
The study involves preparation of TEFR for coal and iron ore handling. The scope involves, arrange tender documents for bathymetry survey, seismic survey, Topographic survey etc. Tori Barrage project:
The project involves detail design of barrage, gates, retaining wall and earthen bunds.
Engineer involved seepage analysis of barrage, layout preparation and selection of retaining wall and design of cross section of earthen bunds.
Paradip Coal Terminal (BOT Project)
Design of 370 m length of coal terminal with cellular type diaphragm wall. Preparation of shore protection for quay side wall. Engineer involved for PMC services of the coal terminal CURRICULUM VITAE RAJARAMA RAO
Page 4 of 12
includes, preparation of EPC schedule using primavera software. Duties involved preparation of monthly progress reports. Checking BOQ submitted by the engineering department, and get approval from the client.
Attending meeting with clients, preparation of progress reports, co-ordination between site and office works.
Jurong Aromatics Complex Project, Singapore
Design of pipe rack sleepers for refinery site project. The study involves foundation design of sleepers, analysis of soil data, preparation reinforced drawing details.
Aqaba New LPG terminal – Jordon
The scope of works includes design of new terminal for unloading of LPG including approach structure, Pipe Bridge, abutment at landfall point and continued pipeline up to tie-inn Location near existing LPG pipeline. The LPG Terminal facility includes Mooring and berthing dolphins, Fenders, bollards & other marine fixtures, Service platform with seating for Loading arm & other components, Approach trestle and pipe bridge. PCS Napata Jetty, Singapore
The study involves layout finalization of Napata jetty for Jurong island. The work includes soil study, dredging requirement for approach channel, orientation of berthing and mooring dolphins. Preparation of design basis, cost estimates.
Dangotte Project, Nigeria
The project involves study location for RO RO jetty at Dangotte refinery site. The work involves preparation of RFP documents for bathymetry survey, geotechnical study. The engineer involved in preliminary design of berthing structures. Analysis of pile berthing structure, berthing energy calculation, preparation of various drawings and BOQ for approval stage.
CURRICULUM VITAE RAJARAMA RAO
Page 5 of 12
Vadinar Expansion Project: (BOT Project)
The duty involves preparation of EPC documents for refinery expansion project. The work includes planning and co-ordination of all engineering discipline to complete the assignment in time. IOCL MBLAL Project
The duty involves deign of foundations for water tank at 12m height, Specifications for steel fabrication works, prepare building drawings of control tower, pipe rack supports for firefighting lines, PMC documents for all civil and Mechanical works.
March 2009-
Jan.2011
Sr. Marine Design Engineer
Parsons International, ABU-DHABI, UAE
TDIC
Guggenheim Museum - Prepared various alternatives for the location of breakwater design, drawings of working platform, drawings for platform location, sections. The design includes calculation of run-up, wave transmission,overtopping, discharge volumes, sizeing of armour units.
North western Promenade - Prepared design report, cost estimate for various alternatives on”Preliminary design of north west promenade.
North beach setps designs, headland creation, piled look - out point designs for saadiyat island.
TDIC jetty breakwater - Prepared design & drawings for breakwater, Commented on contractors drawings.
Prepared report of “Design Considerations for the
Breakwater to Protect TDIC Jetty”.
Marina B - Design of temporary & Permanent Edge
protection. Prepared drawings for reclamation & Edge protection. Anyalysis cost estimate for various
alternatives. Prepared preliminary design report for marina edge protection
CURRICULUM VITAE RAJARAMA RAO
Page 6 of 12
Zyed canal- Works involved fixing alignment for two- kilometer-long canal. Design includes canal edge wall, weir and abra stations. Broad crested weir including hydraulic calculations, pumping rate and discharges. Abra stations designs for different locations in canal. Three alternative Designs for the canal edge protection are studied, i.e, Precast Concrete Block Wall, L-shape precast concrete retaining Wall, Geo-Grid with precast block. All detailed engineering calculations, drawings are prepared. The design of underground tunnel for two-way traffic for roadways.
Desert Islands- Prepared Design Criteria for Dive Bay Marina. Analysis piling system for access bridges in Dive bay Jetty. Reviewed specifications for pontoons, walkway units, Flotation units.
Feb 2009- July 2006
Sr. Engineer (Maritime Division)
Haskoning India Pvt. Ltd., a Royal Haskoning Company Reliance Industries
2008-2009
Design Consists of 750m Jetty wall with Sheet Pile, Sea bed scour protection using Fabri form mattresses for 7000 sq.m, at Jamnagar.
Beach Development - Marine Grade Steel Sheet Piling, Dredging, and Beach Sand under water and beach front, Rock Barrier Dam, Revetment with armored rock 1.1 Km length. Sheet Piling - 100 m long, dredging 10x40m.
Design for replacement of old pile cap to new pile using pre-cast pile cap as a permanent shuttering including walkways in between. Finalizing requirements/
specifications in consultation with others in the
organization.
CURRICULUM VITAE RAJARAMA RAO
Page 7 of 12
ONGC
2008-2009
Mr. Rama was responsible to design of Sea Water Intake Pipelines related civil works at Inlet Risers, Pump House at Kakinada.
Marine works including dredging, excavation and
backfilling. Installation of amour stone, rock blanket, quarry run etc. Design & construction, erection of velocity cap. Construction of temporary cofferdam by sheet piles.
Construction of new docking/berthing facility / jetty, supply of materials.
Designing various other layouts of the projects after comprehending the needs of the clients.
Mumbai Port Trust
2007-2008
Detailed Design of Second chemical berth at Pir Pau. The tasks completed:
Assistance to prepare Inception report for above mentioned project.
Setting up of design criteria of Marine civil works. Design of berthing structures includes two no. of berthing dolphins, four no. of Mooring dolphins, a service platform to cater seven marine loading arms and a combine
roadway and pipeline trestle of 650m length.
Designs of all berthing structures are done in STADD modeling as three dimensional space structures. The work involves analysis of the structures as per Indian code standards.
Designed the berthing dolphins includes selection of fenders i.e Calculations of berthing Energy, deflection of fenders, Design of fender panels, Calculations of mooring loads etc.
Involved in preparing draft tender documents for dredging CURRICULUM VITAE RAJARAMA RAO
Page 8 of 12
includes engineering drawing for dredging and calculation of dredging quantizes in soft & hard rock soils.
Ministry Of Transport
And Communications
Sultanate of Oman
2007-2008
Mr. Rama worked for new port and Dry dock complex at Duqm. The work involved designing Quay wall (gravity type) for naval ships. The task includes preparation of Boat mix, marine tunnel, calculation of berthing energy, mooring analysis, Loading Analysis for quay wall and preparation of engineering drawings. The study involves preparation of preliminary design report, detailed engineering report for the work.
Mazagon Docks
Limited.
2007-2008
Engineer involved to do design checks for Goliath Crane foundations. The study involved identification of crane loads over the rails, alignment for Hinged & fixed legs of the crane. Checking the drawing prepared by the crane consultants.
Kolkata Port Trust
2006-2007
Engineer involved in preparation of Business Plan for Kolkata Port Trust. The task includes preparation of Master Plan for port, land use / Land cover plans, Traffic forecasting and SWOT analysis. Database plan was
created with the help of Arc GIS to functionalize future port handing activities
Andaman and
Laksadweep Harbour
works.
2006-2007
The project duties are preparing layout for passenger jetty in Kachtal and Terasa Islands. The engineer involved fixing up marine borehole for site Investigations. He guided the Geo-technical team for fixing the marine bore holes in the Bay of Bengal and given technical
specifications for soil investigations. The task includes preparing engineering drawing, study subsea soil data.
The work involves proof checking of design for chemical CURRICULUM VITAE RAJARAMA RAO
Page 9 of 12
Afcons Construction
Pvt. Ltd
2006-2007
pier at Trinidad. The assignment involves alternative design of berthing and mooring structures. The alignment of the trestle which includes mono-piles of 1000mm dia steel piles. The design includes review of the load combinations given by the client, checking the design loads and preparing the alternative drawing for the same.
The same project, Engineer involved in cost estimates for civil components of the petro–chemical pier.
Goa ship yard
2006-2007
Mr. Rama acted as Design engineer for repair berths in Goa. The design includes pilling structure of 250X15m size elevated dockyard with lifting facilities, crane movements as per Indian code standards.
Preparation of Structural design of piles and drawings for the project.
Attending to the meetings with the client/ Architects & office colleagues.
Preparation of design manuals and quality control system in the office, including the drawing record and transmittals data.
Attending site meetings related to quality control and project management.
Mauritius Port Authority
2006-2007
Mr. Rama was responsible for detail engineering studies for development of Cruise terminal at Mauritius which includes,
Determine the most suitable location for the construction of cruise berthing facility near the Caudan Waterfront taking into consideration access for small crafts to the inner basins of Caudan.
Prepared dredging drawings to achieve sufficient depth for the berthing of cruise vessels at the berth and the CURRICULUM VITAE RAJARAMA RAO
Page 10 of 12
approaches.
He prepared preliminary designs, drawings and cost estimates for different options for approval, identify the most economical and operationally viable design as per British Standards.
2002 June-to
2004 August
Engineer- Shilpa Constructions, Mangalore
Major Responsibilities
Tasks Involved Design of multistory building with isolated footings.
Site inspection of Pre-casted concrete works including construction of plinth beams, doors and windows.
Involvement of Redi-Mix concrete construction of different levels of slab in the residential apartments.
Built up area – 35,000 sq.ft,
Responsible for reinforcement, shuttering and concreting of slabs, beams and columns.
Responsible for the layout of internal partition walls, column marking, foundation marking etc.
Responsible for the supervision of internal and external sanitary and plumbing works.
Active participation in project management and estimation of quantities.
Supervising all construction activities including providing technical inputs for methodologies of construction & coordination with Site Management.
CURRICULUM VITAE RAJARAMA RAO
Page 11 of 12
Preparing & reviewing Method Statements, Work Specific Quality Control Plans, documents etc.
Persuading with local authorities for clearances and approvals.
Material planning for the assurance of complete material in flow.
Regular following up of the contractors, consultants and suppliers regarding any clarification of drawings required for the execution of work, procurement of material in time. Other experience
Undergone six weeks training in Remote Sensing and Geographical Information System with respect to water resources application at RRSSC, ISRO, Bangalore. The project includes identification of malaria affected area, cause of the disease, spreading of disease and control measures for the same. During the course engineer
involved to digitize the topo maps, analyzing the satellite imagery to cadastral level. Software handled for this project are ERDAS, Arc view, Arc map.
Technical paper presented on Coastal Zone Information System for D.K Coast in International conference held in Hyderabad during June 2006.
M. Tech Project
Analysis and Design of Oil Jetty for New Mangalore Port with allied facilities for crude oil bunkering.
Coastal Zone Information System for D.K Coast by using RS, GIS and V.B 6.0.
STADD Pro, SACS, Auto CADD, OPTIMOOR, ERDAS, Arc
CURRICULUM VITAE RAJARAMA RAO
Page 12 of 12
Software Knowledge GIS, MS Project, Primavera.
Membership
1 American Society of Civil Engineers (ASCE)
2 New Civil Engineer, UK (NCE)
Languages Known
Speaking
Reading
Writing
English Excellent Excellent Excellent
Hindi Excellent Excellent Excellent
Arabic Little None None
Visited Countries
England
Scotland