CURRICULAM VITAE

I have an Overall ** years’ abroad experience with Supervisor/Superintendent/Engineer of Piping, welding in construction of refineries, Power, petrochemical, fertilizer, Water Desalination plants, pipelines, and other facilities related to the transportation and processing of oil and Gas project.

Post apply for : Mechanical Superintendent-Piping

Applicant : Nityanand Singh

Father’s Name : Ravi Pratap Singh

Religion : Hindu

Marital Status : Married

Permanent Address : At Post - Sakhwania,

Tola - Bandhuchhaper

Dist - Kushinagar (Uttar Pradesh)

India- Pin - 274402

GSM- +91-956*******

E-mail Address : ac13vm@r.postjobfree.com

ac13vm@r.postjobfree.com

Skype : nityanandsingh2

Objective:

Experienced and accomplished Piping Superintendent with a proven track record in managing installation of piping for Power Plants, Refineries and Industrial/Commercial construction operations on a large scale and supervising the layout, assembly and installation of various size and type of drainpipe. Experienced leader recognized for building strong contractor and staff relationships while leveraging excellent analytical and strategic planning and pursuing a commitment to excellence. Seek a leadership position where strong knowledge of Project oversight, creative problem solving, and professionalism are held at a premium for an organization poised for extraordinary growth.

Educational Qualification : Bachelor of Science from University of Gorakhpur ( Uttar-Pradesh )

Professional Qualification : Diploma in Mechanical Engineering, Chennai.

Computer Proficiency : Windows XP, MS office Applications, Internet & access, power point

Safety Courses : H2S awareness & escape

: Enhanced Site Supervision Project- ESSW

: Fire Extinguisher Course

: Hazard Identification and Communication

: STOP (Safety Training and Observation Program)

: Basic First Aided Courses

: Job Hazard Analysis Training Courses (JHA)

: HSE for Supervisor

: PTW (Permit to Work)

Responsibilities

• Total responsible for all site activities and sole company representative onsite.

• Monitor work progress closely with planning engineer and determine areas of possible variation orders.

• Able to follow-up project cost performance (LOP) of project and advise management where necessary.

• Direct and manage project development from beginning to end.

• Define project scope, goals and deliverables that support business goals in collaboration with senior management and stakeholders.

• Develop full-scale project plans and associated communications documents.

• Effectively communicate project expectations to team members and stakeholders in a timely and clarification.

• Liaise with project stake holders on an ongoing basis.

• Estimate the resources and participants needed to achieve project goals.

• Draft and submit budget proposals, and recommend subsequent budget changes where necessary.

• Where required, negotiate with other department managers for the acquisition of required personnel from within the company.

• Determine and assess need for additional staff and/or consultants and make the appropriate recruitments if necessary during project cycle.

• Set and continually manage project expectations with team members and other stakeholders.

• Delegate tasks and responsibilities to appropriate personnel.

• Identify and resolve issues and conflicts within the project team.

• Identify and manage project dependencies and critical path.

• Plan and schedule project timelines and milestones using appropriate tools.

• Track project milestones and deliverables.

• Develop and deliver progress reports, proposals, requirements documentation, and presentations.

• Determine the frequency and content of status reports from the project team, analyze results, and troubleshoot problem areas.

• Proactively manage changes in project scope, identify potential crises, and devise contingency plans.

• Define project success criteria and disseminate them to involved parties throughout project lifecycle.

• Where required, coach, mentor, motivate and supervise project team members and contractors, and influence them to take positive action and accountability for their assigned work.

• Conduct project postmortems and create a recommendations report in order to identify successful and unsuccessful project elements.

• Develop best practices and tools for project execution and management.

• Shall ensure progress reports are prepared and submitted for client approval promptly.

•Ensure site activities are executed without LTIs.

1:- All-embracing knowledge of structure/ piping/ equipment fabrication/ blasting/ coating / painting, bending and computerized inspection tracking systems.

2:- Profound knowledge of the industry technology Installation techniques internationally recognized Codes and standards – API, ASME, ASTM etc. along with necessities for the inspection and Certification of material and associated equipment experience in writing /reviewing welding quality And tasting procedures combined with experience in the harmonization of hydro& pneumatic testing.

3:- Field supervisions, Quality control Inspection shop fabrication.

4:- Total experience in construction (site& fabrication shop) related to Oil& Gas plant, petrochemicals in Abroad.

5:- Directly reporting to the Site Manager, Construction Manager, Piping Manager, Planning Engineer, Site Engineer, QA / QC Engineer for work progress and daily activities.

6:- Line checking as per the Isometric and P&ID Taking charge for field execution, mobilize optimum work force and equipment to achieve the work Schedule as per project requirement.

7:- Preparation of daily work progress reports and inspection reports.

Project Construction Cost: 1.4 BILLION USD

•Saipem Saudi Arabia ( Feb 07, 2017 to Apr 03, 2017 )

Client: Petro Rabigh

Designation: Mechanical Superintendent ( Piping )

Project: Petro Rabigh RP2 ( Saudi Arabia )

Manage of Projects, Subcontractors Meetings, Site supervision and Engineering subjects.

Team Leadership • Strategic Analysis • Communications • Mentoring • Analysis & Planning

Drain Pipe Installation Oversight • Staff Training/Development • Vendor Relations • Negotiation

Process Streamlining • Operations Improvement • Workforce Scheduling • Hydraulic and Pneumatic Equipment.

Euro Mechanical, Abu Dhabi ( Apr 01, 2014 to Oct 30, 2016 )

Client: Adgas ( Das Island )

Designation: Piping Superintendent

Project: SRU Train 2 & 3 ( Brownfield Project )

Project Construction Cost: 3.2 BILLION USD

Mechanical Erection Works, Pump installation, commissioning and start-up and other equipments installation and start-up. Piping Erection Works: Refinery Piping installation, Testing, Flushing and start-up activities

•Saipem eni, Abu Dhabi ( July 16, 2012 to Dec 31, 2013 )

Client: Al Hosn Gas

Designation: Mechanical Supervisor ( Piping )

Project: Shah Gas Development Project EPC - 2 & 3 Hameem, UAE

Duties and Responsibilities of :- Responsible for the project unit Mechanical and Piping

Mechanical/piping/Hydro testing :- Should for the new equipment and life time extension.

Pre commissioning :- Of all retained exiting equipment such as pump, combustion air blowers, Incinerator air blower, CO2 capture blower, Acid Gas Pre-heater, Air Pre-heater, Waste heat boiler 1&2, Condenser 1 & 2, Sulphur cooler, Lean/Rich Exchangers, Reactor, Regenerator Re-boilers, LP Blow down drum condenser, Tail Gas Heater, Reaction Furnace, Main Burner, vessel, Tank, etc. manage quality of the should man hours weekly monthly Status reporting equipment Installation coordinating.

2- Activity planning, work scheduling and monitoring. Inter disciplinary checks and co-ordinates, guiding in the Preparation of plot plans, Equipment layouts, piping layouts and reviewing the design calculations, piping Stress analysis. Preparation of design basis, project specification for EPC project and other project involving Basic/details engineering feasibility studies and tenders document preparation, Material engineering which Include for purchase requisition, Technical bib analysis, vendor document /drag evaluation after order, Construction engineering activities including MTO Shop drawing and job package preparation and issue. Site Survey for job and bids, co-ordinate with internal departments, client and inspection agencies Review of bid enquiry documents and clarification/qualification, estimation activities like MTO, Fabrication and material cost estimation

3- Execution and achieving the scope of works as per the project construction schedules and goals.

4- Responsible for piping studies, drawing and isometric, piping material specification, Valve specification, MTO Material / purchase requisition, Technical evaluation of piping items, Generation of insulation and painting report, stress analysis for all critical piping including piping for pump etc. Selection and marking of pipe supports, Preparation of design basis field engineering. Responsible for installation, assembly & alignment of various static and rotary equipment and structural work with Help of drawing Reviews and implement design criteria and specification as per project requirement.

Performing preliminary design of rotating equipment as required.

Installation of all process & utility piping on the existing Gas plant with new cryogenic Tank including tie-in

Works demolition the existing fire water cement lined piping & replace with Glass reinforced Fiber pipe.

Replace the existing pipe connection on the fire water pump station with Duplex stainless steel pipe.

Study the project drawings, specification and Bill of materials.

Coordinate with the plant operator for the scheduled piping tie-in to the existing line.

Conduct piping hydro test Inspection, initiate exemption item list and approved hydro test packages.

Ensure that safety regulations and requirement of the company, safety Manual are observed at all times.

Investigate repetitive causes of Inspection request rejection and propose alternative or corrective measures.

Verify during the day the progress on site and compliance with the Daily work program.

Prepare site logistics plan including required carnage and other equipment maintenance schedule.

Perform trouble-shooting activities by carrying out engineering detailed studies for any reported Mechanical Equipment failure.

Mechanical commissioning and overhauling all types rotary & static equipment like as pump, compressor, valve, Boiler, heat-exchanger, pressure vessel etc.

Preparing for material submittal for approval as per specification preparing inspection request to client

Preparation of time schedule chart. Execution & supervisor of the project unit supervision Mechanical Engineer & supervisor.

Saipem eni ( Ersai ), Kazakhstan ( Feb 08, 2011 to Nov 01, 2011 )

Client: AGIP KCO

Designation: Piping Supervisor

Project: Inshore Hook Up Project, Kuryk.

Responsibilities:

•Progress monitoring, Reviewing and Reporting to client/Management and taking corrective action to control the progress.

•Attending progress review meeting with client, Minuting and conduct internal meets.

•Project management including material resource planning staff supervision, appraisals and motivation working with multi-discipline team, production of weekly and daily reports.

•Co-coordinating and follow up engineering and procurement activities including controlling & distribution of document and engineering drawing at project.

•All over Piping in charge of MODULE-2.

•Set up New Workshop according to project volume.

•Press machine, Drill machine, Angel cuter machine Auto blasting machine etc.

•Attend internal meeting.

•Weekly & daily progress report sends to construction manager & project managers.

•Achieve should required to client.

•Internal estimation for consumable materials.

•Coordination with material transportation.

•Coordination with QC/HSE departments.

•Attend every day tool box meeting.

•Piping & structure, blasting & painting.

•Fabrication monorail, tanks.

•Supervision of multi discipline workforce including pipe fitter, welder, rigger, structural discipline.

•Supervision of hydro tests & pre-commissioning of piping system.

•Responsible for the application of issuing of permits to work and Risk assessment.

•Attended daily Meeting with management and giving progress Report.

•Material identification and marking of components.

•Fabrication of Annular and bottom plates, cell plates, wind grinder,

•Fabrication of plates for Floating roof and cone Roof, sump, Nozzles’, Manholes and COD.

•Fabrication of structural stairways, ladders, approach and loading, plate form handrail etc.

• Erection of Annular plates, Installation of Bottom plates, Tank cell plates and wind grinder, single Deck floating Roof, initial lifting of the Roof.

•Prepare procedure of MPI, UT, RT, and Tank with hydro testing, Painting Primary and Secondary seal Erection.

•Maintenance and Dismantling of Nozzles and spading of Vessel for isolating its process.

•Manhole opening.

•Internal cleaning of the vessel for rendering its fits for cutting and welding works. Clean with high pressure Hydro jetting.

•Taking physical Measurement of the existing vessel and the spare conical section and ensure that there will be no problem for Fitment.

•Cutting and removal of the bottom conical section from circumferential weld joint as marked on the General Arrangement Drawing.

•Carry out all the inspection and testing according to ASME Section VIII and as specified in Para C Quality control requirement.

•The entire fitment dimension with external piping and other items shall be according to drawing and site conditions.

•Painting on the external surface at welded portion and anywhere welding alteration have been carried out.

•Plate layout for shell cone and dish structure support.

•Supervision of hydro test and calibration tasting.

•Gage and manifold before tasting and provide report to the client.

•Inspection of row material before fabrication.

•Vacuum test shell be carryout as per API 650 clause 6.6 bottom plate weld using vacuum testing Equipment with a vacuum of 0.21bar (g) to 0.35bar (g).

•Shall to bottom plate welds shall be carried out Oil Check leak test .

Project Construction Cost: 3.18 Billion USD

Petrofac Engineering & Construction, Oman ( June 21, 2008 to July 07, 2010 )

Client : Petroleum Development of Oman

Designation: Piping Supervisor

Project: Harweel Cluster Phase-2

Responsibilities:

•Pipe Fabrication, Erection and Installation, as built preparation

•Preparation of hydro test plan.

•Hydro test package, hydro test and commissioning procedure Method and statement

•Internal cleaning & gauging, Dewatering of water disposal plan, Method statement of swabbing and drying.

•Chemical treatment of water.

•Prepare project commissioning plan pep coordinate all the testing pneumatic/ hydro test and system reinstate.

•Coordinate commissioning meeting with contractors. Schedule and manage commissioning and pre-commissioning activities. Close out of commissioning activities and plant handover including performance testing.

•Management of delivery of training package. Identity/manage and confirm closer out of first fill data and subsequently lab schedule for operating of punch list item.

•Reviewing and final submission of vendor operation plant.

•Hydro testing, pre-commissioning and commissioning of pump value compressor, tank, piping associated across country pipe line familiar with carbon steel Duplex, Super Duplex, stainless steel, Corrosion resistance alloy glass reinforcement epoxy etc.

•Ensure safety requirement and directives of the safety officer on site and maintain safety on site at a high standard all time.

•Inspect valuable received material and related documents with the quality engineer.

•Activity related to fabrication / erection welding of piping, structural, and storage tanks in accordance with API-1104, API-620, API-650, and ASME B-31.3, 31.4, 31.8 &Project specification.

•Responsibilities also include review of inspection test plan, WPS, PQR, WQT, QC Procedure related QC documents and test package.

•Well versed with engineering & construction Drawing, specification, procedure, Manual& Symbols.

•Engineering analysis and design of components by ensuring the work is executed in accordance.

•Develop Design basis for projects when assigned as lead engineer specialist.

•Provide guidance and mentoring to more junior engineering personnel.

•Assist department manager and or engineering manager with development and standards, specification, etc.

•Prepare report and calculation for cost saving, optimization, design of fixture.

•Attend equipment testing and prepare test reports.

•Review of internal engineering drawings and document and provide necessary comments regards to machinery requirements, mechanical integrity and relative cost

•Evaluate alternative machinery technology and keep track of technological developments, evolution through in rotating equipment as well as changes in applicable codes and standards ( API, ISO, ASME, etc. )

•Construction of Nitrogen metering station, Installation of Pipeline with catholic protection for underground civil, Electrical and instrumentation work.

•Responsible to project coordination for review and appraisal of Mechanical and piping.

•Review specification and schedule for new equipment and life time extension of all retained existing equipment such as Pump, Turbine, compressor, conveyor, Heat Exchanger, Tank, and Vessel etc.

•Manage quality of delivered, schedule, Man-hours, Budgets, weekly Monthly Status and effectively.

•Lead the Mechanical project team creates technical Mechanical specification, review/approved client specification.

•Prepare procurement inquiry package, technically evaluate bids and issues order package for equipment.

•Coordinate and review vendor drawing data and supervise other Mechanical Engineer.

•Designer and Modular assigned to the project participate equipment inspection and testing.

•Develop details Mechanical equipment installation and operation instruction.

Al Jaber Energy Services, Abu Dhabi ( Nov 15, 2006 to April 13, 2008 )

Client: Gasco

Contractor: Bechtel

Designation: Piping Supervisor

Project: AGD-II ( Asab Gas Development Project )

Responsibilities:

•Supervision of Flow line installation

•Pipe Spool fabrication

•Manifold fabrication and preparation

•16” DSS bulk line fabrication and pipe lowering ; tie in joint 500 Meter long length by external clamp with perching hose dummy straight joint with internal clamp sleeving pin bracing by catholic protection holiday test inspection test plan, WPS, PQR, WQT, QC Procedure related QC

•Prepare material requisitions for the defined bulk material. Issue material requisitions for enquiry.

•Participate in technical assurance audits.

•Participate in the site surveillance program and follows up observed non-conformities.

•Perform works, which involves conventional engineering practices.

•Engineering activities includes piping specifications, material procurement specifications and piping calculations.

•Assist. Piping leads as necessary.

•Preparation of permits, Distribution of work to Crew

•Installation of beam pump, multi-port Selector Valve, multi-phase flow meter,

•Installation of Manifolds, piping of oil wells like beam pump, PCP, ESP, Gas lift wells, Gas wells, Self flowing wells, Water Injection wells, piping of MSV, MFM, Manifolds, PE Lining of CS Piping etc .

•Good experience in Fabrication of CS, SS, DSS piping work, construction of flow Line.

•Supervision of installation of pumps, compressor, Valves, heat exchanger, vessel & pipe line etc.

•According to elevation Grouting chipping & leveling of pump foundation.

•Installation of pumps after checked elevation by QC.

•Installation of pumps after checked elevation by QC.

•Preventive maintenance of pump.

•Analyze and monitor the performance efficiency of the equipment and prepare failure analysis report as required.

•Installation and erection of various rotary equipment’s like air compressors, reciprocating pumps, vertical and horizontal centrifugal pump and centrifugal pumps that are used in waste water treatment dept. via double diaphragm pump, axial flow pump etc.

•Startup operation and trouble shooting of Dismantling, servicing, reinstallation of conveyor, mixer and all kinds of valves & hydraulic press, cranes etc.

•Rectification of electro mechanical related to all types of pump, compressor, valves, heat exchanger and boiler etc.

•After pump assembled checked and testing with the help of water leak detector, shaft detector, gas detector venture meter and manometer etc.

•Rectification of abnormal noise of all kinds of mechanical equipment’s, gland leakage, oil leakage and abnormal vibration.

•Responsible of various preventive maintenance and breakdown maintenance job to ensure 100% availability of equipment and machinery.

•Preparation of schedule of monthly, quarterly, half yearly and yearly allotment of daily jobs to several kinds of crew.

•Staff meeting related of company matter to attend with royal commission field engineers, manager and superintendent etc.

•Operation on Machine shop like Automatic lathe, backing off lathe, capstan lathe, centre lathe, c-entre lathe, copying machine, hallow lathe, Slide rest lathe, sliding head automatic lathe, screw cutting lathe, turret lathe/Drilling/shaper etc.

.

C.C.C, Ras Laffan, State of Qatar ( April 01, 2005 to June 31, 2006 )

Client: Qatar Gas

Contractor: CTJV ( Chiyoda Technip Joint Venture )

Designation: Piping Supervisor

Projects: QGX ( Qatar Gas Expansion Project )

Responsibilities:

•Spool fabrication & Erection.

•To check rolling direction of spools lateral fabrication.

•Co-ordinate with Piping and welding group.

•Co-ordinate with NDT division.

•Co-ordinate with Engineering and PCD for Assurance of quality.

•Request for T.Q. [technical query and S.F.I. site field Instruction] to project engineer.

•Close the NCR ones violation becomes solved by codes and specifications.

•Hydro test preparation

•Equipment Installation

•Alignment of Equipment’s

•Leak Test and Pre-commissioning.

•FRP pipe fabrication.

•Reviewing isometrics, support drawings and details.

•Fabrication and erection various classes of piping like CS, SS & A.S. and utility

Services with respect to ISOMETRIC, GADs and P&ID.

•Inspection of incoming material as per quantity, mill certificates, heat number etc.

•Pipe Code Number 308H, 316L, 304L, 309L, 106A, 105B, P22, P11, P91, P333.

•Coordinate & inspect the activity of other disciplines and unit heads in order to precede the work with full assurance to implement quality.

Petrofac International Ltd. Iran ( Feb 13, 2003 to Dec 22, 2004 )

Client: British Petroleum

Designation: Piping Foreman

Projects: Dorood Project, Kharg I land

Hitachi Zosen Corporation, Abu Dhabi ( Dec 05, 1998 to July 31, 2002 )

Client: ADWEA ( Abu Dhabi Water & Electricity Authority )

Designation: Piping Foreman

Projects: ‘Taweelah B Extension’ Project

A creative individual with proven skills in observing and recording behavior of clients and adapting this information to individualized situation. Able to identify potential and group opportunities/problems. Weigh necessary options and determine the best course of action to achieve productive and results. Recognized as an integrator and synthesizes of multiple concepts and ideas.

Others Details:-

Nationality : Indian

Religion : Hindu

Passport No : Z4102084

Date of issue : June 02, 2017

Date of Expire : June 01, 2027

Place of issue : Lucknow

Passport Status : ECNR

Driving License : India



Contact this candidate