CURRICULUM VITAE

INSTRUMENTATION & CONTROL ENGINEERING PROFESSIONAL

** ***** ** ******* ******* Instrumentation (Post Qualification) : Detailing (Engineering & Design) + Project Execution (Erection & Commissioning) + Pre-bid Engineering +Procurement Assistance +QA/QC (Expedition & Inspection) + Operation & Maintenance (Continuous Process Plants) + 3 Years as Instrument Technician in Integrated Pulp & Paper Industry (Pre Qualification)

BRIEF OF WORKING EXPERIENCE

NAME AND ADDRESS EMPLOYER

WORKING PERIOD

JOB PERFORMED

SELF

May 2016

Project Management Consultancy (Detailed Engg.)

VCARE ENGGINEERING PVT. LTD.

Jan 2016 to April 2016

Detailed Engineering, Procurement

WORKING EXPERIENCE OF CRYOGENIC FLUID SVD PACKAGE MANUFACTURING, SUPPLY & COMMISSIONING IN OIL & GAS

INOX INDIA PRIVATE LIMITED, Baroda, Gujarat

June 2011 Dec 2015

HOD, Sr. Manager – (Instrumentation)

WORKING EXPERIENCE OF PROJECT MANAGEMENT CONSULTANCY (DETAILED ENGINEERING)

PROJECTS & DEVELOPMENT INDIA LIMITED

(A Govt. of India Undertaking), WRO, Subhanpura, Baroda-390023

Sept, 2007 to June 2011

Engineering Department in the position of Senior Engineer (Instrumentation) as Team Leader

PROJECTS

EXECUTED

1.Back up Consultancy for 3 x 830 M3 LPG Mounded Bullet, Oil India Limited, Duliajan, Assam, 2.PMC for LPG and Propylene Mounded

Storage Facilities, HPCL, Visakh Refinery, 3.PMC for 525 TPD Methanol Plant, GSFC, Vadodara, 4. PMC for Debottlenecking FCCU-1

(Fractionator) and GHU, HPCL, Visakh Refinery, As Team Leader, 5.PMC for Flue Gas Desulphurization & Purge Treatment Units, HPCL,

Visakh Refinery, As Team Leader, 6. PMC for PSA Unit, HPCL, Visakh Refinery, As Team Leader, 8485

WORKING EXPERIENCE OF ENGINEERING AND PROJECT EXECUTOIN IN EPC ORGANISATION(Environmental Sector)

UPL ENVIRONMENTAL ENGINEERS LTD

(United Phosphorus Ltd. Group of Company), 203, Concorde

Building, R.C. Dutt Road, Alkapuri, Baroda-390007

May, 2006 TO

Sept, 2007

I WAS WORKING AS INSTRUMENTATION

DESIGN ENGINEER IN ENGINEERING DEPTT.

Position : Asstt. Mgr. (Instrumentation)

WORKING EXPERIENCE OF EXPEDITION AND INSPECTION (Asstt. Mgr. –Instrumentation)

NAME OF THE EMPLOYER : NICCO CORPORATION LIMITED ( PROJECT DIVN) NICCO HOUSE, 3RD FLOOR, 2-HARE STREET, KOLKATA-700001,

DURATION : 25.02.1998 TO 30.04.2006, Position: Asstt. Mgr. (Inst.)

From 23rd March 2004 to 30th April 2006 I was working in inspection and expedition department at Mumbai regional

Office of NPD for expedition and inspection of instruments / instrumentation items of NPCIL and other projects.

WORKING EXPERIENCE OF ENGINEERING AND PROJECT EXECUTOIN (INSTRUMENTATION)

PROJECT NAME

CONTROL

SYSTEM

CLIENT

CONSU-

LT ANT

WORKING PERIOD

JOB PERFORMED

PHOSPHORIC ACID PLANT(CAPACITY:335 TPD), DAHEJ, GUJRAT

DCS-CENTUM CS

(YOKOGAWA)

BIRLA

COPPER

FEDO,

FRANCE

MAR-1998

TO JULY-1999

ENGINEERING, ERECTION AND COMMISSIONING,OF PROCESS CONTROL INSTRUMENTATION

GAS LIFT FACILITIES, GGS-04,PAKHAJAN, GUJRAT.

PLC

ROCKWELL(A.B.)

ONGC

EIL

AUGUST,

1999 TO

MAY,2000

ENGINEERING, ERECTION AND COMMISSIONING OF PROCESS CONTROL INSTRUMENTATION

LPZE EXPANSION AND PERFORMANCE IMPRO-

VEMENTPROJECT,DEBARI, UDAIPUR,RAJASTHAN.

LOCAL

CONTROL

PANEL

HINDU-

STHAN

ZINC

LTD.

MECON

JUNE, 2000

TO

JUNE, 2001

ENGINEERING ERECTION AND COMMISSIONING OF PROCESS CONTROL INSTRUMENTATION

EFFLUENT TREATMENT PLANT,(CAP:4000M3/DAY), NORTH KADI, GUJRAT.

LOCAL

CONTROL

PANEL

ONGC

EIL

JULY, 2001

TO AUG-2001

PLANT COMMISSIONING

ALUMINATE LIQUOR EVAPORATION PLANT,

DAMANJODI, ORISSA.

DCS-CENTUM CS

(YOKOGAWA)

NALCO

EIL

SEPT. 2001 TO OCT-2001

PLANT COMMISSIONING

RAW WATER TREATMENT

PLANT(CAPACITY:570M3/H)DAMANJODI, ORISSA.

LOCAL

CONTROL

PANEL

NALCO

EIL

NOVEMBER

2001

PLANT COMMISSIONING

RAW WATER TREATMENT PLANT,DAMANJODI,ORISSA

LOCAL CONTROL

PANEL

NALCO

EIL

MARCH

2002

PLANT COMMISSIONING

AND P.G. RUN

BARODA HEAVY WATER REVIVAL PROJECT, BARODA, GUJRAT.

DCS

ALTERSYS

HEAVY

WATER

BOARD

DIRECT

EXECU-

TION

APRIL, 2002

TO MAR. 04

ENGINEERING, ERECTION AND COMMISSIONING

HEAVYWATER UPGRADI-

NG PLANT, TAPP4, TARAPUR, MAHARASTRA.

PLC,ROCKWELL

(A.B.)

NPCIL

DIRECT

EXECU-

TION

JUNE-2005

OCT-2005

PLANT COMMISSIONING

WORKING EXPERIENCES OF OPERATION AND MAINTENANCE (INSTRUMENTATION)

TITAGARH INDUSTRIES LIMITED (PAPER DIVN.), TITAGARH PAPER MILLS, UNIT NO.02, KAKINARA, 24-PGS (NORTH),WEST BENGAL.

NOV-1996

TO FEB-1998

OPERATION AND MAINTENANCE

Position : Asstt. Engineer (Instrumentation)

THE BENGALPAPER MILL(1989)COMPANYLTD,

BALLAVPUR, RANIGUNJ, BURDWAN, WEST BENGAL.

APRIL, 1993 TO

OCT, 1996

OPERATION AND MAINTENANCE

Position : Asstt. Engineer (Instrumentation)

Pre Qualification Working Experience

THE BENGALPAPER MILL(1989)COMPANY LTD,

BALLAVPUR,RANIGUNJ,BURDWAN,WEST BENGAL

APRIL, 1989

OCT, 1991

Worked as Instrument Technician

COMPETENCY

WORKING EXPERIENCE IN EPC ORGANISATION OF CRYOGENIC EQUIPMENT MANUFACTURING

Pre-bid & Detailed Engineering, Procurement,Technical Evaluation, Erection & Commissioning of SVD System – Instrumentation & Control

WORKING EXPERIENCE OF PROJECT MANAGEMENT CONSULTANCY (DETAILED ENGINEERING)

1.Site Visit and Preparation of Site Survey Report.

2.Preparation of NIT Document for Instrumentation.

A.General Document : (Instrumentation Design Philosophy, Contractor’s Scope of Supply and Installation, Safety Norms / Regulation, Quality Plan, Deviation format)

B.Instrumentation Detail Engineering : (Instrument Index, Preparation of loop diagrams, Instrument location layouts, Instrument cable tray layouts, Terminal Connection Diagram, Interconnection Diagram, Cable schedule, Junction Box Schedule, Control room arrangement, Instrument hook-up drawings, Standard Support Details, Instrument Air distribution Layouts.)

C.Preparation of Data Sheet for Field Instrument : (Flow Instrument, Level Instrument, Pressure Instrument, Temperature Instrument, Gas Detector, Conductivity Analyser, pH Analyser, Control Valve, ROV, Electro-pneumatic positioner etc.

D.Preparation of Data Sheet for Erection Material :(Instrumentation signal and control cable, Thermocouple Extension / Compensating Cable, Junction Box)

E.Control System Instrumentation “DCS/PLC” : (Input / Output List, Input / Output Summary, Specification for Marshalling Cabinet), Preparation of Control System Specification.

F.Sketches for Temperature Instrument: (Sketch for Thermowell, RTD, Thermocouple, Temperature Gauge)

G.Quantity and Schedule of Rates : (i. Quantity and Schedule of Rate for Instrumentation-Supply ii. Quantity and Schedule of Rate for Instrumentation- Calibration, Erection, Testing, and Commissioning)

3.Technical Evaluation of offer of instruments and instrumentation items.

4.Adequacy Checking of Existing Instruments for Revamp Project and Sizing & Selection : (Orifice for Flow Measurement, Restriction Orifice, Control Valve, Safety Valve)

WORKING EXPERIENCE OF QUALITY ASSURANCE-INSTRUMENTATION (EXPEDITION & INSPECTION)

Expedition & Inspection: (i) Review of Instrument Index, specifications / data sheets for field and control room instruments. (ii) Conducting technical evaluation for quality requirements, of items to be purchased. (ii) Review, comments and approval of Inspection and Test Plans (ITP) and test procedures for all Instrument and Instrumentation item. (iii) Expedition of manufacturing of instrument items from office and through visit to vendor works. (iv) Witness inspection, at vendor works, instrument system such as: DCS/PLC/SCADA/F&G & ESD Hardware and marshalling / system cabinets, Level, Pressure, Temperature, Flow and other measurement instrument, Instrument cables, control valves, On/Off valves, safety relief valves, shut down panels, metering systems, Fire & Gas detectors, etc. & Issue of release certificate after satisfactory Quality Verification, Document review. (v) Monitor/witness site testing & pre-commissioning activities of instrumentation systems. (vi) Co-ordination with appointed TPIAs for inspection visits at vendor works. (vii) Co-ordination with engineering consultants, vendors and TPIA for various project related quality issues.

WORKING EXPERIENCE OF ENGINEERING AND PROJECT EXECUTOIN (INSTRUMENTATION)

Engineering, Erection & Commissioning (i) Identify the Scope of Work. (ii) Review of Project Specifications, Material Specifications, P&IDs, Area Classification Drawings, Instrumentation and Fire & Gas Detector Layouts. (iii) Preparation of Instrument Data Sheets for Process Field Instrument. (iv) Co-ordination in preparation of Purchase Orders, Requisitions, (v) Review and approval of vendor package system, Vendor / Pre-Qualification, Technical evaluations etc. (vi) Review and clarification on Technical Queries raised by Contractor and vendor. (vii) Calibration, Loop Checking & Pre-Commissioning and commissioning of Field instruments.(viii) Site acceptance test of control system instrumentation (PLC+DCS), (ix) Review of R.A. Bill submitted by instrument contractor and certification of measurement and quantity of site work.

WORKING EXPERIENCES OF OPERATION AND MAINTENANCE (INST.) OF CONTINUOUS PROCESS PLANTS.

I worked in operation and maintenance in continuous process plants of integrated pulp and paper industry having 11 sections (i) Chipper, (ii) Continuous Kamyr Digester, (iii) Multi-stage Bleaching Plant, (iv) Stock Preparation plant, (v) Paper Machines, (vi) Cutting Section, (vii) Coal Fired Boiler, (viii) Recovery Boiler, (ix) Turbines, (x) Evaporation Plant (xi) Re-causticizing Plant. I get opportunity to gather experiences of (i) Planning & Effective Maintenance,(ii)Identification of Root Cause of Breakdown and Rectification with available Resources, (iii)Troubleshooting of field & Control System Instrumentation.(iv) Improvement in measurement & Control by value engineering, (v) Safety & Regulation, (vi) Inventory Management of Spare and Spare Parts.

(vii)Internal & External Coordination with various departments of company & Manufacturer / Supplier / Contractor.

(viii)Working with concept of Customer-Supplier Relationship.

Pre Qualification Working Experience

I worked in operation and maintenance in continuous process plants in integrated pulp and paper industry as instrument technician simultaneously during the study of AMIE (Sec. A & B)

NAME : RAMESH CHANDRA PAL (Mobile Phone: 91-942*******)

(ISO 9001: 2008 IRCA Certified Lead Auditor)

FATHER’S NAME : LATE HARIMOHAN PAL

DATE OF BIRTH : 11TH FEBRUARY 1962

NATIONALITY : INDIAN RELIGION : HINDU

MARITAL STATUS : MARRIED

LANGUAGE KNOWN : HINDI, BENGALI, ENGLISH

PRESENT ADDRESS : FLAT NO.302, LABH TOWER, SHIVALIK-3, CHANAKYAPURI CANAL ROAD,NEAR CANAL,

(Address for Communication) SAMA, P.O.-CHHANI ROAD, VADODARA, GUJARAT-390024, 91-942*******.

PERMANENT ADDRESS : C/O- AMAL PAL, VILL. 1 NO. NATUN FULIA, P.O. 2 NO. NATUN FULIA

DIST. NADIA, P.S. SANTIPUR, WEST BENGAL – 741402, 91-940*******.

E-MAIL ADDRESS : ac0cf1@r.postjobfree.com, srabanipal @rediffmail.com

PROFESSIONAL QUALIFICATION : B.E. ELECTRONICS & COMMUNICATION ENGINEERING, CHARTERED ENGINEER.

EXAMINATION PASSED : AMIE (Sec .A & B) THE INSTITUTION OF ENGINEERS (INDIA)

RECOGNITION BODY : Ministry of Education & Social Welfare, Government of India

ACADEMIC QUALIFICATION : B.Sc., University of Calcutta (Kolkata)

TRAINING COURSES ATTENDED : i) PROGRAMMING OF PLC & DRIVES FROM C-DAC, MOHALI, CHANDIGARH

(Certificate of Successful Completion) ii) HMI/SCADA SYSTEM DEVELOPMENT FROM DOEACC, CALICUT, KERALA

iii) ULTRASONIC TESTING (ASNT LEVEL-II)

iv) QUALITY MANAGEMENT SYSTEM

LEAD AUDITOR ISO 9001:2008 FROM ESCI HYDERABAD CERTIFICATE FROM IRCA

v) Training for SOLAR PHOTOVOLTAIC FIELD ENGINEER from ESCI, Hyderabad.

SOFTWARE APPLICATION LITERACY : IN-Tools, CONVAL, AUTOCAD, MS OFFICE (WORDS, EXCEL, POWER POINT), LOTUS

(By Working Experience)

DRIVING LICENSE NO. : GJ06 200********, PASSPORT NO : M8183530, Date of Issue 09.06.2015, Date of Expiry 08.06.2025

FIELD OF WORKING EXPERIENCE : PROCESS CONTROL INSTRUMENTATION (24 + YEARS, POST QUALIFICATION)

Reference-1: Mr. B.N. Mishra, V-Care Engineering Pvt. Ltd.-Baroda, Mobile : 942-***-****, E-mail : ac0cf1@r.postjobfree.com

Reference-2: Asim Kumer Niyogi, AVP-Engineering, Inox India Pvt. Ltd., Baroda, Mobile: 982-***-****, E-mail : asim.niyogi @ inoxcva.com

Reference-3: Mr.Chandan Bhattacharyya-C.E.(Inst.), PDIL-Baroda, Mobile : 942-***-****, E-mail : ac0cf1@r.postjobfree.com

Reference-4: Mr.Sugata Banerjee-G.M. (Inst.),TCE-Kolkata, Mobile : 983*******, E-mail : ac0cf1@r.postjobfree.com

1. I WAS WORKING IN INOX INDIA LIMITED AN EPC ORGANISATION IN THE FIELD OF CRYOGENIC EQUIPMENT IN THE AREA OF NITROGEN, OXYGEN, ARGON STORAGE AND VAPORISATION SYSTEM (SUPPLIER OF PACKAGE UNIT TO OIL & GAS INDUSTRIES).

2. I WAS WORKING IN INOX INDIA LIMITED AN EPC ORGANISATION IN THE FIELD OF CRYOGENIC EQUIPMENT IN THE AREA OF NITROGEN, OXYGEN, ARGON STORAGE AND VAPORISATION SYSTEM (SUPPLIER OF PACKAGE UNIT TO OIL & GAS INDUSTRIES).

3. I WAS WORKING IN PROJECTS AND DEVELOPMENT INDIA LIMITED (A GOVT. OF INDIA UNDERTAKING) AN ORGANISATION FOR PROCESS PLANT DESIGN, RESEARCH AND DEVELOPMENT.

4. I WAS WORKING IN ENGINEERING DEPARTMENT OF UPL ENVIRONMENTAL ENGINEERS LIMITED, BARODA GUJARAT AS INSTRUMENATION DESIGNER ENGINEER FOR THE PERIOD OF 01.05.2006 TO 11.09.2007

5. I WAS WORKING IN NICCO CORPORATION LIMITED (PROJECT DIVISION), AN ISO 9001 COMPANY, PERFORMING ENGINEERING & PROJECT EXECUTION (ENGG., ERECTION AND COMMISSIONING) OF DIFFERENT PROCESS PLANTS. DURATION : 25.02.1998 TO 30.04.2006

6. I WAS WORKING IN THE FIELD OF PROCESS CONTROL INSTRUMENTATION IN INTEGRATED PULP AND PAPER INDUSTRIES FROM APRIL 1993 TO FEBRUARY 1998 HAVING CONTINUOUS KAMYR DIGESTER,MULTISTAGE BLEACHING PLANT, PAPER MACHINES, COAL FIRED BOILER, LIQUOR FIRED RECOVERY BOILER, RECAUSTISIZING PLANT, STOCK PREPARATION PLANT AND TURBINE.

>I GOT OPPURTUNITIES OF ACQUIRING FOLLOWING WORKING EXPERIENCES AND KNOWLEDGE OF PROCESS CONTROL INSTRUMENTATION DURING ABOVE SERVICE PERIODS.

(ENGINEERING & DESIGN, OPERATION & MAINTENANCE, ERECTION, COMMISSIONING, INSPECTION OF INSTRUMENTS / INSTRUMENTATION ITEMS AT VENDOR PREMISES, FAT, SAT, PGTR) After completion of B.Sc. from University of Calcutta I started work in integrated pulp & paper industry as “Instrument Technician”. During this working period I took admission in The Institution of Engineers (India) and passed both examinations (Sec. A & B) in Electronics & Communication Engineering in 1992. The examination (Sec. A & B) is recognized by Government of India at par with a Bachelor’s Degree in the appropriate field of Engineering from a recognized. Letter No. F.18- 4/78-T.7 Dated 16.08.1978.



Contact this candidate