Resume:

E-mail Address : *********@*******.***

Telephone Numbers : (Mobile) 002***********

Family Name: Mohamed Hassan Name: Mohsen

Nationality: Egyptian. Date of Birth:

**/**/****.

Educational Attainment: B Sc. Mechanical Engineering Alexandria University

(1974)

Profession : Project Manager

Languages : Arabic "Native", English Very Good "Read, Write &

Speak".

Social status : Married, have two children.

Summary of Experience:

Having more than thirty years experience of working in various projects

related to Oil & Gas facilities, and petrochemical plants.

Most of the experience is related to maintenance of Petrochemical

plants/shutdowns, EPIC projects management, project construction management

of process equipment, piping system engineering and design, new

constructions of pipelines, piping/equipment replacement/upgrading and

related construction works.

Worked extensively and gained hands on experience with respect to Oil &Gas

Processing Facilities, special heavy equipment such as Shell & Tube heat

exchangers, Fin-Fan coolers, Valves of all types used in highly corrosive

atmosphere, high pressure vessels, towers and Centrifugal Pumps. Perform

the role of Project/Construction Manager and Team Leader in various project

activities.

Responsibilities include Project Management, technical evaluation/

tendering for EPC projects, project engineering, material/equipment

procurement, replacement jobs, construction activities, plant

modifications, shutdowns, tie-ins, upgrade of existing facilities, pre-

commissioning and commissioning of related activities.

Familiar with live operation requirement, risk assessment, root cause

analysis (RCA) and HSE regulations in running plants.

Executed several projects as project and construction manager, covering EPC

Onshore Gas/oil projects, HAZOP study, tie-ins to existing facilities,

construction works, revamp and shutdown works. Manage EPC and engineering

projects in UAE (GASCO), SYRIA (AFPC), Qatar and EGYPT.

Have strong understanding and extensive experience in Project management,

coordination of multi-disciplinary and multi-cultural project teams for

vetting and supervision of the project.

Experienced and have good knowledge of Shell DEP, QP Standards and

international codes ASME, ASTM, API and TEMA.

Have experience in piping/ pipeline metallic, GRV, PVC Material along with

construction activities.

Verification and vetting of drawings including discipline checks and

compliance with specifications.

Experienced with construction and deliverables of piping /pipelines above

and underground such as Design Basis, crossing reports, alignment sheets

drawings, route maps, pipelines Station approach drawings, material

specifications, piping wall thickness calculations, expansion loops, MTO's,

field supports, etc..

Main Courses attended:

o Project Management course for PMP

o Quality Management System

o Management and Supervisory skills

o CAESAR II software & applications

o Cost estimation.

o Plant Design System (PDS - Intergraph)

o Basic first aid course, H2S awareness and escape course and HSE

related courses.

Major project Experience:

From September 2011 till June 2013: (Qatar)

COMPANY : Black Cat Engineering and Construction Ltd

POSITION : Project Manager.

EPIC for Upgrading the Instrument Air System at KNDS within Dukhan Field

Client:: Qatar Petroleum

QP compressor package have been in service for long time and have become

unavailable with frequent failures, the controls of the existing units are

obsolete and cannot be integrated into the DCS System.

It has been established that the Instrument Air System upgrade shall be

implemented by constructing a new Instrument Air Compressor facility.

Complete with new oil-free Rotary Air Compressors, Filters, Air Coolers,

Air dryers, wet air receivers, Additional Air Receivers& Buffer Tanks and

with foundation fieldbus redundant PLC-based Master control which is fully

integrated with the plant DCS.

EPIC project of Waste Water Treatment Package at Dolphin Energy Co.

Client: Dolphin Energy Ltd - Qatar.

Procurement, residual engineering and installation of nine related

filtration, pumping spent soda Skids including civil foundations,

interconnecting piping, erection of dirty/clean backwash tanks and

underground GRV drainage piping, integrating to existing DCS System and

commissioning.

From year Jan. 2007 till 30.07. 2011: (Abu Dhabi- UAE)

COMPANY : Abu Dhabi Gas Industries Ltd (GASCO)

POSITION: Project Manager.

Duties & Responsibilities:

- Share in conceptual study and preparation of EPC tender packages

for competitive bidding.

- Share inTechnical specifications review and selection.

- Contractors/Vendors evaluation.

- Conduct technical evaluation/bid analysis of tender bidders and

recomendation for award.

- Participate in HAZOP studies.

- Particpate in the development of project budgets and schedules.

- Lead negotiations for technical clarifications and variations to

minimize /eleminate commercial claims

- Direct and monitor the application of appropriate procedures and

standards in the execution of project activities, in line with

international codes and company best practices.

- Review and approve progress reports and invoices

- Supervise site construction activities.

-

EPC Projects handled:

- Sharing in engineering and execution of Petrochemical plants in Egypt

(VCM, PVC,

And chlorine plants). Evaluate technical proposals of centrifugal

pumps and Shell &

Tube heat exchangers.

- Gas Plant expansions in Abu Dhabi Gas Industries Ltd (OGDI & OGDII}

- Construction of pipelines and flow lines projects.

- Construction superintendent of oil gathering stations

- Onshore Oil & Gas Development facilities.

- Oil and Gas processing facilities comprised of separation and

stabilization

- Gas and water injection.

- Hydrocarbon and NGL recovery projects.

- Flaring systems.

- Upgrading of injection compressors capacity and related piping.

- Replacement of rich amine CS piping by upgraded SS material,

- Replacement of convection and radiation sections of heaters.

- Upgrading/Replacement of CS coolers bundle with upgraded incoloy

material.

- Capacity enhancement and de-bottlenecking projects.

- New electro chlorination units.

- Prepare, issue, and follow up through to commissioning and handover

of Engineering Packages and Construction "EPC" contracts.

- Review and comment on Engineering Piping Packages prepared by

consultants /EPC

Contractors.

- Review contract requirements for project execution, organize the

preparation of the Technical Document Register, and identify the

requirements and the scope of work,

- Review specifications of manual valves and piping materials, review

drawings (P&ID, GA, Piping Plans and Isos' etc Identify/comment

and resolve discrepancies and divergences from original proposal

through instigation of technical queries to EPC contractor.

- Review / supervise and comment on stress analysis reports prepared by

consultant in

CAESAR II software and modeling works in PDS, ensure that isometrics

are updated

as required. Monitor the identification of stress factors and layout

feasibility, resolve

design irregularities and Piping Clashes appear through PDS. Provide

stress and piping loads to civil engineering group.

- Carry out/evaluate stress analysis for piping systems by "CAESAR II"

software and

propose different scenarios to reduce stresses in critical

locations.

- prepare, review/comment of all types of manual valves, safety valves,

ESD and

control valves (mechanical part).

- Evaluate deviations/ exception to tender/ engineering documents of

technical

proposals.

- Define man-hours estimate.

- Define engineering deliverables and schedule.

- Define interface with other disciplines.

- Organize technical proposal write up related to the piping package of

projects.

- Identify particular technical and execution feature that may have an

impact during

project execution.

From year 1998 until 2006: (Abu Dhabi/ UAE)

COMPANY : Abu Dhabi Gas industries Ltd (GASCO)

POSITION : Senior Dev. Engineer.

- Study field problems and propose remedial measures.

- Piping systems design, and management of EPC Piping projects.

- Prepare Scope Of Work and EPC packages of different projects.

- Conduct technical evaluation/bid analysis of tender bidders and

recomendation for award.

- Procure materials necessary for modifications and upgraded

equipment.

- Familiar with maximo system and CAESAR II stress analysis software.

- Investigate and study recommendations of stress analysis for

different piping systems.

- Work execution follow-up.

- Material specification review.

- Review design for piping, pipelines, tanks, pressure vessels,

towers, centifugal pumps.

From year 1996 to 1998: (SYRIA Arab Republic):

COMPANY : AL-FURAT Petroleum Company (AFPC)

POSITION : Project/Construction Engineer

Duties & Responsibilities:

- Construction engineer/coordinator of pipelines and flowlines.

- repare detailed engineering design and drawings for approved capital

budget projects, material specifications, detailed scope of work and

technical specifications.

- Carry out bid analysis evaluation and prepare recommendation for the

award.

- Study field problems that have design oriented solutions and propose

remedial measures.

- Participate in Hazops.

- Supervise the execution of project activities of pipelines and

equipment erection.

- Ensure compliance of drawings with specifications and standards.

- Participate in project briefing, bid evaluation and neogotiations.

- Flowlines coordinator.

From 1992 to 1995: (SYRIA Arab Republic):

COMPANY : Al-FURAT Petroleum Company (AFPC)

POSITION : Mechanical Maintenance Engineer

Duties & Responsibilities:

- Recommends the required remedial actions and plant modifications.

- Issue preventive maintenance procedures of various equipment.

- Prepare annual shutdown schedules and planned maintenance programs.

- Raises requests and follow up the replenishment of warehouse stocks.

- Study field problems and propose remedial measures.

- Prepare technical reports and various monthly, periodic reports to

keep management advised of status.

From 1984 to 1991: (Alexandria, Egypt)

COMPANY : Egyptian Petrochemical Company

POSITION : Graduated in the following Positions

Maintenance Manager of V.C.M. Plant; from 1990 till 1991

Duties & Responsibilities:

- Provide technical and maintenance information support.

- Monitor all kinds of mechanical maintenance in VINYLE Chloride

MONEMER plant (V.C.M.).

- Coordinate with the maintenance planning engineers, and other

operating sections in preparing planned maintenance programms for

all plants equipment installations, pipelines, vessels, towers ...

etc.

- Assess and follow up the equipment and facilities condition by

evaluating the results of performance checks and periodic

inspections.

- Prepares reports and studies to assist in evaluating the performance

of maintenance activities.

- Set up equipment history system.

- Raise requests and follow up the replenishment of store stocks to

assure the availability of spare parts required for both normal and

major repairs.

- Participate in training and development of the new engineers.

- During my practical experience, always keeping myself informed with

the engineering codes and regulations such as ASTM, ANSI, ASME, API

and TEMA.

- Review the specifications of various materials and their behavior

against acids facing practical problems of corrosion.

Section Head of Static Equipment (V.C.M. plant); from 1987 till 1989

Duties & Responsibilities:

- Supervision of mechanical maintenance planning office.

- Supervise the execution of major overhauls, specific repairs and

trouble shooting for towers, reactors, furnaces, heat exchangers,

vessels... etc

- Prepare planned maintenance programs.

- Recommend the required remedial actions and plant modifications.

Construction Engineer; from 1984 till 1987

Duties & Responsibilities;

- Construction engineer of reactors, furnaces, heat exchangers,

pipelines, compressors crackers and pumps,

- Study the licensor and general contractors proposals for P.V.C. and

V.C.M. plants, and preparing technical comments,

- Attend the negotiations, discussions and comment/approve the

technical proposals with the general contractors and licensors.

From 1974 to 1984: (Alexandria, Egypt)

COMPANY : Dyestuffs and Chemicals Company (ISMADYE)

POSITION : Graduated in the following Positions

Mechanical Maintenance and Planning section head; from 1979 till 1984

Duties & Responsibilities:

- Prepare preventive maintenance programs.

- Prepare schedules for major repairs and annual maintenance shutdown.

- Follow up and update master plan.

- Establish spare parts requests required for both normal and major

repairs.

- Prepare engineering specifications for the ordered equipment and

share in the technical evaluation of the offers.

Mechanical Maintenance Engineer; from 1977 till 1978

- Ensure safe and efficient operation of rotating equipment.

- Follow up maintenance of centrifugal pumps, plunger pumps,

centrifugal compressors, reciprocating compressors, agitators,

kettles, spray dryers, centrifuges... etc.

Workshop Mechanical Engineer; from 1974 till 1977

- Responsible for supervision of execution of piping work.

- Supervise machining workshop.

- Prepare requisitions for tools and materials.



Contact this candidate