NIRANJAN PRASAD Mobile No.938-***-**** ~ E-mail:
************@*****.**.**
810-***-**** : ********.******@********.**
DGM Mechanical Reporting to CCM - Abhijeet Project Limited, Chakla,
Chandwa, Latehar, Jharkhand (4x270MW) Having unlimited Vision seeking the
challenging assignment in similar nature of project
Professional Profile
Production Engineering Graduate with more than 17 years of work experience
in Project Planning and Execution, Installation & Commissioning and
Resource Management. Expertise in estimating & planning project schedule,
system engineering and conducting verification of engineering drawings.
Proficiency in handling the complete project operations entailing planning,
resource utilization, maintenance & manpower management; proficient in
installation, commissioning, fabrication & erection of plants. Adept in
using technological tools with proficiency in developing new systems and
equipment in compliance with pre-set technical specifications. Holds the
distinction of handling construction for Jindal Stainless Ltd, Duburi,
Orissa, Rourkela Steel Plant, Rourkela, Orissa, TPP-WBPDCL, Sagardighi-West
Bengal, TPP-Maithon Dhanbad, beside others. An effective communicator with
excellent relationship management skills and strong analytical, problem
solving & organizational abilities.
Core Strengths
Project Management
< Monitor & Control the execution of entire Mechanical & Structural work of
4x270 MW IPP within agreed time and budget which includes Boiler, TG, CW
Piping, CHP, Pumps, Fuel handling System Ash Handling system, Coal
Handling System.
< Monitoring project schedules / plans, Engineering Designs / Drawings and
technical specifications for smooth execution of projects within the time
and cost parameters maintain safety & quality specification.
< Monitoring & control of Material & detail engineering; conducting project
review meetings for evaluating project progress & taking adequate
corrective actions if required.
< Maintaining good and cordial relationship with local people and govt.,
officials for better execution of work.
< Conduct meeting with consultant, contractors and own functional team to
ensure the adherence of quality plan.
< Establish high level of leadership to motivate the entire team to exert
their best towards their work to complete their job within the schedule
time and within the provision of budget and provide technical competence
as and when required.
Contract Management
< Coordination with commercial for placement of contracts, project cost
estimates and deliveries.
< Coordination for placement of orders to maintain project schedule.
< Coordination with commercial and contractors for any deccripencies
during construction.
< Monitoring of cost overrun and prepare action plan accordingly for
completion of job.
< Ensure optimum utilization of materials to monitor the cost.
< To back down the overall cost estimate to individual activities for
better control.
Planning and Monitoring
< Study and analyse the area wise schedule in comparisation with project
schedule.
< Study and detailing into the micro planning of the schedule of
individual area.
< Ensure the progress of all micro level activities to meet the
construction target.
< Conducting regular meetings and interact with the contractors to meet
the target.
< To ensure optimum utilization of available resources.
< Finalization of the sequence of the project
< Conducting meeting with internally, Vendors, Contractors on daily,
weekly & monthly basis to monitor the project activity. Action plan to
be made for the critical activity with deployment of man power and the
other resources required to complete the same on time.
Material Management
< Coordination with contractor for deployment of material availability &
T&P on time.
< Follow up & monitoring for release of order on time with Vender as
well as internals to reach the material on time.
< Ensure timely procurement.
Fabrication Engineering
< Monitoring & control the designing processes & developing for
implementation during execution of project.
< Building dimensional components with Technical drawings, coordinating
with Design Department/commercial team in order to meet the project
requirements.
Erection, Commission and Maintenance
< Erecting and commissioning as well as conducting quality tests &
inspections to ensure operational effectiveness of utilities.
< Conducting inspection and tests to ensure the effectiveness of various
machines and equipments keeping in view the performance, safety & quality
standards.
< Planning and effectuating predictive & preventive maintenance schedules
for equipments; conducting periodic checks to ensure performance of
various equipment.
< Establishing quality standards, implementing stringent quality control
systems for incoming materials to enhance quality of products & reduce
the rejection rate.
Resource Management
< Implementing and monitoring effective procurement schedules along with
finalizing the specifications of the spare parts and establishing the
quality & quantity limits.
< Effectively allocating the resources optimising the available time for
enhancing profitability.
< Follow-up with suppliers for monitoring quality & expediting delivery
schedule.
Organisational Experience
Since Jun'2010 DY. General Manager (Mech.) Abhijeet Group Chandwa
Site
< Join Abhijeet Group at Chandwa Site with a great challenge to work in
this difficult area with BHEL Main contractor for BTG Package.
< Functioning as BTG In-charge for 4x270MW in two phase at Chandwa site,
located at Latehar District.
< All four units progress is in advance stage, Drum of all four units are
erected, Drainable Hydro of two unit completed, One Unit is ready for
Light-up & consecutive synchronisation also but held due to some critical
constraints.
Since Aug'08 Construction Manager (Mech.) MPL
SITE MAITHOM
Company Larsen & Toubro Ltd. - ECCD Consultant TCS
Client Tata Power Limited
< Functioning as Project Manager for erection of:
o 02 No Boiler-525 MW
Mar'06 - Aug'08 Asst. Construction Manager (Mech.)
SGTPP, WBPDCL
Company Larsen & Toubro Ltd. - ECCD Consultant DCPL
Client Dongfang Electric Corp (DEC), China
< Functioning as Area Project Manager for erection of:
o 1 No Boiler-300MW with ESP (19600MT)
o 2-TG Buildings (9600MT)
o 2-Bunkers (8600MT) including all the Structure, C.W. piping
(1250 MT) all equipment, (Static & Rotary) for 2X300MW Thermal
Power plant.
Notable Feat;
< Played a stellar role in:
o Erection of Boiler Drum (175MT) in 98 days (after erecting over
2400MT of Structural) & received Client's appreciation letter.
They say it is an Indian record.
o Erection of Collecting Electrode at ESP received accolade from
Client & Owner. The method is unique in India resulting to 400-
450 nos of erection per day.
< Highlights: Boiler Drum Erection, Bunker Structure, TG Structure &
Equipment, ducting and coal piping completion.
< Recipient of a Certificate for "Best Organized & Quality Work" & "Safest
Site" from DEC & appreciation letter from WBPDCL.
Nov'05 - Feb'06 Asst. Construction Manager (Mech.)
Larsen & Toubro Limited
Company Larsen & toubro Lid. - ECCD
Consultant DCPL, Kolkata
Client Jindal Stainless Ltd., Duburi, Orissa
< Handling fabrication & erection of structure for TG building (2 X 125MW)
& Bunker.
< Accountable for preparation & implementation of Project Quality Plan for
QA/QC implementation
Notable Feat;
< Demonstrated abilities in fabrication of (6200 MT) Structure & Erection
of TG structure (4000MT.) completed on time without any reportable
accident.
Mar'05 - Oct'05 Asst. Construction Manager (Mech.) Larsen
& Toubro Limited
Company Larsen & Toubro Ltd.- ECCD Consultant CET
Client Rourkela Steel Plant, Rourkela, Orissa: Capital repair of
Blast Furnace - 4
Joined as Asst. Construction Manager (Mech.) and deputed to Rourkela Site,
to handle the shut down job for revamping of Blast Furnace # 4.
< Accountable for fabrication and erection of furnace Shell & structure
surrounding the furnace, erection of Bussle Main & accessories.
Notable Feat;
< Played a pivotal role in capital repair of Blast Furnace - 4 for
successful salamander tapping & get success in one time without any
repair.
< Received an appreciation letter for Good Quality Work from the client for
timely completion of the project.
Nov'03 - Mar'05 DY. Manager (IQA) McNally Bharat
Engineering Co. Ltd.
Company McNally Bharat Engineering Co. Ltd.(Manufacturing Unit at
Kumardhubi, Dist. - Dhanbad)
< Functioning as an In-charge: Inspection Quality & Assurance Department.
< Making documents for QAP / FQP of different Mechanical Equipment as
Quality internal auditor and responsible for MR function in ISO Quality
Audit:
Ball Mill Rod Mill Apron
Conveyor
Reciprocating Feeder Swing Hammer Reversible Impactor
Tripper
Double Roll Crusher Jaw Crusher
Ring Granulator
Flip Flow Screen Vibrating Screen Shuttle
Conveyor
Pressure Vessel etc. & critical spares.
Notable Feat;
< Steered function for procuring visual, dimensional, surface texture & NDT
inspection for procurement, fabrication, machining, assembly of assembled
Rotary Equipment, Vasa Pump & Final Dispatch.
< Dispatch of Zero defective products.
< Played a core member to handle activities for receiving no complains from
the client on quality of products and control over the cost of rework,
optimum utilization of man.
Apr'01 - Oct'03 Dy. Manager (M/C Shop) McNally Bharat
Engineering Co. Ltd.
Company McNally Bharat Engineering Co. Ltd. Manufacturing Unit at
Kumardhubi, Dist. - Dhanbad
Notable Feat;
< Steered functions in the machine Shop having:
< Heavy Machines: Double Column Vertical Turning & Boring M/c,
Horizental Boring M./c, Gear Hobbing M/c (Cap- 80 Module),
Plano Milling M/c
< Lathe: Heavy Duty Lathe, Center Lathe, CNC Lathe M/c
< Others: Planning M/c, Vertical Turning & Boring M/c
< Distinction of increasing the productivity by minimising setting time and
implementing incentive system.
< Reduced the number of reworks of the job by controlling the sequential
activity.
Nov'95 - Mar'01 Asstt. Manager (maint) McNally Bharat
Engineering Co. Ltd.
Company McNally Bharat Engineering Co. Ltd. Manufacturing Unit at
Kumardhubi, Dist. - Dhanbad
< Handling maintenance of several machineries & tools:
Lathe Boring M/c Vertical turning & boring M/c
Plano Milling M/c
Planning M/c Gear Hobbing M/c Slotting M/c Shaping
M/c
Hydraulic Shearing M/c Rolling M/c Press Brake
CNC Lathe M/c
Mechanical Punching M/c DG Engine Hydraulic & Pneumatic Tools
Compressor
< Performing of erection & commissioning of critical machineries and tools
covering:
Center Lathe Boring M/c Hobbing M/c Plano
Miller
Miller & Crushing Screening M/c
Notable Feat;
< Successfully implemented computerized planning for preventive maintenance
schedule for plant, Break down analysis, Inventory of Spares, Pre-
Assessment & Post Assessment of preventive maintenance.
< Actively involved in up keeping the machine history, breakdown hour,
reason of breakdown, spares used and spare to be arranged for future&
performance report of the individual M/c.
< Demonstrated abilities in operation & maintenance of stress reliving oil
furnace
< Worked as single point of contract to handle maintenance department
covering the area Mechanical Maintenance & Water Treatment Plant.
< Distinction of minimising the breakdown time from 22% to 12% and finally
it was with in 5% to 8%.
< Played a stellar role in starting and running:
o The 510 kva. DG Set (Imported) at the rated load which was in
breakdown and supposed to be disposed by the management.
o The shearing M/c (Cincinnati) which was really a challenge for
the maintenance team as it was in major break down & badly
damage the Hydraulic system since long back & declared for
disposed.
Academe` B.Tech in Production Technology from B.I.T. Sindri,
Dhanbad in 1995
Diploma in Production Technology from Govt. Polytechnic
Ranchi in 1989
General Intermediate in the Year 1984.
Matriculation in the Year 1982.
Personal Profile
Date of Birth: 11.10.1965
Present Address: Flat. No. 101, C/o Taramani Enclave, In front of Vishnu
Puri Shishu Mandir, Bardman Compound, ps-Lalpur, Ranchi,
Jharkhand, Pin-834001
Permanent Address: Vill Kazichak, PO: Ichhose, Ps: Islampur, Dist:-
Nalanda, State:- Bihar, Pin 801303
Present CTC: 24 Lakhs Per Anum
Expected CTC: Neqotiable
Notice for joining: Minimum Three Months.
NIRANJAN PRASAD
Date:-30/04/2013