[pic]
CURRICULUM VITAE
Name : MUHAMMAD FARRUKH ZAKI
Date of Birth : 7th February 1956
Marital Status : Married
Profession : Civil Engineer
Present Position : Resident Engineer
Specialization : Project Management & Construction Supervision of
Roads/Highways/pipeline /water treatment
plant /under ground dam/buildings related
Projects
Countries of Work Experience : Saudi Arabia, Oman, Pakistan & Bangladesh
Total Professional Experience : 29 Years
Work Experience in Gulf : 6 Yrs - 6 Months
Affiliation with Professional : - Member, Pakistan Engineering
Council
Institutions (Regd. #
Civil/6732)
- Saudi Council of Engineers (Regd. #
100095)
Driving License: : Oman, Saudi Arabia, Pakistan
KEY QUALIFICATIONS
Practicing professional Engineer since 1981.
- Construction Supervision of Roads / Highways / Buildings and
Infrastructure.
EDUCATION
Name of Institution Year Degree/Diploma
N.E.D. University of Engineering 1981 B.E. (Civil) Degree -
First Division
& Technology Karachi, Pakistan
EXPERIENCE (FROM PRESENT TO PAST)
1. Date: September 2012 till date (3rd April 2013)
Company: NESPAK, LOCATION: SAUDI ARABIA
Role held: Resident Engineer
Project: Construction Supervision of Sedimentation protection by Gabion
works upstream side of the Baysh dam and shadan dam, in jizan region,
Saudi Arabia.
Duties: I AM RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF EACH
CONTRACTOR, ADVISING THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE ANY OF
THE CONTRACTOR DID NOT COMPLETE THE PROJECT IN TIME,I AM SUPPOSED TO
RECOMMEND TO THE CLIENT ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC
CONDITIONS OF CONTRACT.
2. Date: March 20, 2012 to 27/7//2012
Company: Alishar construction company (Contractor FIRM)-Released by my
company to work for this contractor temporarily
Role held: Project Manager (site based), LOCATION: SAUDI ARABIA
Project Name: Water supply line 600mm DI pipes 49.8 km including 62
chambers from al-leeth dam to various cities, water treatment plant and
underground dam, SAUDI ARABIA)
Project Scope of Work: CONSTRUCTION OF pipeline 600 mm dia ductile irons
from dam near moa har area to al-leeth city 49.8 km
-construction of WTP with 2 clarifiers+teated water tank, distribution
chamber, pump house, administration building, SCECO building, etc.
3.
Date: July 2010 to-15/3/2012
Company: NESPAK (THE BIGGEST CONSULTANCY FIRM OF PAKISTAN-
www.nespak.com.pk)
Role held: RESIDENT ENGINEER
Project Name: BALADIA ROADS PROJECT, (IN RIYADH REGION SAUDI ARABIA)
Project Scope of Work: CONSTRUCTION OF NEW ROADS AND CULVERTS IN
JALAJIL,MAJMAA,AL-TAVIA,ROWDA SUDEER,HOWTA SUDEER AND TUMAIR
Value: 202 MILLION SAUDI RIYAL
Duties: RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF EACH
CONTRACTOR, ADVISING THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE ANY OF
THE CONTRACTOR DID NOT COMPLETE THE PROJECT IN TIME,I WAS SUPPOSED TO
RECOMMEND TO THE CLIENT ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC/
CONDITIONS OF CONTRACT.
THERE WER 3 CONTRAACTORS WORKING IN THE 6 CITIES MENTIONED ABOVE.FOR SIX
CITIES I HAD 6 SITE INSPECTORS, 6 SURVEYORS,2 QS, 2 MIs (MATERILAS
INSPECTORS) 3 C.Es (CIVIL ENGRS OF MIN 8 YRS EXPERIENCE)
3.
Date: October 2009 - July 2010
Company: ITALCONSULT (AN ITALIAN CONSULTANCY FIRM)
Role held: RESIDENT ENGINEER, LOCATION: SAUDI ARABIA
Project Name: Altawal-Jazan-Shuqqaq Expressway, 130 Km long with 29 Bridges
and 6 interchanges
Project Scope of Work: CONSTRUCTION OF NEW EXPRESSWAY (DUAL CARRIAGEWAY 6
LANE HAVING 29 BRIDGES, 6 INTERCHNAGES, 84 PIPE CULVERS (1000 MM DIA), 46
BOX CULVERTS (FROM SINGLE BARREL TO 12 BARRELS)
Value: 600 MILLION SAUDI RIYAL
Duties: I WAS RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF WORK, ADVISING
THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE THE CONTRACTOR DID NOT
COMPLETE THE PROJECT IN TIME,I WAS SUPPOSED TO RECOMMEND TO THE CLIENT
ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC CONDITIONS OF CONTRACT.
IN THIS PROJECT A MAJOR PROBLEM WAS OBSTRUCTIONS LIKE ELECTRIC POLES,
HOUSES, CULTIVATED LANDS, GRAVEYARDS ETC.I WAS ALSO RESPONSIBLE TO RECEIVE
FROM THE CONTRACTOR GENERAL PLAN SHOWING SIZE (AREA) THE OBSTRUCTIONS,
CHECK ITS CORRECTNESS AND THEN FOR WARD TO THE MINISTRY OF TRANSPORT FOR
REMOVAL OF THE OBSTRUCTIONS THRU THE CONCERNED AGENCIES.
THE PROJECT PASSED THRU DESERTS, HILLS AND SABKHA AREAS ( SABKHA AREA IS A
SANDY DESERT WITH VERY HIGH WATER TABLE (SALTY) WHICH MAKES CONSTRUCTION
MORE DIFFICULT AS COMPARED TO NORMAL DESERTS.
AL THE BRIDGES HAD PRE-STRESSED CONCRETE GIRDERS OF 19.80 M LENGTH.THE
LARGEST BRIDGE WAS OF 200M LONG.ALL THE BRIDGES WERE ON PILE FOUNDATIONS.
4
Date: June 2008 - October 2009
Company: ITALCONSULT (AN ITALIAN CONSULTANCY FIRM)
Role held: RESIDENT ENGINEER, LOCATION: SAUDI ARABIA
Project Name: Majmaa-Shaqra expressway 96 km long, Riyadh region, Saudi
Arabia
Project Scope of Work: CONSTRUCTION OF NEW EXPRESSWAY (DUAL CARRIAGEWAY 12
PIPE CULVERS (1000 MM DIA), 6 BOX CULVERTS (FROM SINGLE BARREL TO 10
BARRELS)
Value: 165 MILLION, SAUDI RIYAL
Duties: I WAS RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF WORK, ADVISING
THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE THE CONTRACTOR DID NOT
COMPLETE THE PROJECT IN TIME,I WAS SUPPOSED TO RECOMMEND TO THE CLIENT
ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC CONDITIONS OF CONTRACT.
5
Date: January 2007 - May 2008
Company: NESPAK (CONSULTANTS)
Role held: PROJECT MANAGER (CONSTRUCTION),LOCATION: PAKISTAN
Project Name: construction supervision of ADB assisted NHA project CSP-2.
Hub-Uthal Road: 85 km
Multan-Muzaffar Garh Including Muzaffar Garh bypass) : Road 36.5 km
Sukkur -Jacobabad Road: 65 km
Project Scope of Work: CONSTRUCTION OF NEW ROADS AND CULVERTS AS PART OF
NETWORK OF NATIONAL HIGHWAYS IN PAKISTAN.
VALUE:75M USD
Duties: AS A PROJECT MANAGER (CONSTRUCTION SUPERVISION) I WAS RESPOSIBLE
FOR OVERALL MANAGEMENT OF THE WORK.NESPAK WAS THE LEAD CONSULTANT OF THE
JV OF 5 LOCAL CONSULTANTS.
. Also working as Proposal engineer for highway division of nespak
. Also coordinator for the 459 km road project in Balochistan (Basima-
Nag-Panjgur-Hoshab)
. Also coordinator for German SWAB road projects in Mansehra and
Abbott Abad.
6
Date: December 2006 - January 2007
Company: NESPAK (CONSULTANTS)
Role held: Deputy Team Leader, LOCATION: PAKISTAN
Project Name: construction supervision of ADB assisted NHA project CSP-2.
Hub-Uthal Road: 85 km
Multan-Muzaffar Garh Including Muzaffar Garh bypass) : Road 36.5 km
Sukkur -Jacobabad Road: 65 km
VALUE:75M USD
DUTIES: AS DEPUTY TEAM LEADER (CONSTRUCTION SUPERVISION) I WAS RESPOSIBLE
TO ASSIST THE TEAM LEADER IN CARRYING OUT HIS DURIES AS THE TEAM LEADER OF
THE PROJECT.HELPING OUT THE PM IN PREP OF MONTHLY REPORT, PROCESSING
CONTRACTOR'S IPCS.DEPLOYMENT OF SUPERVISION STAFF. ETC
7
Date: May 2006 - Dec 2006
Company: NESPAK (CONSULTANTS)
Role held: Senior Expat Contract Specialist, LOCATION: BANGLADESH
Project Name: 4 laning of Dhaka-Chittagong highway
VALUE:75M USD
Scope of work: construction of 2 additional lanes 189 km long for the
existing road from Dhaka to Chittagong including 36 bridges and 84 culverts
DUTIES: My duty was to prepare pre-tender documents like general conditions
of contract, technical specifications, BOQ
8
Date: JANUARY 2006 TO APRIL 2006
Company: NESPAK (CONSULTANTS)-LOCATION: OMAN
Role held: RESIDENT ENGINEER
PROJECT NAME: CONSTRUCTION SUPERVISION OF MAHOUT TO NIZWA - THUMRAIAT ROAD
(SECTION - II).
PROJECT SCOPE:
o 30 km new Asphalt Road
o 28 Nos. Box and Pipe Culverts (of variable cells)
The construction period was 12 months ended in April 2006.
VALUE: 45M USD
Duties: I WAS RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF WORK, ADVISING
THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE THE CONTRACTOR DID NOT
COMPLETE THE PROJECT IN TIME,I WAS SUPPOSED TO RECOMMEND TO THE CLIENT
ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC CONDITIONS OF CONTRACT.
9
Date: Sept 2004 - DECEMBER 2005
Company: NESPAK (CONSULTANTS)-LOCATION: OMAN
Role held: RESIDENT ENGINEER
PROJECT NAME: CONSTRUCTION SUPERVISION OF MAHOUT TO NIZWA - THUMRAIAT ROAD
(SECTION - III).
VALUE: 55M USD
PROJECT SCOPE:
o 41 km new Asphalt Road
o 23 km long Track Road to divert the traffic in case the road has to be
closed for traffic during routine practice session of Military.
o Construction of 2 km long Runway (where C-130 Aircraft would land with
2 Tanks on board)
o Tank Crossings: 4 tank crossings on the road.
Duties: I WAS RESPOSIBLE FOR QUALITY ASSURANCE OF THE WORK DONE BY THE
CONTRACTORS, CHECKING & PROCESSING CONTRACTORS' IPCs, PREPARATION OF
MONTHLY PROGRESS REPORTS, KEEPING AN EYE ON THE PROGRESS OF WORK, ADVISING
THE CONTRACTOR IF FOUND BEHING SCHEDULE,IN CASE THE CONTRACTOR DID NOT
COMPLETE THE PROJECT IN TIME,I WAS SUPPOSED TO RECOMMEND TO THE CLIENT
ABOUT TIME EXTENSION AS PER ARTICLE 44 OF FIDIC CONDITIONS OF CONTRACT.
10
Date: July 2003 - September 2004
Company: NESPAK (CONSULTANTS)
Role held: PRINCIPAL ENGINEER, LOCATION:PAKISTAN
PROJECT NAME: QUAILY ASSURANCE AND PROPOSALS
PROJECT SCOPE: PREPARATION OF TECHNICAL AND FINANCILA PROPOSALS FOR HIGHWAY
PROJECT.PREP OF PRE-QUALIFICATION DOCUMENTS.QUALITY ASSURANCE OF ALL
DOCUEMTNS PREPARED BY CONTRAC SECTION (TECHNICAL SPECIFICATIONS, TENDER
DRAWINGS AND VILUNE-1 (GENERAL CONDITIONS OF CONTRACT)
DUTIES: As Principal Engineer Quality Assurance & Proposals (QA&P)
responsible for the preparation of proposals, quality assurance of
documents like Technical specifications of the Contract, TENDER
Drawings, Engineer's Estimate etc. Preparation of Expression of
Interest, writing Letters of Interest for projects in Pakistan and
abroad. Meetings with various Consulting Firms to form Joint Ventures
for projects etc.
11
Date: October 2000- July 2003
Company: NESPAK (CONSULTANTS)
Role held: SENIOR ENGINEER, LOCATION:PAKISTAN
PROJECT NAME: CONSTRUCTION SUPERVISION OF PUNJAB HIGHWAY PROJECT
SCOPE: GENERAL SUPERVISION OF ROAD, BRIDGES AND CULVERTS IN THE CENTRAL
PART OF THE PROVINCE OF PUNJAB IN PAKISTAN.THERE WERE 3 BRIDGES (2 OF
CONVENTIONAL CONCRETE GIRDERS AND ONE PRE-STRESSED)
VALUE: 6M USD
DUTIES: I WAS RESPOSIBLE FOR OVERALL QUALITY OF WORKS OF THE PROJECT AND
PROCESSING OF IPCs OF THE CONTRACTOR.
12
Date: Nov. 1998 to Sept. 2000
Company: NESPAK (CONSULTANTS)
Role held: Assistant Resident Engineer, LOCATION:PAKISTAN
PROJECT NAME: FARM TO MARKET ROADS
PROJECT SCOPE: Construction Supervision of ADB assisted Rural Access
Roads Projects over 100 Km long having over 125 No. Culverts, in
Pakpattan & Sahiwal Districts. This residency was spread over two
districts of South Punjab; Sahiwal and Pakpattan Sharif. Two roads were
in Sahiwal and the rest in Pakpattan Sharif.
VALUE:27M USD
DUTIES: I WAS RESPONSIBLE TO ASSIST THE RE IN QUALITY ASSURANCE OF
PROJECTS, IN PROCESSING THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND
MONTHLY PROGRESS REPORTS,COMPARING WORK DONE AGAINST THE CONSTRUCTION
SCHEDULE,LETTER DRAFT LETTERS ABOUT QUALITY OF WORKS TO THE
CONTRACTOR.CHECKING BAR BENDING SCHDULES FOR THE STRUCTURES.
13
Date: MAY1998 to NOV1998
Company: NESPAK (CONSULTANTS)
Role held: Resident Engineer, LOCATION:PAKISTAN
PROJECT NAME: Bridge over main Railway Track at Garhi Shahu, Lahore
PROJECT SCOPE: bridge 250m long with 500mm diameter piles, pre-
stressed girders 22m long, deck slab, approach slabs and 100 m road with
embankment on each side of the bridge.
VALUE: 15M USD
DUTIES: I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS,
PROCESSING THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY
PROGRESS REPORTS,COMPARING WORK DONE AGAINST THE CONSTRUCTION
SCHEDULE,WRITING LETTERS ABOUT QUALITY OF WORKS TO THE
CONTRACTOR.MAKING SURE THAT THE STAFF IS WORKING PROPERLY.
14
Date: Jan1995 to April1998
Company: NESPAK (CONSULTANTS)
Role held: Resident Engineer, LOCATION:PAKISTAN
PROJECT NAME: Fyzee Rahamin Art Gallery in Karachi
SCOPE: 3 STOREY BUILDING OF ART GALLERY & AUDITORIUM WITH SEATING CAPACITY
OF 1800 PEOPLE. IT WAS A CENTRALLY AIR CONDITIONED BUILDING.
VALUE: 5M USD
DUTIES:I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS, PROCESSING
THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY PROGRESS
REPORTS,COMPARING WORK DONE AGAINST THE CONSTRUCTION SCHEDULE,WRITING
LETTERS ABOUT QUALITY OF WORKS TO THE CONTRACTOR.MAKING SURE THAT THE
STAFF IS WORKING PROPERLY.
15
Date: Aug 1994 to Dec1994
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer (claim analyst), LOCATION:PAKISTAN
PROJECT NAME: Evaluation of claims for Korangi Fisheries and Harbor
Authority
SCOPE: Evaluation of claims for Korangi Fisheries and Harbor Authority,
Karachi 380 million Pakistan rupees claim. There was disagreement
between the Contractor and the Consultant about the recommendations of
the Consultants. So NESPAK (the biggest Pakistani consultant were hired
to give final recommendations. I was assigned this task.
Duties: My duty was to do the job single handedly,
I completed the job and was accepted by the concerned parties.
16
Date: June 1992 to July 1994
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer Construction, LOCATION:PAKISTAN
PROJECT NAME: Development of 2 new tows near Karachi (NORTH KARACHI AND
SURJANI TOWN) OF KARACHI DELEVOPMENT AUTHORITY
SCOPE: CONSTRUCTION OF MORE THA 100 KM LONG ROADS & 21 CULVERTS, WATER
SUPPLY, SEWERAGE AND 1000 FLATS*APPARTMENT (4 STOREY)
VALUE:3.5M USD
DUTIES: MY DUTY WAS TO SUPERVISE THE CONSTRUCTION FROM QUALITY POINT OF
VIEW AND PROCESSING OF CONTRACTOR IPCs,
17
Date: Jan1991 to May1992
Company: NESPAK (CONSULTANTS)
Role held: Resident Engineer, LOCATION:PAKISTAN
PROJECT NAME: Headquarters Building Pakistan Medical & Dental Council at G-
10/4 Islamabad, and Ware House of duty Free shops in I-11/4 Islamabad.
SCOPE: 3 STOREY BUILDING WITH CENTRAL AIRCONDITIONING SYSTEM.
VALUE:3.0M USD
DUTIES: I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS, PROCESSING
THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY PROGRESS
REPORTS,COMPARING WORK DONE AGAINST THE CONSTRUCTION SCHEDULE,WRITING
LETTERS ABOUT QUALITY OF WORKS TO THE CONTRACTOR.MAKING SURE THAT THE STAFF
IS WORKING PROPERLY.
18
Date: Jan 1989 to Dec1990
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer Construction, LOCATION:PAKISTAN
PROJECT NAME: Construction Supervision of Pak - Suzuki Plant near Karachi
SCOPE: PAK SUZUKI MOTOR'S PLANT COMPRISING THE PLANT, WATER TANKS, MOSQUE,
THE MAIN PLANT HAD ROOFING OF PRE-CAST PLANKS RESTING ON STRUCTURAL STEEL
TRUSSESS RESTING ON RCC COLUMNS.
DUTIES: I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS, PROCESSING
THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY PROGRESS REPORTS ON
BEHALF OF THE RE,COMPARING WORK DONE AGAINST THE CONSTRUCTION
SCHEDULE,WRITING LETTERS ABOUT QUALITY OF WORKS TO THE CONTRACTOR.MAKING
SURE THAT THE STAFF IS WORKING PROPERLY.
19
Date: Jan1988 to Nov1988
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer, LOCATION:PAKISTAN
PROJECT NAME: CONTRACT PREPARATION CELL
SCOPE: PREPARATION OF CONTRACT DOCUMENTS (TECHNICAL SPECIFICATIONAS AND THE
GENERAL CONDITIONS OF CONTRACT) FOR ROADS AND BUILDING PROJECT.
DUTIES: I WAS RESPOSIBLE FOR PREPARATION OF CONTRACT DOCUMENTS AND SUBMIT
TO THE PRINCIPAL ENGINEER
20
Date: Feb1987 to Dec1987
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer Construction, LOCATION:PAKISTAN
PROJECT NAME: CONSTRCUTION OF NATIONAL STADIUM KARACHI FOR WORLD CUP
CRICKET 1897
SCOPE: CONSTRUCTION OF NEW GENERAL ENCLOSURE, CLUB ENCLOSURE AND STUDENTS'
ENCLOSURE WITH ROOF.ROOF WAS OF PRE-CAST PLANTS PLACED ON STRUCTURAL STEEL
TRUSSES PLACED ON STELL COLUMNS ON FIELD SIDE AND RCC COLUMNS ON THE OUTER
SIDE.
VALUE:5M USD
DUTIES: I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS, PROCESSING
THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY PROGRESS REPORTS ON
BEHALF OF THE RE,COMPARING WORK DONE AGAINST THE CONSTRUCTION
SCHEDULE,WRITING LETTERS ABOUT QUALITY OF WORKS TO THE CONTRACTOR.MAKING
SURE THAT THE STAFF IS WORKING PROPERLY
.
20:
Date: 1985 to jan1987
Company: NESPAK (CONSULTANTS)
Role held: SENIOR Engineer Construction, LOCATION:PAKISTAN
PROJECT NAME: Construction Supervision of Road from Star Gate to Karachi
Airport
SCOPE: CONSTRCUTION SUPERVISION OF ROAD AND CULVERTS FROM STAR GATE ON MAIN
NATIONAL HIGHWAY TO THE TERMINAL 3 OF KARACHI AIRPORT.
IT WAS WATER BOUND MACADAM ROAD WITH BINDER COURSE AND WEARING COURSE.
VALUE:0.55M USD
DUTIES: I WAS RESPONSIBLE FOR QUALITY ASSURANCE OF PROJECTS, PROCESSING
THE IPCs OF THE CONTRACTORS,MAKING WEEKLY AND MONTHLY PROGRESS REPORTS ON
BEHALF OF THE RE,COMPARING WORK DONE AGAINST THE CONSTRUCTION
SCHEDULE,WRITING LETTERS ABOUT QUALITY OF WORKS TO THE CONTRACTOR.MAKING
SURE THAT THE STAFF IS WORKING PROPERLY
21:
Date: 1981 to 1985
Company: NESPAK (CONSULTANTS)
Role held: JUNIOR Engineer (construction)
PROJECT NAME: Main Access Roads (asphalt concrete) from National Highway
to Port Bin Qasim including Bridges and Culverts. Thickness of binder
course was 40 mm and that of wearing course 40 mm.THERE WERE 2 BRIDGES OVER
MAIN RAILWAY TRACK.BOTH WITH PRE-STRESSED GIRDERS.ONE WAS SKEW AND OTHER
STRAIGHT.ONE WAS 80M LONG AND THE OTHER WAS 91M LONG.
CULVERTS WERE OF 2 BARRELS TO 14 BARRELS.
DUTIES: AS JUNIOR ENGINEER MY DUTIES WERE TO ASSIST THE SENIOR ENGINEER IN
CHECKING THE REINFORCEMENT STEEL OF BRIDGES AND GIRDERS AND THOSE OF
CULVERTS,ALSO COMPACTION OF SUB-BASE AND BASE CORSE LAYERS.
CONTACT: Cell : +966-*********
E-mail : ********@*****.***
LANGUAGE CAPABILITY
English - Excellent in speaking, reading and writing
Arabic - Fair in speaking
Urdu - mother language
Bengali - Excellent in reading, writing and speaking (I was born
in Bangladesh and brought up there till the age of 14)
Dated: 02 MAY, 2013 [pic]