Posted/Modified on: 04/10/2012 04:31 PDT
Resume Title:
Lead Scheduler
Contact e-mail:
abpqcv@r.postjobfree.com
Industry:
Power, Oil, Gas
Desired Location:
Lake Charles, La
Willing to Relocate:
No
Desired Salary:
$61/hr - $75/hr
NAME: Dickey Lynn Monceaux
CITIZEN: USA
EDUCATION: High School Graduate
TRAINING Project Management Institute,
CPM, Timberline & Detail Estimating, Cost, SAP, JD
Edwards
Primavera P3, P3e, P5, P6
MARITAL STATUS: Married
ADDRESS: 2211 Division Rd
Sulphur, La
cell
abpqcv@r.postjobfree.com
Feb 2009
-PresentShaw Modular Solutions
Lake Charles, La
Nuclear Modules
2011
-2012Assistant Production Manager (Interim
)
2009
-2011Planning/Scheduling Manager
Plan and develop and schedule module fabrication for 6 separate Nuclear Units. I am
responsible for managing 3 schedulers and 4 planners. Daily Reports, Weekly Reports,
Histograms & Monthly Reports. Current schedule is over 100,000 activities
Jan 2005
-2009RECON ENGINEERINING
Sulphur, La.
Petro Chemical Engineering & Management
JAN 2007 Turnaround Lead, Lead Planner, P5/6 Scheduler
FEB 2009 ConocoPhillips Refinery
Lake Charles, La.
Plan, Develop Schedules in P5/P6, and Develop Level 2 &3
Estimates, SAP, Track Cost & Execute Turnarounds for COP
Turnaround Group
JUN
2005Planner/Scheduler
JAN 2007 CITGO Refinery
Lake Charles, La.
Develop scope, Define material & equipment requirements,
Plan, build schedules, & update and maintain schedules
during execution of T/As. Produce histograms, S-Curves,
And Earned Value Reports daily.
1995
-2005FOSTER WHEELER CORPORATION
Clinton, NJ
Petro Chem, Pharmaceutical & Power EPC
JAN 2001 Project Controls/Lead Planner/Scheduler
JUN 2005 Cinergy (Gibson Station)
Owensville, In.
Installation of 5 SCR Units on an existing power plant facility. Responsible for earned
value reporting, 2 week look a heads, manpower histograms, resource loading and building
hourly schedule for outages. Performed weekly cost & schedule analysis. Updated the
schedule weekly and uploaded the CIR into P3 for actual % complete progress. Built and
maintained several commissioning schedules. Built and maintained master schedules with
several sub projects interface.
OCT
2000Area Superintendent
JAN
2001Cinergy (Gibson Station)
Princeton, IN
Installation of new SCR Units on an existing power plant facility.
JAN
2000Piping Superintendent
OCT 2000
Bay Shore Refining
Oregon, OH
Construction of a 180 MW Repowering Project including 8,000 linear feet of pet coke
conveying, water and treatment system, boiler, ash handling, limestone handling and
balance of plant work.
SEP
1999
Shop Superintendent
JAN 2000 Chickasaw Fabrication Facility
Built Pipe Rack Modules for Venezuela
Chickasaw, AL
DEC 1998
Project Superintendent
SEP 1999
Formosa Plastics Corp.
Point Comfort, TX
Pipe rack/piping installation project on an Ethylene/Propylene Purification Unit.
MAR
1998Piping Superintendent
SEP 1998
Westlake Petrochem
Sulphur, LA
Engineering, procurement and construction of the offsites for the Lipex Unit.
SEPT
1997Field Superintendent
MAR 1998
Seadrift Coke L.P. Project
Seadrift, TX
Coker Revamp.
OCT
1996Field Superintendent
JULY
1997Roche Carolina, Inc.
Florence, SC
Erection of a Bulk Pharmaceutical Launch Facility
JAN
1996Construction Manager
SEP 1996
Vista Chemical Company
Lake Charles, LA
ETO Expansion Project
AUG
1995Project Superintendent
DEC 1995
Jamaica Public Service Co. Ltd
Old Harbour, Jamaica
Replace Boiler Unit #4
MAY 1995 Area Manager/Estimator
JULY 1995 Lake Charles, LA
Marketing, Estimating, and Project Execution
1989
- 1995WEST-CAL CONSTRUCTION
Sulphur, LA
Capital, Maintenance & Turnarounds
Project Manager
- Responsible for estimating, planning, scheduling, cost control and
served as jobsite superintendent on numerous capital projects in Lake Charles and Beaumont
area.
1995 Project Superintendent
Star Enterprise
Port Arthur, TX
Sulphur Recovery Turnaround
1994 Project Superintendent
Beaumont Methanol
Beaumont, TX
Sour Water Expansion
1994 Project Superintendent
Arcadian
Lake Charles, LA
Decommission Ammonia Plant
1994 Project Superintendent
CITGO
Lake Charles, LA
Benzene Recovery
1994 Project Superintendent
Conoco
Lake Charles, LA
Coker Turnaround
1993 Night Superintendent
CITGO
Lake Charles, LA
Waste Water Plant
1993 Project Superintendent
Big 3
Lake Charles, LA
Turnaround
1993 Project Superintendent
Tetra
Lake Charles, LA
Turnaround
1993 Project Superintendent
West Lake, Petro Chemical Chem.
Lake Charles, LA
Capital
1992 Project Superintendent
Big 3
Carlyss, LA
Turnaround
1991 Project Superintendent
CITGO
Lake Charles, LA
Amine Vessels
1990 Project Superintendent
Citcon
Lake Charles, LA
Wax Recovery
1989 Project Superintendent
Citcon
Lake Charles, LA
Turnaround
1989 Project Superintendent
Certainteed
Lake Charles, LA
Maintenance
1989 Night Superintendent
Arcadian
Lake Charles, LA
Ammonia Turnaround
Also many small capital projects at all local plants.
1982
- 1989AUSTIN INDUSTRIAL
Beaumont, TX
Capital, Maintenance & Turnarounds
Site Manager
- Over a maintenance & capitol contracts for five (5) years at Chevron USA
in Port Arthur, TX. 800 employees
1984
- 1989 Various maintenance and capital projects
1989
Piping SuperintendentTexaco Chemical
Port Arthur, TX
Ethylene Turnaround
1989
Piping SuperintendentFina
Port Arthur, TX
FCCU Revamp
1988
Project SuperintendentChevron USA
Port Arthur, TX
FCCU Turnaround
1987
Project SuperintendentChevron USA
Port Arthur, TX
FCCU Turnaround
1986
Project SuperintendentChevron USA
Port Arthur, TX
FCCU Turnaround
1985
Project SuperintendentChevron
Port Arthur, TX
FCCU Turnaround
1984
Project SuperintendentTexaco
Port Arthur, TX
FCCU Turnaround
1983
Project SuperintendentTexaco
Port Arthur, TX
FCCU Revamp
1982
Piping SuperintendentChevron
Port Arthur, TX
Benzene Pipeline
1982
- 1983MARS CONSTRUCTION
1983
Site SuperintendentTexaco
Port Arthur, TX
Vacuum Turnaround
1983
General ForemanGulf Refinery
Port Arthur, TX
FCCU Turnaround
1982
Fabrication Shop Superintendant
Lake Charles, LA
1973
- 1982PIPEFITTER - LOCAL 106
Lake Charles, LA
General Foreman, Foreman, Welder, Fabricator,
Pipe fitter, Instrument Fitter & Pipeline
Welder
.
I worked on many local plants & pipeline projects in the Lake Charles and surrounding
areas including offshore pipe lay barges. Work in several shipyards & offshore platforms
throughout the Gulf Coast. Worked in several major fabrications shops from Houston to Lake
Charles.
1981 Foreman PPG (Lk Charles, LA) Fluor Daniels Cap.Project
1980 Foreman-CITGO Lake Charles, LA) Foster Wheeler Coker
1979
Welder / Fitter-CITGO (Lake Charles, LA
) FCCU
1978
Welder / Fitter-CITGO (Lake Charles, LA
) Petro Chem
1977
Foreman-Gulf States Utilities (Lake Charles, LA) Bechtel
Heavy Wall Rigging
1976
Pipefitter-LNG (Lake Charles, LA) Welder - K.C.I
.
1975
Apprentice- Augustine CITGO Maintenance
1974
Apprentice- American Fabricators- Conoco Cap. Project
1973 Apprentice- Firestone / C.F. Braun Capital Project
BROWN & ROOT
1979
Welder ARCO (Houston, TX) Oxarain.
Shell Oil
(Houston, TX
) FCCU Grassroots
1975
Welder Dupont (Orange, TX
) ADR ExpansionREFERENCES
Rusty Parnell
Project Controls Manager for Cinergy Power Plant
abpqcv@r.postjobfree.com
Dale Krider
Product Manager
for Shaw Modular Solutions
abpqcv@r.postjobfree.com
Martin Lacey
Project Director for Foster Wheeler