Ronald L. Mailhot

888 Lake Rd Burbank, WA 99323 * Phone: 509-***-****, Work: 509-***-****

E-mail: aboy49@r.postjobfree.com or aboy49@r.postjobfree.com

PROFILE

Twenty Seven years in the nuclear power industry with experience as follows: Project Controls, Field Engineering, Project Scheduling, Supervision, Refueling Operations, Mechanical Planner to include: Corrective Maintenance, PM, Modification and Decommissioning Planning, Primavera P6 Scheduler.

Work performed utilizing the Core Values of Teamwork, Excellence and Accountability, Mutual Respect and Trust achieved through Open, Honest Communication.

* Planner/Work Analyst (Mechanical & Civil)

* Indus IAS Passport Portal G/J

* Project Controls Scheduler/Cost Analyst

* Primavera P6 Proficient and Certified Scheduler

* DOE Civil Decommissioning and Demolition Planning

* Civil Field Engineer/Supervisor

* Certified Technical Director / Refuel Floor Supervisor for General Electric Nuclear

* Westinghouse Split Pin Replacement

* ANSI/ASME Codes

* JCS, CHAMPS, RMIS, HDCS, ACCESS PJS, AJHA For Hanford

TRAINING

* General Electric Hitachi Certified Refuel Floor Operations Technical Director/Supervisor

* Concepts of Planning (AEP Electric)

* Nuclear Power Plant Systems Training (AEP Electric)

* High Performance Team Training (IMPO)

* Microsoft Project (Glendale Community College)

* Westinghouse Reactor Cooling Pumps and Motor Inspection Course (Duke Power/Westinghouse)

* Byron Jackson Reactor Coolant Pump training (AREVA Nuclear Technologies)

* Reactor Coolant Pump over haul and repair training (APS/Combustion Engineering, Siemens Allis/KSB)

* Overhaul of steam feed water pumps and resurfacing machines; hydraulic cutting machines (General Electric)

* Nuclear Reactor Head Technician training (Westinghouse)

* Nuclear Refueling equipment operation certification and qualification (various nuclear stations)

* Westinghouse Control Rod Drive Split Pin Replacement

* Control Rod Drive Mechanism (CRDM) maintenance and in-core instrumentation replacement (AREVA Nuclear Technologies)

* Motor actuator refurbishment course (ITI Movats)

* Certified Motor Actuator Technician, ANSI 3.1 current (AREVA Nuclear Technologies)

* Steam generator and eddy current equipment training (AREVA Nuclear Technologies)

* B.T.R.I.S,Brooks Top of Reactor Inspection Service: (R Brooks Associates)

* Watercraft Engineer for MOS 61B40, vessel first mate (U.S. Army

EXPERIENCE

Columbia Generating Station, Energy-Northwest

Planning and Scheduling Work Control Group- Direct Position (12/2008 to Present)? Provide technical knowledge and experience in the development of Computerized Primavera P6 Schedules for Corrective, Preventive, and Predictive Maintenance during on line and off line plant operations. ?Committed to ?Pride In Performance? expectations for the future of Columbia Generating Station.

Computer Programs used: Primavera P6, Indus IAS/Passport, Peoplesoft, Excel

General Electric Hitachi Outage Scheduler/Planner, Exelon LaSalle Power Station

(10/2008-12/2008) Responsible for maintaining, updating, tracking and interfacing with the Dresden Scheduling Department providing daily status reports for the General Electric outage schedule. Coordinated activities within Client shared scheduling tools. Work performance involved teamwork in a strong team-oriented environment committed to working with emphasis on safety, quality, and team morale.

Computer Programs Used: PASSPORT/PORTAL J, Microsoft Project 2003, Primavera

Preventative Maintenance Optimization (PMO) Planner, Southern Company Pilgrim Nuclear Station, Shaw Group

(05/2008 to 10/2008) Prepare detailed Model Work Orders for the Preventative Maintenance Optimization Program packages in compliance with industry standards to include proper written instruction, historical data, procedures, clearance boundaries; ensuring correct course of action to ensure a safe and successful completion of work performed.

Computer programs used: Indus IAS/Passport, Word, Excel,

Project Controls Specialist, FF&L Turkey Point, Areva

(03/2008-05/2008) Support AREVA Project Management during full scope refueling outage, duties and activities included work package control and status tracking, refuel activities schedule reporting for the POD, Field Support, Clearance Tag holder for Reactor Head and Reactor Cooling Pump(s) maintenance, material verification and requisitioning and work package closures.

Computer programs used: PASSPORT/PORTAL G, Word, Excel, Access, Noms,

Project Controls Specialist, Exelon LaSalle Power Station, General Electric Hitachi

(12/2007-03/2008) Support to GEH Project Management refuel floor and under-vessel work activities to include work package status tracking, refuel activities scheduling, field support, material verification and requisitioning and work package closures. Coordinated activities within Client shared scheduling tools.

Computer Programs Used: PASSPORT/PORTAL J, Microsoft Project, Word, Excel, Access

Project Controls Cost Analyst/Scheduler, Columbia Generating Station

(01/2007- 10/2007) Prepared project plans utilizing planner/scheduler skills, schedule and detail manpower utilization plans. Ascertained that the correct scope of work is reflected on all schedules. Integrated inter-discipline, cross-functional, and subcontract schedule requirements and restraints to establish logical work sequences. Prepared and scheduled resources and quantities as well as progress, and performance reports. Prepared and maintained milestone summaries, intermediate and detail level schedules and punch-lists. Prepared detailed manpower utilization plans. Analyzed critical path and restraints to determine effect of changes on the schedule and recommended work around to mitigate impacts. Coordinated activities within Client shared scheduling tools.

Computer programs used: PASSPORT/PORTAL J, MICROSOFT PROJECT 2003, Word, Excel, Access

Outage Scheduler/Planner, Exelon Dresden Power Station, General Electric Hitachi

(10/2006-12/2006) Responsible for maintaining, updating, tracking and interfacing with the Dresden Scheduling Department providing daily status reports for the General Electric outage schedule. Coordinated activities within Client shared scheduling tools.

Computer programs used: PASSPORT/PORTAL J, Microsoft Project software

Construction Maintenance Planner, Exelon Quad Cities Power Station, Venture Group

(08/2006-10/2006) Prepared detailed Construction Maintenance work packages in compliance with industry and plant standards to include proper written instruction, historical data, procedures, clearance boundaries; ensuring correct course of action to ensure a safe and successful completion of work performed. Monitored work order needs based on established priorities and scheduled dates. Coordinated activities within Client shared scheduling tools.

Computer programs used: PASSPORT/PORTAL J, Microsoft Word, Myraid.

Refuel Outage Scheduler/Planner, Exelon Quad Cities Power Station, General Electric Hitachi

(03/2006-04/2006) Responsible for maintaining, updating, tracking and interfacing with the Quad Cities Scheduling Department providing daily status reports for the General Electric outage schedule. Coordinated activities within Client shared scheduling tools.

Computer programs used: PASSPORT/PORTAL J, Microsoft Project software

Refuel Outage Scheduler/Planner, Exelon Clinton Power Station, General Electric Hitachi

(11/2005-02/2006) . . . Responsible for providing refuel floor and under-vessel work package tracking, scheduling, field support, material requisitioning and work package closures. Coordinated activities within Client shared scheduling tools.

Computer programs used: PASSPORT/PORTAL J, Microsoft Project, Word, Excel, Access

Maintenance Planner for Hurricane Recovery, Day & Zimmerman, FP&L St. Lucie Power Generation Station,

(06/2005 to 11/2005) Prepared Hurricane Recovery work packages in compliance with industry standards to include proper written instruction, historical data, procedures, clearance boundaries; ensuring correct course of action to ensure a safe and successful completion of work performed. Monitored work order needs based on established priorities and scheduled dates. Computer programs used: PASSPORT/PORTAL J, Microsoft Word, Excel, Access

Areva Reactor Head Service Technician, FP&L Turkey Point Power Generation Station

(03/2005) Reactor Head Removal Project team member. Duties included initial job preparation, disconnection and separation of the Reactor Head from the Reactor Vessel for Reactor Head replacement. Duties also included operation of nuclear fuel handling equipment during reactor core fuel offload.

Civil Construction Planner for Security Upgrades Project, FP&L Turkey Point Power Generation Station

(09/2004 ? 03/2005) Initiated and prepared Plant Change Modification (PCM) work packages, interfaced with Engineering, Safety and Operations groups as required during work package preparation, implementation and work package closure. Monitored work-order needs based on established priorities and scheduled dates.

Contacted and communicated with venders as required in support of work activities. Prepared supporting documentation as needed, Performed job site observations, initiated material request/store orders ensuring pre-staging of parts to support planned work activities.

Computer program used: PASSPORT/PORTAL J, Microsoft Word, Excel.

NPS Planner for Corrective Maintenance, Day & Zimmerman, FP&L St. Lucie Power Generation Station

(02/2004 to 08/2004) Prepared detailed work packages in compliance with industry and plant standards to include proper written instruction, historical data, procedures, clearance boundaries; ensuring correct course of action to ensure a safe and successful completion of work performed. Monitored work order needs based on established priorities and scheduled dates.

Computer program used PASSPORT/PORTAL J, Chesterton Valve Wizard Program, Microsoft Word and Excel.

Planner for Civil D & D Projects, Department Of Energy / Fluor Federal Services,

Hanford K Basin Hanford K Basin Sludge and Water System Retrieval

(08/2003 to 01/2004) Responsible for providing work package preparation, field support, scheduling, and oversight of assigned work tasks ensuring safe and successful performance of maintenance and decommissioning work activities for the K Basin Spent Fuels/Sludge Water System and Reactor Decommissioning project.

Identified required drawings, materials, tests, evaluations, and support groups, interfaced with vendors, engineering, environmental and production support groups in compliance with Fluor Federal Services and Department of Energy regulations.

Computer Programs used: JCS, CHAMPS, RMIS, HDCS, ACCESS, PJS, AJHA, and Microsoft Project.

Refuel Floor Technician, Westinghouse Nuclear Field Services

(03/2003 ? 08/2003) Performed nuclear reactor system maintenance to include reactor head electrical and instrumentation connections, Control Rod Drive (CRD) latching and drag testing, nuclear fuel core offload/onload fuel movement and equipment refurbishment. One field assignment also included Eddy Current equipment refurbishment at the Westinghouse division in Stockholm Sweden.

Civil Overhaul Projects Supervisor Aps Cholla Steam Power Plant

(01/2003 ? 03/2003) Project Supervisor and Inspector for unit outage overhaul of the air pre-heaters and coal piping boiler nozzles. Performed field supervision of union Boilermakers and Pipe fitters, verified parts and materials available and correct for the projects. Performed final inspections of equipment prior to equipment going back into service. Documented and reported daily work progress to Outage Manager. Projects were completed ahead of schedule and under allotted budget.

Civil Projects Planner for River Protection Project, Hanford River Protection Project, Department Of Energy / Ch2mhill

(10/2001 ? 10-2002) Duties entailed validation of initial work request and determination of scope for deactivation and decommissioning of 244AR waste storage buildings and tanks in the 200E Tank Farm. Identified required drawings, materials, tests, evaluations, and support groups. Interfaced with engineering, environmental, vendors, and production support groups in the preparation of high-quality, accurate work instructions and supporting documentation in compliance with CH2Mhill/DOE regulations.

Computer Programs used: JCS, RMIS, HDCS, ACCESS, PJS, AKHA

Mechanical Maintenance Planner at Columbia Generation Station, Day & Zimmerman

(11/2000 ? 10/2001) Prepared or assisted in preparation of design change packages, as appropriate. Conducted field investigative walk-downs to analyze problem identification for corrective maintenance, preventative maintenance, and surveillance activities on plant equipment; interfaced with Engineering, Alara, Safety and Operations groups and venders as required to support work activities.

Initiated Material Request/Store Orders ensuring pre-staging of parts to support planned work activities, acted as a Temporary Craft Supervisor when assigned. Monitored work order backlogs and package preparation needs based on established priorities and scheduled dates. Ensured work order package preparation met industry and plant standards. Prepared, resolved and disposition Problem Evaluation Requests (PERs), Technical Evaluation Requests (TERs).

Work performance involved teamwork in a strong team-oriented environment committed to working with emphasis on core values and team morale, safety and quality.

Computer program used: PASSPORT/Portal G, Word Perfect, Excel, Word, Curator, People Soft.

Re-Start Maintenance Planner, American Electric Power (AEP) D.C. Cook Nuclear Power Station,

(2/99 ? 10/00) Duties Entailed: Providing technical knowledge and experience in the development of Computerized Mechanical (Corrective, Preventive, and Predictive) Work Order Packages during the Two Unit Plant extended Shutdown and Startup evaluations. Performed field walk downs, analyzing equipment problems, verifying component configuration, and identifying non-conforming issues with provisions for resolution. Researched procedures, manuals, drawings, and documentation to perform assigned tasks. Performed various Special Projects and was challenged to be a Team Member in the resolution of many Emergent issues. Attended two enhanced, Onsite Systems and Planning training classes, adding to the professional attitude of the Station Management ?Committed to Excellence? expectations for the future of D.C. Cook.

Civil Planner, Exelon LaSalle Nuclear Power Station,

(10/98 ? 2/99) Performed field walk downs of system / components to evaluate required repairs, engineering requirements, RWP information, out-of- Service conditions, and associated regulatory requirements

Computer programs utilized: Passport/ Portal G, Electronic Work Control Station (EWCS), Nuclear Station Work Procedures (NSWP).

Planner for Mechanical Maintenance, Southern Nuclear Plant Hatch,

(8/98 ? 10/98) Assigned to the Valve Maintenance Group. Validated work requests and determined scope of work. Prepared work packages for valve repairs during refueling outage.

Computer programs used: PMMS and Lotus Approach

Civil Planner, Construction Maintenance Modification Group, Exelon Dredson Nuclear Power Station

(3/97 ? 6/98) Validated initial work request and determined scope of work to be performed. Identified required drawings, materials, tests, evaluations, and support groups. Interfaced with engineering, vendors, and production groups. Prepared high-quality, accurate work instructions in a timely and cost-effective manner.

Computer programs used: Passport/Portal G, Electronic Work Control Station (EWCS), Nuclear Station Work Procedures (NSWP).

Civil Field Enginee,r Exelon Quad Cities Nuclear Station, Bechtel Engineering

(10/93 ? 3/94) . . . Performed work package and surveillance walk-downs and procedure verification. Inspected scaffolding for seismic and safety-related qualifications. Parts and material expediter for the Mechanical Field Engineering group.

Palo Verde Nuclear Generating Station, Arizona Public Service

Reactor Coolant Pump Technician (9/95 ? 11/95) . . . Removed two Siemans Allis RCP motors from service. Replaced the KSB mechanical pump seals on four pumps. Performed related equipment maintenance.

Steam Generator Support (8/94 ? 12/94) . . . Provided support for steam generators. Performed eddy current inspections, tool head change-outs, probe maintenance and repair.

Reactor Maintenance Technician (2/92 ? 4/92) . . . Destack/restack of the Combustion Engineering System 80 Reactor Head and its associated components. Design modification installation of quick-release vents for the Control Element Drive Mechanisms (CEDM).

Outage Management Task Group Supervisor (4/89 ? 2/90) . . . Coordinated shift and monitored Mechanical Maintenance crew. Lead technician for reactor coolant pump disassembly/reassembly, Control Element Drive Mechanism (CEDM) coil stack modification, reactor destack/restack, reactor refueling equipment maintenance and integrated Leak Rate Testing (ILRT) support. Shift supervisor responsibilities include shift maintenance documentation and turnover, procedure verification, parts/material requisitioning, inter-departmental coordination, system walk-down, post-maintenance testing and work order close out.

Supervisor, Technical Adviser, David Bessi Nuclear Station, Areva

(3/93 ? 4/93) . . . Supervised union craft personnel performing maintenance on the B&W reactor head to include control rod drive mechanism (CRDM) component maintenance and installation. In-core instrumentation installation. Reactor vessel head and component reinstallation. Documentation and interdepartmental coordination for the work performed.

Motor Actuator Technician Laguna Verde Nuclear Generating Station, Veracruz, Mexico

(8/92 ? 9/92) Mechanical refurbishment of SMB 000-SMB 3 motor actuators. Approximately 90% of work was performed while on critical path. ITI Movats.

Machinist, CHIN SHAN NUCLEAR PLANT, General Electric, Republic Of China, Taiwan

(10/88 ? 12/88) . . . Using the Mac-Tech machines 410, 616, and 812, cut out and removed recirculation pipes on General Electric BWR reactor.

Watercraft Engineer, 61B30, United States Army

(1/76 ? 10/84) Assigned to various Army watercraft, certified to level 61B30. Vessel Master of Army LCM (Landing Craft Mechanized). First Mate on LCU (Landing Craft Utility) and ocean going tugboats. Duties entailed maintenance and repair of vessels and equipment. Logistical support of Army training operations. Provided transportation of equipment to various military stations, where overland transportation wasn?t practical. Trained new crew members. Docked and undocked ocean going vessels in the port of Azores, Portugal. Performed open ocean-docking maneuvers with U.S Navy submarines to assist with delivery and removal of submarine crew- members. This task was performed in international waters off the coast the Azores, Portugal.