PERSONAL PROFILE OF MR TIMOTHY BOND

Address **** **** ***** ****

Kissimmee, FL. 34746

Mobile 407-***-****

E-mail aboet5@r.postjobfree.com

Date of birth June 17, 1961

EDUCATIONS AND QUALIFICATION

Higher National Certificate in Mechanical Engineering

City and Guilds Technical

Offshore Survival, Marins De Pompiers Marseille, France

Shell Opris No 29897P

Spectrom Analysis Operational Course given by Sprectro Incorporated

Combi-Laser Alignment Course, on site training.

Solar Operation and Maintenance Course, San Diego, California

Solar Control system Logic Course, San Diego, California

Energy Services International, Bray, Ireland

Framo Engineering as, Sandsli, Norway

Ariel Compressor Training Centre, Mount Vernon, Ohio

Bush Compression Industries, South Maybelle, Tulsa, Texas

Fire Fighting, First Aid, Breathing Apparatus, Safe Site Practices

CAREER HISTORY

April 99 to July 04 representing the below Companies and Projects whilst

being employed by Shanahan Engineering in a Consultancy capacity.

Oct 21 to Present Date. Turbine Technical Services.

Position. Consultant

Engineer.

Duties. To advise on

installation of 2 x Siemens 501 FD3 Turbine

Units

driving 2 x Siemens TEWAC Generators and all

Associated

balance of plant equipment.

Jan 12 to Jan 12 North Eastern

Services.

Position Technical Field

Advisor.

Duties To oversee the

final rebuild of a John Brown frame 5 after

Having a

major overhaul being carried out.

July 11 to Oct 11 North American Energy

Services.

Position. Technical

Director..

Duties To oversee a GE

7FA Rotor removal, bearing and

All major

component inspection.

Carry out

necessary repairs, realign unit, rebuild and

Starting of

unit to ensure correct operating parameters

Are met.

Feb 11 to March 11 Turbine Technical

Services

Angola,

Africa

Position. Mechanical

Consultant.

Duties Commissioning

and startup of 2 x Westinghouse 251

Barge

mounted units and all associated equipment.

Jan 08 to Nov 10 Proenergy services

Sedalia, Mo

Position. Technical

Advisor

Duties Various

projects world wide working on various sized

Units by

different manufacturers.

Works

covered included major outages, Installation

Commissioning, start up and trouble shooting.

Dec 06 - Oct 07 Mitsubishi Heavy

Industries.

Minnesota,

USA

Position. Technical

Advisor.

Duties. Installation

and commissioning of 2X MHI 501G Gas

Turbines

and Melco Generator sets.

Installation and pre commissioning of all associated

Equipment.

Carry out

various modifications and enhancements to

Starter,

Air inlet and exhaust systems.

Dec 05 - Sept 06 Mitsubishi Heavy

Industries.

Oregon,

USA.

Position. Senior Technical

Advisor.

Duties. Installation,

commissioning and start up of MHI 501 G

Gas turbine

and Melco hydrogen cooled 300 MW

Generator,

Seal oil system, Control oil system, Lube oil

System and

all associated plant.

May 05 - Oct 05 Vernon Power and Light

California,

USA.

Position Mechanical

Engineer

Duties Commissioning

and start up of 2x Alstom GTX 1000

Gas

turbines in a combined cycle status with 1 GE

Steam

turbine plus 3x Gas fuel reciprocating

Compressors

and all associated balance of plant and

Establishing complete preventative maintenance plan

For plant

continuous operation.

March 04 - July 04 ABB/BHP joint venture

Ohanet

project, Algeria

Position Technical

Consultant

Duties To oversee

commissioning and start up of 3x Nuovo

Pignone

Gas Turbine compressor drive units.

Aug 03 - Sept 03 Tenaska Corporation

Brownsville, Tn.

Position Technical Advisor

Duties Feasability / Quotation study for relocation of complete

Power Plant consisting of 3X Mitsubishi 501 Gas

Turbines and all associated equipment.

March 03 (periodic) Mitsubishi Heavy Industries

Boston, Ma.

Position Senior Mechanical Engineer

Duties Installation, Commissioning and Startup of 2X M501G

Siemens Gas Turbines and 1X Mitsubishi 230 MW

Steam

turbine.

May 02 - Jan 03 UMCI Constructers Inc.

Seattle, Wa.

Position Consultant Mechanical Engineer

Duties Installation of 2X General Electric 7FA Turbine /

Generator sets and all associated equipment

Sept 01 - March 02 Duke Fluor Daniel

Philadelphia, Pa.

Position Toshiba Liaison / Consultant

Duties Commissioning and Startup of 1X 320 MW Steam

Turbine and all associated equipment.

March 01- Aug 01 Siemens Westinghouse

Pittsburg, Ca.

Position Site Mechanical Construction / Commissioning Engineer

Duties Construction, Commissioning and Startup of 3X 501FD

Siemens Westinghouse Combustion Turbines driving 3X Aero pack

Generators, plan preventative maintenance procedures and carry

out ongoing production modifications.

July 00 - Feb 01 Siemens Westinghouse

Joplin, Mo.

Position Site Mechanical Construction / Commissioning Engineer

Duties Construction, Commissioning and Startup of 2X 501FD

Siemens Westinghouse Combustion Turbines driving 2X

Aero pack Retrofit 501F upgrade and all associated

Modifications.

Jan 00 - June 00 Siemens Westinghouse

Gleason, Tn.

Position Site Mechanical Construction / Commissioning Lead

Engineer (Technical Field Assistance)

Duties Construction, Commissioning and Startup of 3X Siemens

Westinghouse 501F units driving 2X Aero pack Generators

and 1X Hydrogen Cooled Generator Unit.

April 99 - Nov 99 Siemens Westinghouse

Tihama, Saudi Arabia

Position Site Mechanical Commissioning Engineer

Duties Installation, Commissioning and Startup of 2X 501D5

Turbine / Generator Units and all associated plant plus

Construction and commissioning of 2X Distillate Fuel Storage

Tanks with a total capacity of 22974 cubic meters.

Oct 98 - April 99 Energy Services International

Mobol Equatorial Guinea

Position Rotating Equipment Specialist

Duties Involved in Installation, Commissioning, and Startup of all

Mechanical systems required on a floating production and

Storage operation including X3 Solar Taurus 60 Turbine

Generators, Solar Taurus 60 Turbine driving a BW/IP Water

Injection Pump (3500gpm), Solar Mars 100 Turbine driving

3 stage Centrifugal Compressor, Ariel JGK/2 Reciprocating

Fuel Gas Compressor, Fisher 2 stage Lift Pumps (9250 gpm)

Goulds Charge Pumps and Airdyne Service Air Compressors

Sept 98 - Oct 98 Westmont Offshore

Labuan, Malaysia

Position Mechanical Engineer

Duties To inspect X1 501D and X2 CD251B11+12 Westinghouse

Barge mounted Turbine Generator Sets, survey units to inform

Owner of the percentage of mechanical completion of all

Systems and detailing required works to bring units to Com-

missioning / Startup status; and advise on ongoing maintenance

procedures.

Aug 98 - Sept 98 Nuovo Pignone

Florence, Italy

Position Mechanical Supervisor

Duties Overseeing strip down and hot gas path inspection of frame

6 General Electric Turbines. Installation of redesigned

transition pieces and combustor cans to enable the unit to

run on liquid as well as gas fuels.

March 98 - July 98 Kvaerner Process, Western Route Pipeline

Azerbaijan, Former Soviet Union

Position Mechanical Superintendent

Duties Overseeing installation and commissioning of Sulzer

Mainline and Booster Pumps, Skids, Generators, Tanks, Associated

Equipment and construction / installation of 20"

pipeline to accommodate / finance 42" Mainline System.

Oct 97 - Dec 97 Westinghouse Electric Corporation

Barranca Bermesa, Columbia

Position Commissioning / Startup Mechanical Engineer

Duties Installation, Pre-Commissioning, Commissioning and Startup

of one Westinghouse 501F Turbine and Westinghouse D5

165MW Generator Set. Balance of Plant etc on a turnkey

project management status.

Feb 93 - Jan 97 Elf Petroleum / Bouygues Off Shore

OML 100, Nigeria

Position Turbine Superintendent

Duties Involved in complete commissioning period from install-

ation to startup programming logic, adhearing to Solar

specification and preparation of complete maintenance

procedure for 2 Solar Centaur H, 3.5 MW Dual

Fuel

Turbines.

Also responsible for Commissioning Startup

and routine

Maintenance of 2 Aerial Gas Lift Compressors, Model JGE /

4. 1500 HP.

Plus being in charge of maintenance of all Mechanical

Systems

and Ancillary Equipment of 5 Offshore Oil

Production platforms.

March 92 - Feb 93 Enron Power Plant

Teesside,

England

Position Mechanical Supervisor

Duties Preparation of Site, Installation and Commissioning of 8

Mitsubishi 701D, 160MW Gas Turbines plus 2, Westinghouse,

350MW Steam turbines.

Responsible for alignment of 360 tonne Generator to Turbine,

Generator to Starter Pack, Package to

Boiler and all Ancillary Equipment.

June 91 - Oct 91 General Electric

Dammam, Saudi Arabia

Position Technical Advisor

Duties To supply a complete package to the customer regarding

Any works undertaken, mobilization of crews, full technical

Backup facilities for projects undertaken on any model

Turbine.

Oct 88- May 91 Dresser Rand

Wythenshawe

Position Service Engineer

Duties Strip down removal, overhaul in workshop, rebuild, startup

And commissioning of various makes and output of both

Centrifugal and Reciprocating Compressors. Work scope

consisted of modification of pipe work, construction of Grout

Beds, Wire, Optical and Reverse Alignment, also work under-

taken on Gearboxes and drive units including P.K.V.G. Gas

Engines, Electric Motor Units and both Gas and Steam

Turbines.

Countries worked in Spain, Libya, Belgium, France, Kuwait, and

Bahrain.

1983 - 1988 (periodic) Woodgroup Offshore

Aberdeen, Scotland

Position Mechanical Technician

Duties Various tasks including Construction, Maintenance, and

Overhaul Projects consisting of Water Injection, Gas

Compression, and Power Generation Systems. Also planning

Preventative maintenance routines. Involved in being part of a

2 man team, sub contracted to Shell via Woodgroup, surveying

most Shell North Sea Platform Lifeboats, including engine and

winch overhauls, contents and general boat seaworthiness.

1985 - 1986 I.T.M. Engineering

Cleveland, England

Position Mechanical Technician

Duties Maintenance of all Mechanical, Hydraulic, Pneumatic and

Instrument Systems, including Drilling and Draw-Works and

Caterpillar Power Plants on land based drilling rig.

1984 - 1985 British Steel, 44" Mill

Hartlepool

Position Mechanical Fitter

Duties Maintenance and overhaul of Hydraulic and Pneumatic pumps,

Rams, and Valves. O. D. and I.D. Welders. Overhead Cranes

and High Pressure Hydro - Testing.

1981 - 1983 Bendix Field Eng-Corporation

Saudi Arabia

Position Mechanical Technician

Duties Overhaul of Radar Power Systems for the Presidency of Civil

Aviation.

1977 - 1981 British Rail

Cleveland, England

Position Apprentice Mechanical Fitter

Duties Full Apprenticeship, 4 year Block Release



Contact this candidate