SUMMARY/INTRODUCTION
A skilled Cost Estimator & Coordinator, with proven Project Management /
Procurement capabilities, seeking to Plan, Direct, and Coordinate projects,
with the goal of extending my career achievements, managing construction
projects, building strong client relationships, leading effective
communications and coordination efforts to provide solid support with a
growth oriented company
CORE STRENGTHS
* Assemble Contract/Construction Documents * Value
Engineering, Project Evaluation & Development
* Organize & Implement Procurement Plan * Assemble Project
& Development Proposals, HUD
* Proficient with Microsoft Project, Word, Excel * Operate
Timberline, BIM, Agtek, AutoCAD 2010
* Plan / Conduct Pre-Bid & Pre-Construction Services * Public
Speaking, Community Service, Coordinator
PROFESSIOAL EXPERIENCE
June 2007 - June 2009 HDR Design Build, Inc. - Project Engineer /
Cost Estimator, Construction Administration
. $26M - Biosolids Processing Facility - West Palm
Beach, Florida
. Coordinate Equipment Procurement with Design Build
Project, prepared contract documents
. Estimate, Water/Wastewater Treatment Plants,
Hospitals, Metal Bldgs. from $3M to $100M.
October 2004 - June 2007 Omaha Housing Authority - Project
Facilitator, Contract Administrative duties, Coordinator
. $4,500,000 - Facilitated Capital Improvement and
Development Projects Constructing Homes
. $1,154,815 - Coordinated Site Improvements
. $800,000 - Facilitated coordination, field engineered
the scope of work for Cherry Apartments
. Preparation of Development Proposal to obtain HUD
funding for Chambers Court Renovation, Long School
and North Omaha Development Projects.
March 2003 - Present CMC,LLC - Construction Management Contractors
- Owner / Manager
. Consulting, Project Management & Estimating Services
. $25,250 - Bob Kerrey Pedestrian Bridge parking lot
improvements, / City of Omaha Parks
. $36,163 - SID 286 Project - 180th & Q Street,
Constructed sidewalk, culvert pipe, and inlets
. $22,750 - Benson & Gallagher Park, constructed Ball-
field dugouts, City of Omaha Parks
September 2000 to Mar. 2004 Rupert Construction Co. - Project Manager /
Cost Estimator, Heavy highway
. $74,245 - Omaha Field Club Trail, Prepared cost
estimates, Project Manager
. $30,250 - Heartland Park - Concrete Sidewalk
February 2000 to Aug. 2000 Kiewit Western Co. - Engineer / Estimator,
. $1,700,000 - Union Pacific Auto Unloading Facility,
Council Bluffs, IA
. $2,200,000 - I-229 Heavy highway, South Falls, South
Dakota
Project Engineer / Coordinator, assist with preparing
cost estimates, construction administration
and project coordination.
EDUCATION University Nebraska-Omaha
Masters of Engineering in Construction Graduate Student
Bachelors of Science in Engineering Technology (May,
1999)
Associates of Science in Engineering Technology
(December, 1997)
SKILLS AND ACCOMPLISHMENTS
*AACE - Certificate of Achievement for Estimating/Bidding
*DBIA - Certificate of Completion for Conceptual
Estimating
*Bangert - Certificate of Achievement for Timberline
CERTIFICATION
*Nuclear gauge training, soil properties instrument
Thomas L. Smith II - List of Project Estimates
City of Coeur d' Alene, WWTP Low Phosphorus Demonstration Pilot Facility,
Coeur d' Alene, ID.
Evaluated the installation cost of three separate types of Low Phosphorus
treatment. Treatment includes membrane bioreators (MBRs), tertiary
membrane filtration (TMF) and continuous up flow media filtration (CUMF).
All three systems were to be capable of maximum monthly flow of 50,000 gpd
with remova efficiency of up to 200,000 gpd. Estimate of probable cost was
$3,803,000.
Coucil Bluffs Water Works South Water Plant, Council Bluffs, IA.
Developed an opinion of probable construction cost estimate for the 30% and
60% design levels. The facility was a submerged membrane design with an
initial capacity of 10 MGD expandable to 20 MGD with significant structural
modifications. Process include filter tubs for 20 MGD of submerged
membranes, chemical feed facilities for 20 MGD and High service pumping
capacity of 10 MGD expandable to 20 MGD with the addition of pumps only.
60% design level opinion of probable construction cost was $36,578,000.
Pinellas County Utilities, Pinellas County, FL - Onsite Sodium Hypochlorite
generation projects.
Provided cost estimating services for 4 separate hypochlorite generation
projects at various pump station and waste water treatment plants: a) South
Cross Bayou, b) William F. Dunn WRF, c) Water Transmission Logan Pump
Station & North Booster Pumps Station, d) Oakhurst Pump Station, and Capri
Pump Station, Gulf Beach Pump Station. Opinion of probable cost for all
segments was $4,310,000.
Orlando Utilities Commision - 14 miles of 24" reclaimed water transmission
main, Orlando and the City of Apopka, FL.
Developed 4 opinions of probable construction cost for client in selecting
a potential routing of a 24" reclaimed water transmission main from an
existing Orlando water treatment plant to a new City of Apopka water
treatment plant. Opinion of probable cost for the base estimate was
$100,316,000.
Anacortes Wastewater Treatment Plant - Odor Control Duct Modification FRP
- $759,702
Charlotte, NC - Cary / Apex WTP - Earthwork, Equalization Basin -
$1,416,394
Arizona - CAP, Salt Gila Pumping Plant- Potable Water Connection Plant,
Sitework, Mechanical - $366,920
Arizona - CAP, San Xavier Pumping Plant - Potable Water Connection Plant,
Sitework, Mechanical - $247,488
Nevada - Coyote Springs Development - WWTP Effluent Storage ponds & RWPS
Wet Well - $4,768,216
Atlanta, GA - Johnson Creek Pump Station - Concrete Lift Station, Earthwork
- $1,240,791
Norman, OK - Norman Lift Station D Rehabilitation - Equalization Basin,
Sitework - $1,519,412
Waco, TX - WMARSS Central WWTP Expansion - Concrete Peak Storage Flow -
$522,929
South Dakota - Lewis & Clark WTP - Cast In-Place Concrete Structure,
Concrete Block Walls, Structural Steel, Earthwork - $29,225,452
Alamogordo, New Mexico - WWTP - Earthwork, Structural Concrete, Yard Piping
- $10,855,495
Port of Sunnyside, Washington - WWTP - Earthwork, Structural Concrete, Pre-
Engineered Metal Building - $992,793
Yadkin Valley Water Supply, Caldwell County, NC - Well Development Project
- Earthwork, Mechanical Piping, Concrete Paving, Pre-Engineered Metal
Building, Electrical - $5,623,443
Anacortes WTP Improvements Project - Earthwork, Structural Concrete,
Mechanical Piping, $49,598,675