MUSTAFA AL-SAEDI

abljo4@r.postjobfree.com

*** ********* **. *******-** 32809

Cell: 407-***-****

SUMMARY

Commissioning and maintenance engineer 8 years of experience in designed, modification,

installation, maintenance & commissioning. Proficient in Microsoft Word/Excel/Outlook, Windows

3.1 through Windows XP

Professional Experience COMMUNICTION 2008

Company: ASLLC sub contract WINTARA .

Project: Remote Monitor System (RMS) connecting the GAS TURBINE STATION in

one monitoring place at Baghdad south

Type of work:

• Install all the site equipment (2 servers,transmitter,receiver and antenna

• Install and connect with the controller and download all the file on the HMIs

• Training the MOE on using and maintain this system

Generation 2007-2008

Company: GRD/IPA .

Project: Commissioning and Operate mussibe gas turbine for 10UNITS type LM6000 GE

manufacture with RO unit and refinery

Type of work:

• Calibrate and test all transmitter,pressure switches,level switches, temperature

switches and all gauge

• Install all the software for MK 6 controller,GEFANUC and HMI s

• Install fiber optic cable for communication between the units

Operating and maintenance 2006-2007

Company: WGI, Inc . Project: Rehabilitation of instrument in taza gas turbine station

unit one(64)unit tow

(94) manufacture by SIEMENS

Type of work:

• Calibrate and test transmitter SITRANS P and SITRANS T manufacture by

SIEMENS

• Calibrate and test pressure gauge and temperature gauge

• Training for instrument department at taza gas turbine station (OJT) on job training

• Design the matching drawings between the old GIS 400kv and new protection and

control system (ABB)

• Design the matching drawings between the old disconnect switch and new protection

and control system (ABB)

Testing and commissioning 2006

Company: WGI, Inc .

Project: Commissioning agrguf 132kv /33kv substation, 7 bays 132kv manufacture

(ALSTOM & SIEMENS) type AIS, the protection and control system manufacture

(SIEMENS) and 20 bays 33kv manufacture (ALSTOM)

Type of work:

• Testin g circuit breakers for all bays, the tests are CB timing analyzer, contact

resistance, PF test and function test

• Testin g disconnect switches for all bays, the tests are, contact resistance and

function test

• Testin g and calibrate the protection relays siemens

• Commissioning and test all 33kv circuit breaker

• Commissioning and operating all bays and lines

Testing and commissioning 2006

Company: WGI, Inc Project: Rehabilitation center C.B of diameter 3 in west

Baghdad substation 400 KV, 2000A

Type of work:

• Design the matching drawings between the new CB (ABB) and old protection and

control system (ASEA)

• Testin g all parts of line (Circuit breaker, CTs).

• Testing and commissioning circuit breaker 400KV, 2000A (ABB)

• Commissioning and operating t he center C.B

Testing and commissioning 2006

Company: WGI, Inc .

Project: A L KALIS 400/132 kV GIS manufacture by ASEA, 4 diameter 10 bays

Type of work:

Commissioning and operating t he bays

Testing and commissioning 2006

Company: WGI, Inc Project: Rehabilitation of diameter 3 in west

Baghdad substation 400 KV, 2000A

Type of work:

• Design the matching drawings between the new CB (Siemens 3AP2-F1) and new

p rotection and control system (SIEMENS)

• Design the matching drawings between the old disconnect switch and new

p rotection and control system (SIEMENS)

• Testin g all parts of line (Circuit breaker, CTs, PTs, Surge arrestor, Disconnect

switch, earthing switch).

• Testing and commissioning circuit breaker 400KV, 2000A (Siemens 3AP1F6)

• Commissioning and operating t he lines

• Calibrate the protection relay (SIEMENS)

Testing and commissioning 2006

Company: TDS, Inc .

Project: Construct indoor and space-saving gas-insulated switchgears (132 KV GIS)

manufacturing by VATECH type TH7m which consist of ten bays three transformer

bays, six line bays, two bus bar and bus coupler bay

Type of work:

• Testin g circuit breakers for all bays (VATECH D TH7m), the tests are CB timing

analyzer, contact resistance, dielectric and function test

• Testin g disconnect switches for all bays (VATECH SI TH7m), the tests are

t iming, contact resistance, dielectric and function test

• Testin g earthing switches for all bays (VATEH STL TH7m), the tests are timing,

Testing and commissioning function test 2006

contact resistance, dielectric and

• Testing GI, Inc . Project: Rehabilitation of ratio,ABU GRAB2, ABU GRAB3 in

CTs and PTs, the tests are turn Bay polarity, insulation and excitation

Company: W

West Baghdadfor CT

saturation substation 132 KV, 2000A

• Commissioning and operating t he line

Type of work:

• Design the matching drawings between the new CB (Siemens

3AP1F6) and new protection and control system (SIEMENS)

• Testin g all parts of line (Circuit breaker, CTs, PTs, Surge

arrestor, Disconnect switch, earthing switch).

• Testing and commissioning circuit breaker 132KV, 2000A (Siemens 3AP1F6)

• Testing of all Power & control cables.

• Testin g all parts of line (Circuit breaker, CTs, PTs, Surge

arrestor, Disconnect switch, earthing switch).

• Testing and commissioning circuit breaker 132KV, 2000A (Siemens 3AP1F6)

• Testing of all Power & control cables.

Commissioning and operating t he line

Testing and commissioning 2006

Company: TDS, Inc . Project: Rehabilitation of diameter 1 in East

Baghdad substation 400 KV, 2000A

Type of work:

• Design the matching drawings between the new CB (Siemens 3AP2-F1) and old

p rotection and control system (ASEA)

• Design the matching drawings between the new disconnect switch (HAPAM motor

d rive type EAF) and old protection and control system (ASEA)

• Testin g all parts of line (Circuit breaker CTs, PTs, Surge arrestor, Disconnect

switch, earthing switch).

• Testing and commissioning circuit breaker 400KV, 2000A (Siemens 3AP1F6)

• Commissioning and operating t he ten bays

Testing and commissioning 2006

Company: TDS, Inc . Project: Rehabilitation of Bay Farabi 2 in East

Baghdad substation ML8 132 KV, 2000A

Type of work:

• Design the matching drawings between the new CB (Siemens 3AP1F6) and

old protection and control system (ASEA)

1999-2000

Ministry of higher education Baghdad, Iraq

Design and development of control system and machine control by computer

Instilling of control system and wiring and control machine by computer

Reverse engineering

Reconstruction, Instillation& commissioning 75kva UPS unit 1 at AL-Mussaib Thermal

Power Station

EDUCATION 1996-2000

B.SC University of Baghdad College of engineering electrical department

engineering

Al-khazin Center 2000- 2005

Commissioning 2003- 2005 Design and development many electronic card as DC

drive, UPS, AVR and CHRGER

Baji gas station Baji, Iraq 2004- 2005

Maintenance of UPS in Baji Electric Power station

Maintenance of (6.6KV, 11KV, 33KV switchgear C.B)

Najif gas Power Station Najif, Iraq 1/2004 – 7/2004

Maintenance of CHARGER in AL-Najif Electric power station

Mussaib electric power Station Mussaib, Iraq 2000 –2003

Maintenance of AVR in AL-Mussaib Electric power station for all units

Maintenance of UPS in AL-Mussaib Electric power station for all unit

Al- Numania camp kut, Iraq

Establish of six (1.75MW Generator) as small station in kut