RESUME - LYNN MERTZ

Lynn Patrick Mertz

N* W*7372 Lyles Drive

Waukesha, Wisconsin 53188

Phone Number: 262 - 853- 5140 (Home)

262-***-**** (Cell)

E-mail: *******@***.***

Birth Date: April 7, 1947

Married - Spouses name is Barb

I am free to travel wherever the project might be.

Safety Qualified - OSHA 30 Hour

DOD & NRC Clearance - currently inactive.

SUMMARY

I have over 40 years experience in project management, construction

management, contract management, analysis, and reconciliation on design &

construction projects, union and non-union, related to civil, structural,

mechanical and electrical..

.

I have worked with Owners, Contractors, Architects and Engineers on

commercial, and industrial projects in various cities around the United

States. I have extensive experience in construction management, project

management, contract bid preparation, bid analysis, change order

preparation and reconciliation, contract negotiations, contract writing,

contract reconciliation, draw requests, expediting, safety oversight and

compliance, contract management, project scheduling and customer relations.

I am computer literate in IBM and Mac. I have extensive experience with all

Microsoft Software including Word, Excel, Project, as well as Primavera P3

Scheduling, and Expedition Project software, as well as graphics, desktop

publishing, and AutoCAD 12 experience.

Education: Associate of Applied Science Degree in Civil Engineering

Professional and Personal References are provided on last page.

PROFESSIONAL EXPERIENCE

July 2009 to Jan. 2010

TDS Inc. (Technical Diagnostics Inc.), Fort Worth, Texas

Worked as Project Manager in the Commissioning and Acceptance Dept. at the

National Enrichment Facility of LES, Louisiana Energy Services in Hobbs,

NM. Start-up and Commissioning Mechanical Systems and Buildings. Develop

and maintain schedules for testing, Develop testing procedures,

documentation of operatinal control, P&ID's, as-built drawings, CR's,

DCR's, ECN's, and Turn-Over documentation. Project involved NRC procedures

and documentation.

(March 2005 to April 2009)

Black & Veatch Corporation

Ann Arbor, Michigan / Kansas City, Kansas

Worked as Site Engineer and construction management for the construction of

coal fired power plants, including all aspects of the plant. Supervised the

subcontracts for civil/structural/mechanical, boiler, turbine and

generators, substations, and all balance of plant equipment.

(June 2002 to 2004) Site Engineer and Contract Compliance Engineer,

Consulting work on a variety of projects, Contract

PEC, LLC., Milwaukee, Wi.

Consulting work - having to do with Construction Management, Contract

Management, bid analysis, change order preparation and reconciliation,

contract negotiations, contract writing and field verification of contract

compliance.

Wisconsin Energy work at the Oak Creek Power Plant. Field supervision of

Contractors installing new underground services, foundations for new high

lines, erection of new towers, inspections, safety, scheduling, field

change tracking, as-builds, and project close-out.

(2001 to March 2002) Site Project Controls Engineer

MWH Energy and Infrastructure, Milwaukee, Wisconsin

Worked as Site Construction / Controls Engineer on a Joint Venture Project

for Mirant Corporation in Terre Haute, Ind. Responsibilities were as MWH

site representative for Civil, Structural, and Mechanical, and Electrical,

working with the Joint Venture, subcontractors, and Owner to answer

questions related to construction contracts, contract preparation and

award, contract compliance and analysis, design, design change requests,

field change controls, RFI's, documentation of field as-built conditions,

and contract close-out.

(1996 - 2001) Lead Construction Engineer

Siemens / Siemens Westinghouse Power Corporation

As Lead Construction Engineer, responsible for the project planning,

construction management, and contract management for Siemens Turnkey power

plant projects. Responsibilities include advance planning of power plants,

layout, coordination of engineering activities, bid scope and package

preparation, bid strategy, contract strategy, writing contracts, contract

compliance and analysis, change order preparation and reconciliation,

schedule analysis, owner negotiations, estimates, construction management,

and contract close-out and documentation

(1994 - 1996) Project Manager

ASC Services Company, L.L.C.

Project Manager for the design and construction of projects for Ameritech,

including design, engineering, and construction management of facility

renovations, space planning, modifications, and new construction in

Wisconsin.

(1992 - 1994) Construction / Contract Manager

Aldrich Chemical Company, Sheboygan Falls, Wisconsin

Construction Manager / Contract Manager for the design, engineering,

estimating, and construction phases of a 2 story, 12,000 sq ft, $6 million

dollar, cGMP chemical manufacturing facility, involving liaison efforts

with the architects / engineers and the owners chemists and engineering

personnel. Contract Manager for the construction, start-up, and validation

of the facility, involving the preparation of bid packages, evaluation of

bids, writing and awarding of contracts, construction verification,

contract compliance, contract change order tracking and reconciliation, and

contract close-out

(1991 - 1992) Project Manager / Contract Manager

The Enertech Group, Inc.

Project Manager for design/build medical facilities both site built and

modular. Responsible for project management of projects from initial

proposal through engineering and construction. Included bid evaluation,

general contractor selection, contracts and negotiations, change order

control and verification, draw request verification, site investigation of

work performance, contract close-out and documentation.

(1987 - 1991) Construction Manager

General Electric Medical Systems, Waukesha, Wisconsin

As Construction Manager, duties included on-site representative for General

Electric Company, Medical Systems Group, responsible for the construction

management of medical facilities on a turnkey basis for GE Medfacs (Medical

Facilities Construction Services)

(1985 - 1987) Construction Manager

PDC Inc. Milwaukee, Wisconsin

Construction Manager of medical diagnostic facilities related primarily to

Magnetic Resonance Imaging (MRI), as manufacture By G.E., Siemens, Picker,

Technicare, etc., and the installation of Radio Frequency Shielding (RF).

Project durations were 4 to 9 months and involved the bidding, scheduling,

contract compliance, project controls, coordination and supervision of

construction, change order control, invoice and draw requests, and close-

out. This required 100% travel and close interaction with owners,

architects, engineers, contractors, city, county, and state agencies.

(1984 - 1985) Design Engineer

Aldrich Chemical Company, Inc, Milwaukee, Wisconsin

As Design Engineer, duties included design and layout of laboratories,

process piping, hydraulics, balance of plant equipment, heating,

ventilation and air-conditioning systems, fume scrubbers, and plumbing.

Also supervised and coordinated the construction and renovation of the labs

with plant maintenance personnel and subcontractors.

(1980 - 1984) Engineer

Kilngas R&D, Inc., Milwaukee, Wisconsin

Allis-Chalmers Corp.

Engineer in the design, construction & operation group of the coal

gasification systems operation department. Became vice-president of Kilngas

R&D, Inc., a wholly owned subsidiary of Allis-Chalmers in the spring of

1981.

(1977 - 1980) Construction Superintendent

Trebor Development Corporation, Milwaukee, Wisconsin

As Construction Superintendent, responsible for the supervision of

construction activities by the subcontractors. This involved the

scheduling, budget, coordination, safety, expediting of materials and

equipment, and daily reporting on the jobsite. Included liaison function

with the owner as well as local building departments and agencies having

permit and code compliance authority.

(1975 - 1977) Project Engineer

Grunau Company, Milwaukee, Wisconsin

As Project Engineer/Coordinator, work included planning, layout, design and

scheduling of projects, tracking progress, and coordination of engineering

efforts both in the office and in the field.

(1973 - 1975) Planner

Lorne Company, Division of Limbach Co., Pontiac, Michigan

As planner, designer, and detailer, work involved the establishing of

project engineering and design schedules, detail design and layout of

mechanical systems, and coordination of field trades in the installation of

those systems.

(1972 - 1973) Purchasing Agent

Townsend and Bottum Inc., Ann Arbor, Michigan / Lorain, Ohio

Conducted jobsite purchasing and procurement of all equipment and materials

used by the trade crafts for the West Lorain, Ohio. - Ohio Edison Power

Plant Project.

(1967 - 1972) Project Engineer

Babcock and Wilcox Co., Inc., Barberton, Ohio

Project Engineer on a number of civil, structural, and mechanical projects.

Made numerous trips to all of B&W's fabrication facilities throughout the

United States for the purpose of planning and supervising the construction

and installation of various buildings, equipment, and renovations.

(1966) Construction Inspector

State of Ohio Department of Highways, Ashland, Ohio

Project Experience (Only some of the larger projects are listed)

National Enrichment Facility of LES, Louisians Energy Services in Hobbs,

NM. Start-up and Commissioning Mechanical Systems and Buildings. Develop

and maintain schedules for testing, Develop testing procedures,

documentation of operatinal control, P&ID's, as-built drawings, CR's,

DCR's, ECN's, and Turn-Over documentation. Project involves NRC procedures

and documentation.

Dalman 4 200 MW Coal Fired Power Plant, City of Springfield, Ill. On site

representative for Black & Veatch responsible for Civil, Structural, and

Mechanical aspects of the plant. All power island equipment as well as all

balance of plant equipment.

Campbell Power Plant, Consumer Energy, West Olive, Michigan.

Unit 3 Renovation of the 500 MW Boiler. On site representative for Black &

Veatch responsible for the Structural Steel installation, platform

redesign, as-built sketches, close-out documentation.

Sugar Creek Power Plant, West Terre Haute, Indiana

Client: Mirant Power Corp.

Site Project Controls Engineer on Phase One of a 1000 MW power plant,

consisting of 4 GE frame 7 gas turbines / generator sets, 4 HRGS's, 2 GE

Steam Turbine / Generator sets, three switchyards, Administration Bldg, 2 -

8 cell FRP Cooling Towers, and all balance of plant facilities.

Great River Energy - Pleasant Valley Station, Dexter, Minnesota

Client: Great River Energy

Lead Construction Engineer for the construction of a simple cycle gas

turbine power plant with two gas turbines, two generators, and balance of

plant support facilities (2000 to 2001).

St. Francis power Plant Unit 1 and 2, Glennonville, Missouri

Client: AECI Power Company

Lead Construction Engineer / Construction - Contract Manager

Combined cycle single shaft power plant consisting of two Gas turbines, two

generators, two heat recovery steam Generators, 2 - 8 cell FRP Cooling

Towers, and two steam turbines. This was a green-field site and all of the

site facilities for the balance of plant and Support facilities were also

part of the project. Total power plant capacity was 1100 megawatts. The

plant was completed in early 2001 (1997 to 1999)

Mcintosh Power Plant, Mcintosh, Alabama

Client: AEC Power Corporation

Simple cycle gas turbine power plant with two gas turbines, two Generators,

and balance of plant support facilities. (1996 to 1997). AEC Power

Corporation

National Institutes of Health, Washington, D.C.

Client: National Institutes of Health, Washington, D.C.

Worked on the 12,000 sq ft facility for 4 MRI (magnetic resonance imaging)

systems. As Project Construction Manager, duties included on-site

representative of General Electric Company, Medical Systems Group,

responsible for the construction management of medical facilities (1986 to

1990).

Washington Hospital Center, Washington, D.C.

Client: Washington Hospital Center, Washington, D.C.

Worked on a 4000 sq ft MRI facility. As Project Construction Manager,

duties included on-site representative of General Electric Company, Medical

Systems Group, responsible for the construction management of medical

facilities. (1986 to 1990).

Walter Reed Army Hospital, Washington, D.C.

Client: Walter Reed Army Hospital, Washington, D.C.

Worked on two cardio-cathorization and special procedure labs. As Project

Construction Manager, duties included on-site representative of General

Electric Company, Medical Systems Group, responsible for the construction

management of medical facilities. (1986 to 1990).

University Hospital of Medicine and Dentistry, Newark, New Jersey

Client: State University of New Jersey, Newark, New Jersey

Worked on the 3500 sq ft MRI and CT (computer tomography) facility. As

Project Construction Manager, duties included on-site representative of

General Electric Company, Medical Systems Group, responsible for the

construction management of medical facilities. (1986 to 1990).

4000 sq ft Multi-Modality Out-Patient Facility

Client: South Shore Imaging Associates, Rockville Center, N.Y.

Determined the design and layout of the facility, and supervised the

construction of the facility, which included MRI, CT, radiography and

fluoroscopy, ultrasound, and mammography (1986 to 1990).

Health Science Center at Brooklyn, Brooklyn, New York

Client: State University of New York

As Project Construction Manager, duties included on-site representative of

General Electric Company, Medical Systems Group, responsible for the turn-

key construction management of medical facilities, which consisted of a

5000 sq Ft MRI addition (1986 to 1990).

Coal Gasification Plant, East Alton, Illinois

Client: Allis-Chalmers Corp.

Work involved the planning, estimating, and scheduling of the coal

gasification plant to be built in East Alton, Ill. Interacted with process

engineers to learn the process, equipment, and develop a schedule by which

to plan the fast track engineering and construction. There were numerous

trips to the architects and engineers for the project. Became Vice

President of "KilnGas R & D Inc. - a wholly owned Subsidiary of Allis

Chamers Corp. in the spring of 1981. Primary on-site responsibilities

included establishing the jobsite office, procedures, policies, and

managerial systems and project controls required for the construction of

the plant.

Trebor Development, Brookfield, Wisconsin (1977 to 1980)

Several Car Dealerships in the greater Milwaukee area: Boucher Lincoln

Mercury, Tolkan Pontiac, McBain Lincoln Mercury, Heiser Ford.

All Star Lanes Bowling Alley, Accents Unlimited, several strip malls

including branch banks.

Retail construction and renovations.

Blue Cross of Wisconsin, Milwaukee, Wisconsin

Client: Blue Cross of Wisconsin

Work included detailed layout of mechanical systems including heating,

ventilation, air conditioning, plumbing and fire sprinkler (1976 to 1977).

Miller Brewing Executive Office Building, Milwaukee, Wisconsin

Client: Miller Brewing Co.

Work included detailed layout of mechanical systems including heating,

ventilation, air conditioning, plumbing and fire sprinkler (1976 to 1977).

Hyatt Regency Hotel, Dearborn, Michigan

Client: Dell Webb Corporation

Work included project engineering and design schedules, detail design and

layout of mechanical systems, and coordination of field trades in the

installation of heating, ventilation, air conditioning, plumbing, and fire

sprinkler (1975 to 1976).

American Motors Town Center, (Retail Shopping Center) Southfield, Michigan

Client: American Motors Corporation

Work included project engineering and design schedules, detail design and

layout of mechanical systems, and coordination of field trades in the

installation of heating, ventilation, air conditioning, plumbing, and fire

sprinkler. Also involved with the supervision of retail store construction.

(1975 to 1976).

Pontiac Metropolitan Football Stadium, Pontiac, Michigan

Client: Detroit Stadium Authority

Work included project engineering and design schedules, detail design and

layout of mechanical systems, and coordination of field trades in the

installation of heating, ventilation, air conditioning, plumbing, and fire

sprinkler (1975 to 1976).

Detroit Renaissance Center, Detroit, Michigan

Client: Ford Motor Company

Work included project engineering and design schedules, detail design and

layout of mechanical systems, and coordination of field trades in the

installation of heating, ventilation, air conditioning, plumbing, and fire

sprinkler (1974 to 1975).

West Lorain Ohio Power Plant Project, Lorain, Ohio

Client: Ohio Edison Co.

Conducted jobsite purchasing for the West Lorain Ohio Power Plant Project.

Position involved the procurement of all equipment and materials used by

the trade crafts. All capital equipment was purchased and supplied by Ohio

Edison.

Uranium Recovery Facilities, Lynchburg, Virginia

Client: Babcock and Wilcox Co., Inc.

Spent one year at Babcock and Wilcox's naval nuclear fuel division.

Involving construction of a uranium recovery facility. AEC (Atomic Energy

Commission) and DOD (Department of Defense) clearances were required. AEC

is now referred to as NRC (Nuclear Regulatory Commission) Responsibilities

included the supervision of the construction trades, ordering of

construction materials and equipment, and the coordination of the project

with the plant engineering department at the main office in Barberton, Ohio

(1967 to 1968).

7.5 MEV (Million Electron Volt) X-Ray Building and Facilities

Client: Babcock and Wilcox Co., Inc

Spent one year at Babcock and Wilcox's Mount Vernon, Indiana plant as

jobsite Superintendent responsible for the construction of a 7.5 MEV

(Million Electron Volt) x-ray building and facilities (1970 to 1971).

PROFESSIONAL REFERENCES

BRYAN ESKRA,

PEC. LLC., MILWAUKEE, WISCONSIN

414-***-****

ED HOPKINS, DELEFIELD, WISCONSIN

PHILIPS MEDICAL SYSTEMS NORTH AMERICA

262-***-**** (Home Office) 414-***-****

GARY ANDERSON,

GE POWER SYSTEMS

414-***-****

DICK FULKERSON, ORLANDO, FLORIDA

SIEMENS WESTINGHOUSE POWER CORPORATION

407-***-****

MASOUD TARTIBI, ORLANDO, FLORIDA

SIEMENS WESTINGHOUSE POWER CORPORATION

407-***-****



Contact this candidate