Scott Erlandson

*** ******** *****

Green Bay, WI 54301

414-***-****

abidyc@r.postjobfree.com

PROFESSIONAL EXPERIENCE:

Peter Schwabe, Inc. Big Bend, Wisconsin June 2005 to

present.

January 1985 to January 1993

December 1976 to October 1983

Provided comparative cost estimates and established profit margins on

competitively bid projects as well as conceptual estimates and budgets for

design / build projects. Negotiated all subcontracts and purchase orders.

Established and maintained construction schedules. Responsible for

complete project management activities including Owner and Architectural

interface. Reviewed material submittals and shop drawings. Developed

change orders, drafted monthly draws and reviewed payouts. Coordinated

project close out and production of O & M manuals.

Medallion Homes, Inc. Green Bay, Wisconsin September 1998 to

May 2005.

Designed and constructed new and remodeled residential projects. Home

design was showcased in the 2002 Brown County Home Builders Association -

Spring Preview of Homes.

Hoffman Corporation Appleton, Wisconsin June 1996 to

September 1998

Construction Manager for new and remodel negotiated, design / build

projects including subcontract negotiations, purchase orders, scheduling,

change orders, draws and payouts. Provided conceptual estimating and

budgeting including consultation with our design division on materials,

finishes and structural elements.

ShopKo Stores, Inc. Green Bay, Wisconsin February 1993 to

May 1996

Owner's Representative and Liaison between Design, Contractors and Store

Operations for new and remodel construction projects. Oversaw remodeling

activities to minimize impact and provide for the safety of store patrons.

Maintained budgets and schedules. Selected contractors, authored change

directives, approved draws and contract close-out.

Stevens Construction Corp. Milwaukee, Wisconsin October 1983 to

January 1985

In addition to project management duties was responsible for concrete,

masonry and carpentry crews production including material purchases and

equipment allocation.

EDUCATION:

University of Wisconsin - Green Bay

University of Wisconsin - Milwaukee

College of Engineering

School of Architecture and Urban Planning B.S. Architectural

Studies

PREVIOUS PROJECT EXPERIENCE

COMMERCIAL

SHOPKO STORES, INC. - Green Bay, Wisconsin

Construction of three new stores and remodel of seven existing stores

in two years.

592,000 square feet. Total cost over $21 million.

McDONALD'S CORPORATION - Oakbrook, Illinois

Construction of over 200 new restaurants and remodeling of an

additional 500 over a 20 year period.

Currently involved in an extensive rebranding / reimaging program.

Total construction costs in excess of $70 million.

APPLETON AVENUE SHOPPING MALL - Menomonee Falls, Wisconsin

Complete renovation of 40,000 square feet of existing retail space.

$1.5 million.

SUNSET FIELDS SHOPPING CENTER - Waukesha, Wisconsin

Design / build addition to existing facility including approximately

60% tenant finish out.

18,000 square feet. $900,000.

BAY VIEW COMMONS - Milwaukee, Wisconsin

Mixed use: 34,000 sq ft retail space, 21 condos and underground

parking. $4.6 million.

LOCKER'S POINTE - Wauwatosa, Wisconsin

Mixed use: 7,000 sq ft retail space, 7 condos and underground

parking. $2.2 million.

CHASE BANK - Chicago, Illinois

Construction of two new branch bank facilities. 5,000 sq feet each.

$ 2.6 million.

MITCHELL BANK - Milwaukee, Wisconsin

Two story addition and complete renovation of existing bank and

office space

plus construction of remote drive-up building. $1.6 million.

PETER SCHWABE, INC. - Big Bend, Wisconsin

New corporate office building for general contractor.

14,000 square feet. $2.1 million

GOVERNMENTAL

MILWAUKEE COUNTY ZOO - Milwaukee Wisconsin

New construction of Great Apes Facility and complete renovation of

the existing Primates Building.

Work included interior and exterior exhibit spaces, holding cages and

staff offices.

55,000 square feet. $3.7 million.

KANE COUNTY GOVERNMENT CENTER - Geneva, Illinois

New three story County office building.

24,000 square feet. $1.6 million.

WARNING AND FORECAST OFFICE - Sullivan, Wisconsin

New construction of offices and weather radar facility for

National Oceanographic and Atmospheric Administration.

6,000 square feet. $900,000.

MILWAUKEE COUNTY TRANSIT SYSTEM - Milwaukee, Wisconsin

General construction of new headquarters office building.

28,000 square feet. $2.1 million.

PREVIOUS PROJECT EXPERIENCE

INSTITUTIONAL

ST. FRANCIS HOME - Fond Du Lac, Wisconsin

Design / build, 100 bed, skilled care nursing facility.

Three stories. 86,000 square feet. $7.2 million.

XAVIER HIGH SCHOOL - Appleton, Wisconsin

Fine Arts Center including 750 seat auditorium, band, choir, drama

and art classrooms.

Original design was $1.6 million dollars over budget.

Project was changed to design / build and brought in budget. 26,000

square feet. $4.2 million.

RONALD MCDONALD HOUSE - Wauwatosa, Wisconsin

New construction of hostel for families of children receiving medical

treatment at local hospitals.

Acted as construction manager and also coordinated donations to

building fund

from subcontractors and material suppliers. Three stories. $2.1

million.

BETHESDA LUTHERAN HOME - Aurora, Illinois

Residence facility for mentally handicapped adults.

Design / build project was originally $500,000 over budget.

Project was redesigned and brought into budget. 45 beds. 28,000

square feet. $2.2 million.

ERIN ELEMENTARY SCHOOL - Hartford, Wisconsin

Design / build project consisting of a 22,000 square foot addition

and 10, 000 square feet of renovation to existing school facility.

$1.8 million.

NORRIS ADOLESCENT CENTER - Mukwonago, Wisconsin

Two design / build projects including a new 10,000 square foot

administrative office building

and a 6,000 square foot addition to a student dormitory. Total

construction cost of $1.7 million.

PRESCOTT PUBLIC SCHOOLS - Prescott, Wisconsin

Two building project including gymnasium and classroom additions and

renovations

to Malone elementary and Prescott Middle School. Total construction

cost of $1.1 million.

UNIVERSITY SCHOOL - River Hills, Wisconsin

Construction of indoor hockey facility including rink, bleachers,

concession area and locker rooms.

18,000 square feet. $1.7 million.

NEW BERLIN PUBLIC LIBRARY - New Berlin, Wisconsin

Children's wing addition and renovations to office and circulation

desk. $600,000.

PREVIOUS PROJECT EXPERIENCE

MEDICAL

DANADA MEDICAL OFFICE BUILDING - Wheaton, Illinois

Condominium style office building occupied by twelve tenants.

Work included all interior tenant finish outs.

Three stories, 48,000 square feet. $5 million.

MARSHFIELD CLINIC - Marshfield, Wisconsin

Two clinic projects in western Wisconsin including X-Ray, Labs and

Treatment Rooms

and Geo-Thermal wells for heat pump systems.

5,200 square feet each. Total cost of $2.8 million.

WHEATON MEDICAL CLINIC - Wheaton, Illinois

Major addition and alterations to an existing medical facility.

Two stories. 20,000 square feet. $2.4 million.

MEQUON MEDICAL PARK - Mequon, Wisconsin

General construction project including concrete and carpentry work.

Two stories. 24,000 square feet. $1.1 million.

SACRED HEART HOSPITAL - Eau Claire, Wisconsin

Linear Accelerator Treatment Facility under construction in existing

Oncology Center.

1,100 square feet. $500,000.

INDUSTRIAL

OAK GROVE TECHNICAL CENTER - Prescott, Wisconsin

Initially awarded this project based on competitive bid.

Structural site problems prompted the owner to change to a design /

build agreement.

Research and development lab and office building is located on a 400

foot bluff

overlooking the Mississippi and St Croix Rivers. Three stories.

22,000 square feet. $2.1 million.

WISCONSIN ELECTRIC POWER COMPANY - Milwaukee, Wisconsin

General construction of a post-tensioned concrete parking structure.

Work done was first phase of a multi-million dollar project managed

by Boldt Construction for WEPCO.

Four levels. 250 cars. $1.3 million.

TOLIBIA CHEESE CORPORATION - Fond Du Lac, Wisconsin

Design / build project including office addition and remodeling of

production areas.

13,000 square feet. $800,000.

PHILLIPS PLASTICS CORPORATION - Eau Claire, Wisconsin

Design / build project including additions to office and

manufacturing areas.

24,000 square feet. $1.1 million.

GRAPHIC TECHNOLOGIES - Fredonia, Wisconsin

Design / build addition to office and production areas.

22,000 square feet. $1.2 million.



Contact this candidate