Tim S. Resh
**** ********* *****, *** *****, California 95758
916-***-**** abibpk@r.postjobfree.com
Education: Construction Management Experience:
B.S. Construction Over 25 years of project management,
Management; estimating and scheduling experience in
Minor, Business the construction industry. Estimating
California State experience includes public and private
University, civil engineering projects valued up to
Chico $9,000,000, and include sitework
projects, design-build projects,
Computer Skills: subdivisions, reconstruction projects,
Microsoft Office, Word, overlays & maintenance projects.
Excel & Outlook.
Suretrack
Scheduling Program, Background work includes paving,
Bids2 grading, underground piping, concrete
Estimating Program structures, flat work, road
reconstruction, sitework, infrastructure
Licenses/Certifications: & MSE walls. I also have many years'
experience, preparing commercial and
Contractors License industrial construction sites for
(C12) development work, including grading,
Earthwork & Paving, underground utilities, concrete
sidewalks and driveways, curbs and
CA #725641 gutters and asphalt paving.
40 hr Hazmat training
CPR trained
Renewable Energy: Excellent interpersonal and
Attending Certified communication skills, interfacing well
Solar Class Accredited with owners, engineers, contractors and
by ISPQ the public.
solar electric (PV)
Systems design
estimation and
installation of PV
systems
Solar Industry
economics, permitting,
financial analysis &
business operations
Select Project Experience:
Estimator, Granite Construction Co. Inc., Sacramento, CA 1997-2010
General estimator responsible for preparing estimates on public & private
civil engineering projects up to $9,000,000 which included: paving,
grading, underground, concrete, road reconstruction, site development,
infrastructure, and sitework projects.
Project Manager/Estimator, Cameron Park Airport District, Cameron Park, CA
2009-2010 Granite's PM for a $1,200,000 project to rehabilitate ten
residential roadways and provide drainage improvements. Responsible for
project estimates from conception to completion. Managed subs and crews,
dealt with engineers, owners & and public agency staff. Provided field
supervision, product procurement, submittals, RFIs and change-order
negotiations.
Project Manager/Estimator, Intel Corp. New Parking Lot / Sitework
Construction, Folsom, CA 2006-2008 Granite Construction Grading,
underground infrastructure work, concrete & asphalt paving for this
$800,000 project. Managed subs and crews, worked with engineers & owner's
representative. Provided field supervision, product procurement,
submittals, RFI's, change-order negotiations & billings.
Project Manager/Estimator, Foothill Raw Water Pump Station, Auburn, CA 2005-
2006 Granite's PM for this $700,000 grading, concrete & paving project
performed for the Placer County Water Agency.
Project Manager/Estimator, Woodland CNG Bus Facility, Woodland, CA 2003-
2004 Granite's PM for the $200,000 project which included grading,
drainage, concrete and paving for the City of Woodland Public Bus Station.
Project Manager/Estimator, Fruitridge Road Sewer Rehabilitation Project,
Sacramento, CA 2001-2002 Granite's PM for a $1.1 million project to
resurface and refinish approximately 4 miles of road surface. This road
reconstruction project called for the repair of damaged road sections and
the installation of an asphalt/concrete overlay. Responsible for schedule,
product procurement, RFI's and change-order negotiations. Also managed
subs, reviewed and approved pay requests.
Regional Manger, R. Gunn Construction, Sacramento, CA 1992-1997 Multiple
Asphalt Paving/Reconstruction Projects. Managed the office and field crews
providing asphalt paving and sealcoating operations. Estimated projects,
prepared billings, invoices, correspondence, and collected accounts
receivables. Responsible for office profitability and decisions pertaining
to equipment and operations.
Project Manager, Martech Environmental, Jet Fuel Line Installations,
Edwards Air Force Base, Lancaster, CA 1991-1992 $10 million jet fuel line
installation at Edwards Air Force Base. Performed all product purchasing,
scheduling, takeoffs and submittals. Prepared change orders and handled
contract and safety administration. Due to the sensitive nature of the
installation and the potential for needed abatement measures, the project
required in-depth environmental review and containment plans, hazardous
materials plan and a comprehensive SWPPP plan.
Project Manager, The Reinforced Earth Co., Western United States, 1989-1991
Multiple Projects. Responsible for training and oversight of the
construction and installation of MSE, (precast retainined earth) walls for
bridge abutments and roadway embankments & retaining walls. Served as a
Technical Representative during construction while preparing budgets, job
costing, purchasing, estimating, project plan review, change orders,
billings and accounts receivable from the home office.
References available upon request