B.S. Electrical Engineer, The Citadel, 1977-1981
SRO Certification GE BWR 4 & 6
Six years U.S. Navy –1971-1977 Nuclear Propulsion Plant Operator
Operations/Operations Support/Test/Modifications/Maintenance Engineer/Supervisor
PRA and On-Line Maintenance Engineer
Outage Management/Work planning Engineer w/Finest Hour and P2
Nuclear Safety and Compliance/Independent Safety Engineering Group Member
BWR and PWR Experience
Over 30 years power plant experience
“L” Doe Clearance
Plant Hatch Nuclear Safety and Compliance
Plant Hatch SRO School
Plant Hatch Engineering, Electrical Systems
Hatch Onsite Quality Assurance Lead Auditor Certification
Training Department Lead Engineering Instructor
PROFESSIONAL EXPERIENCE
10/97 – 9/2010 Various positions Plant Hatch, Baxley Ga
Started as Sr. Engineer and went on the Licensing Nuclear Safety and Compliance (NSAC) Duty rotation
quickly due to my experience in the nuclear field and comprehension of Technical Specifications. Answered
NRC Information Notices specific to Plant Hatch. Performed on many Root Cause and trouble-shooting
teams. (KT qualified)
Hatch SRO School – Completed (passing) through the Audit but due to Blood Pressure problems was
deemed not fit for Control Room duty. I did not let this affect my SRO grades.
Assigned to Engineering Support where I was assigned RPS, NSSS, ATTS and many other systems not the
least of which was RHR and Core Spray. Became very good with electrical prints until I was the “Go to”
person for any relay replacement on site. I was assigned to the Battery system when the current Engineer
retired. Performed as Project Lead for the battery replacement for 1B and 2B Station Service which occurred
under budget, under time and without injuries. Worked on projects for various Plant Uprates. I worked
extensively on the Iso Phase Bus project after a transformer fire. Because of my SRO experience and plant
knowledge, I was most often selected to “Stand In” for my supervisor when absent.
Was selected for Quality Assurance by Upper Management where I qualified as Lead Auditor. While in QA, I
Performed a surveillance on the Corrective Action Program for all three sites and corporate. This gave me an
in-depth understanding of the CAP Process. I participated in many other audits, as well.
Plant Hatch, Baxley Ga cont’d
Due to new engineer turnover, I volunteered for Training for Engineering to steepen the learning curve for
new engineers and shorten the time until they are fully qualified. This has given me an understanding of what
training has to do to train engineers and because of my engineering and operations knowledge, I explain well
to new personnel. At the time of my retirement I was the lead Engineering instructor.
2/96-10/97 Outage Lead Engineer - Point Beach Nuclear Station
Responsible for Unit - 2 restart schedule including coordinating all Group inputs, progress and delays.
Reported critical path progress to Management staff.
Resume for
Glenn M. Davies
12/96-2/97 System Engineer - Maine Yankee Nuclear Station
Reviewed plant modifications and walked down plant systems to answer NRC concerns for plant restart.
Responsible for five Engineer review walkdown team.
9/95-12/96 PRA/On-Line Maintenance Engineer- Millstone Unit 2, Operations Work Control
Assisted in implementation of On-Line Maintenance Program by performing Probability Risk Assessment
(PRA), reviews of Look Ahead schedules for LCO conflicts and acceptable contingency plans for high-risk
maintenance. Coordinated with Northeast Utilities Corporate PRA office to ensure Risk Profile within
acceptable limits and adjusted schedules as necessary.
4/94-7/95 Operations Test Group Supervisor - New York Power Authority Indian Point 3
Responsible for supervising 11 NPO Test Group. Supervising and managing all post work, Post
Modifications, Technical Specifications, and Surveillance Testing required on Westinghouse PWR Plant.
Responsible for progress reporting to Management using Finest Hour generated bar-chars and schedules.
7/93-4/94 Integrated Operations Planner- New York Power Authority Indian Point 3
Integrated Operations Planner for Daily and Long-term Schedule. Extensive use of Finest Hour for Outage
Planning/Scheduling and Coordinating for Operations, Engineering and Performance Testing. Responsible
for scheduling and reporting on all Post Work, Post Modifications and Technical Specification Testing.
6/92-7/93 Lead Scheduler-Dresden Nuclear Station.
Assigned to the Work Planning Department to maintain Daily Schedule, incorporate backlog, pre-outage and
commitment activities into 12-week schedule while working priorities into 3 day, 1 week and 2 week
schedules. Represent Work Planning Department in Management Meetings to insure proper task integration
into Plan of the Day.
3/92-5/92 Capital Assessment Management Process Coordinator-Savannah River Site.
Developed integrated implementation plan for (CAMP) involving Capital Assessment Survey and maintained
implementation plan.
11/91-3/92 PM Component Evaluator-Savannah River Site.
Evaluated components for Proper Preventive Maintenance and intervals.
6/90-11/91 Operations Readiness Review Engineer - Savannah River Site
Performed activities to assure The Department of Defense nuclear reactors were ready for operation per the
stated schedule. This includes system walk-down as well as review of documentation, hardware, programs
and personnel to assure the appropriate programs are in place and functional.
9/89-6/90 Reactor Restart Issue Closure Coordinator- Savannah River Site.
Prepared Reactor Restart issue closure packages for Westinghouse Savannah River Corporation (SRS) and
the Department of Energy (DOE) approvals. Dispositioned and documented resolution of Reactor Quality
surveillance findings and Reactor Safety Evaluation Section (RSES) non-concurrences for Reactor
Operations restart issues to expedite closure. Formally traced restart issue deliverables, closure package
preparation and WSRC/DOE issue closure approvals.
5/89-9/89 Start-up System Engineer - Peach Bottom Atomic Power Station Unit-3.
Performed modification acceptance tests, system walk-down, trouble shooting and start-up testing.
1/89-5/89 Electrical Maintenance Staff - Peach Bottom Atomic Power Station Unit-3.
Rewrote inspection and Maintenance Procedures for AC and DC breaker assemblies. Performed walk-down
inspections.
Resume for
Glenn M. Davies
3/88-1/89 Project Management Engineer - Peach Bottom Atomic Power Station.
Liaison between Nuclear Engineering Department (NED) and Construction and Modification Department.
Represented NED at daily and weekly Construction meetings, Expedited NCR’s, Engineering Work Request,
and Modification Requests through NED.
11/87-3/88 Operations Support Engineer - Peach Bottom Atomic Power Station.
Performed activities required for plant start-up and NRC imposed plant shutdown. Specified work order Post
Maintenance Testing requirements and reviewed and approved Post Maintenance Test results. Developed a
computer tracking system for Post Maintenance Testing from work order initiation to final package close-out.
Wrote new and revised old Plant Administration and Operating Procedures.
3/87-11/87 Maintenance Planning and Scheduling Manager - Pilgrim Nuclear Station
Assigned to Pilgrim Nuclear Station during and extensive modification and refuel outage. Managed the
Maintenance Planning and Scheduling Group, which included 20 engineers, planners, and clerical personnel.
Maintenance Engineer Staff Assistant - Pilgrim Nuclear Station.
Responsibilities included performance and production monitoring, NCR tracking and closeout, and procedure
review and revision. Resolved an action item list generated from daily management and engineering
meetings.
4/86- 3/87 Nuclear Safety Engineer - Plant Vogtle
Assigned to Independent Safety Engineering Group. Reviewed the Fire Protection Program analyzed
Licensee Event Reports (LER’s) and prepared a Near Term Operating License report for management with
recommendations on how to reduce the number of LER’s for the first two years of operations.
Outage Management Engineer - Plant E.I. Hatch
Performed scope development, work planning, work package preparations, distribution and clearance
management.
Maintenance Engineer - Plant E. I. Hatch
Performed extensive reviews of Maintenance Management and peripheral maintenance programs for overall
maintenance assessment. Prepared reports for programmatic changes at both site and corporate levels for
Southern Company Corporate Management.
8/85-4/86 Operations Support Engineer - Carolina Power and Light Brunswick Station.
Assigned by General Electric to perform certification Senior Reactor Operator technical review of Plant
Modifications, and operations procedures.