Post Job Free
Sign in

Engineer Plant

Location:
Hazlehurst, GA, 31539
Posted:
September 08, 2010

Contact this candidate

Resume:

Glenn M. Davies ** Willie Mae Harrell Rd.

Hazlehurst Ga. 31539

Home: 1-912-***-****

Cell: 1-912-***-****

B.S. Electrical Engineer, The Citadel, 1977-1981

SRO Certification GE BWR 4 & 6

Six years U.S. Navy –1971-1977 Nuclear Propulsion Plant Operator

Operations/Operations Support/Test/Modifications/Maintenance Engineer/Supervisor

PRA and On-Line Maintenance Engineer

Outage Management/Work planning Engineer w/Finest Hour and P2

Nuclear Safety and Compliance/Independent Safety Engineering Group Member

BWR and PWR Experience

Over 30 years power plant experience

“L” Doe Clearance

Plant Hatch Nuclear Safety and Compliance

Plant Hatch SRO School

Plant Hatch Engineering, Electrical Systems

Hatch Onsite Quality Assurance Lead Auditor Certification

Training Department Lead Engineering Instructor

PROFESSIONAL EXPERIENCE

10/97 – 9/2010 Various positions Plant Hatch, Baxley Ga

Started as Sr. Engineer and went on the Licensing Nuclear Safety and Compliance (NSAC) Duty rotation

quickly due to my experience in the nuclear field and comprehension of Technical Specifications. Answered

NRC Information Notices specific to Plant Hatch. Performed on many Root Cause and trouble-shooting

teams. (KT qualified)

Hatch SRO School – Completed (passing) through the Audit but due to Blood Pressure problems was

deemed not fit for Control Room duty. I did not let this affect my SRO grades.

Assigned to Engineering Support where I was assigned RPS, NSSS, ATTS and many other systems not the

least of which was RHR and Core Spray. Became very good with electrical prints until I was the “Go to”

person for any relay replacement on site. I was assigned to the Battery system when the current Engineer

retired. Performed as Project Lead for the battery replacement for 1B and 2B Station Service which occurred

under budget, under time and without injuries. Worked on projects for various Plant Uprates. I worked

extensively on the Iso Phase Bus project after a transformer fire. Because of my SRO experience and plant

knowledge, I was most often selected to “Stand In” for my supervisor when absent.

Was selected for Quality Assurance by Upper Management where I qualified as Lead Auditor. While in QA, I

Performed a surveillance on the Corrective Action Program for all three sites and corporate. This gave me an

in-depth understanding of the CAP Process. I participated in many other audits, as well.

Plant Hatch, Baxley Ga cont’d

Due to new engineer turnover, I volunteered for Training for Engineering to steepen the learning curve for

new engineers and shorten the time until they are fully qualified. This has given me an understanding of what

training has to do to train engineers and because of my engineering and operations knowledge, I explain well

to new personnel. At the time of my retirement I was the lead Engineering instructor.

2/96-10/97 Outage Lead Engineer - Point Beach Nuclear Station

Responsible for Unit - 2 restart schedule including coordinating all Group inputs, progress and delays.

Reported critical path progress to Management staff.

Resume for

Glenn M. Davies

12/96-2/97 System Engineer - Maine Yankee Nuclear Station

Reviewed plant modifications and walked down plant systems to answer NRC concerns for plant restart.

Responsible for five Engineer review walkdown team.

9/95-12/96 PRA/On-Line Maintenance Engineer- Millstone Unit 2, Operations Work Control

Assisted in implementation of On-Line Maintenance Program by performing Probability Risk Assessment

(PRA), reviews of Look Ahead schedules for LCO conflicts and acceptable contingency plans for high-risk

maintenance. Coordinated with Northeast Utilities Corporate PRA office to ensure Risk Profile within

acceptable limits and adjusted schedules as necessary.

4/94-7/95 Operations Test Group Supervisor - New York Power Authority Indian Point 3

Responsible for supervising 11 NPO Test Group. Supervising and managing all post work, Post

Modifications, Technical Specifications, and Surveillance Testing required on Westinghouse PWR Plant.

Responsible for progress reporting to Management using Finest Hour generated bar-chars and schedules.

7/93-4/94 Integrated Operations Planner- New York Power Authority Indian Point 3

Integrated Operations Planner for Daily and Long-term Schedule. Extensive use of Finest Hour for Outage

Planning/Scheduling and Coordinating for Operations, Engineering and Performance Testing. Responsible

for scheduling and reporting on all Post Work, Post Modifications and Technical Specification Testing.

6/92-7/93 Lead Scheduler-Dresden Nuclear Station.

Assigned to the Work Planning Department to maintain Daily Schedule, incorporate backlog, pre-outage and

commitment activities into 12-week schedule while working priorities into 3 day, 1 week and 2 week

schedules. Represent Work Planning Department in Management Meetings to insure proper task integration

into Plan of the Day.

3/92-5/92 Capital Assessment Management Process Coordinator-Savannah River Site.

Developed integrated implementation plan for (CAMP) involving Capital Assessment Survey and maintained

implementation plan.

11/91-3/92 PM Component Evaluator-Savannah River Site.

Evaluated components for Proper Preventive Maintenance and intervals.

6/90-11/91 Operations Readiness Review Engineer - Savannah River Site

Performed activities to assure The Department of Defense nuclear reactors were ready for operation per the

stated schedule. This includes system walk-down as well as review of documentation, hardware, programs

and personnel to assure the appropriate programs are in place and functional.

9/89-6/90 Reactor Restart Issue Closure Coordinator- Savannah River Site.

Prepared Reactor Restart issue closure packages for Westinghouse Savannah River Corporation (SRS) and

the Department of Energy (DOE) approvals. Dispositioned and documented resolution of Reactor Quality

surveillance findings and Reactor Safety Evaluation Section (RSES) non-concurrences for Reactor

Operations restart issues to expedite closure. Formally traced restart issue deliverables, closure package

preparation and WSRC/DOE issue closure approvals.

5/89-9/89 Start-up System Engineer - Peach Bottom Atomic Power Station Unit-3.

Performed modification acceptance tests, system walk-down, trouble shooting and start-up testing.

1/89-5/89 Electrical Maintenance Staff - Peach Bottom Atomic Power Station Unit-3.

Rewrote inspection and Maintenance Procedures for AC and DC breaker assemblies. Performed walk-down

inspections.

Resume for

Glenn M. Davies

3/88-1/89 Project Management Engineer - Peach Bottom Atomic Power Station.

Liaison between Nuclear Engineering Department (NED) and Construction and Modification Department.

Represented NED at daily and weekly Construction meetings, Expedited NCR’s, Engineering Work Request,

and Modification Requests through NED.

11/87-3/88 Operations Support Engineer - Peach Bottom Atomic Power Station.

Performed activities required for plant start-up and NRC imposed plant shutdown. Specified work order Post

Maintenance Testing requirements and reviewed and approved Post Maintenance Test results. Developed a

computer tracking system for Post Maintenance Testing from work order initiation to final package close-out.

Wrote new and revised old Plant Administration and Operating Procedures.

3/87-11/87 Maintenance Planning and Scheduling Manager - Pilgrim Nuclear Station

Assigned to Pilgrim Nuclear Station during and extensive modification and refuel outage. Managed the

Maintenance Planning and Scheduling Group, which included 20 engineers, planners, and clerical personnel.

Maintenance Engineer Staff Assistant - Pilgrim Nuclear Station.

Responsibilities included performance and production monitoring, NCR tracking and closeout, and procedure

review and revision. Resolved an action item list generated from daily management and engineering

meetings.

4/86- 3/87 Nuclear Safety Engineer - Plant Vogtle

Assigned to Independent Safety Engineering Group. Reviewed the Fire Protection Program analyzed

Licensee Event Reports (LER’s) and prepared a Near Term Operating License report for management with

recommendations on how to reduce the number of LER’s for the first two years of operations.

Outage Management Engineer - Plant E.I. Hatch

Performed scope development, work planning, work package preparations, distribution and clearance

management.

Maintenance Engineer - Plant E. I. Hatch

Performed extensive reviews of Maintenance Management and peripheral maintenance programs for overall

maintenance assessment. Prepared reports for programmatic changes at both site and corporate levels for

Southern Company Corporate Management.

8/85-4/86 Operations Support Engineer - Carolina Power and Light Brunswick Station.

Assigned by General Electric to perform certification Senior Reactor Operator technical review of Plant

Modifications, and operations procedures.