ARUN KUMAR PANDEY
Contact: 828-***-**** (M),************@*****.***,**************@*****.***
Seeking Middle level Assignments in:
Project Management, E, C&I design of power plant/substation/steel plant
PROFESSIONAL PROFILE
o A result oriented professional 3.9years of experience in Project
Designing, Project Management, Quality Assurance, electrical & Control
and Resource management.
o Proficient in managing maintenance operations and taking cost-saving
initiatives to optimize efficiency of machines and enhance productivity.
o Proven abilities in enhancing process operations, optimizing resource &
capacity utilization, escalating operational efficiencies; while
curtailing costs and expenses. Expertise in project monitoring & ensuring
cost control within budgeted parameters.
o Proficient in reviewing of project schedule, ensuring cost control within
budget. Demonstrated excellence in handling activities involving working
out various requirements & monitoring overall project operations for
ensuring timely completion.
o Adept in managing maintenance operations and taking cost-saving
initiatives to optimize efficiency of machines to enhance the
productivity.
o Gained exposure in selection, programming and setting of MRSS's HT
breaker Siprotec, Areva's Micom, Easun Reyrolle's relay along with Devot,
INIX, etc.
o Experience in executing site enabling activities entailing following-up
of contractual & statutory requirements, installation of equipment,
safety requirements at site.
o An effective communicator with exceptional relationship management skills
with ability to relate to people at any level of business.
AREAS OF EXPERTISE
Designing of HT/LT System BOQ/BOM/PLANNING Relay &
protection selection
Cost Reduction Vendor Development Project
Management
Quality Management Operations Management
Electrical & Instrumentation Team Management
IEC61850, 60038, 60034, 60076, 61131, 62443, 60255IMPLEMENTATION
(Intermediate)
User SAP (simco) Module (Material Management & PM Module)
ORGANISATIONAL EXPERIENCE
Uttam Galva Metallics Limited Group, Wardha: Dec'09-NOV'011
Project Engineer (Electrical Sinter plant, Blast furnace, Power Plant &
MRSS Projects) / EPC Engineer
Rishabh Electrical Power Services, Location -Noida NOV '11-MAY 2013
Sr. Project Engineer (PROJECT & DESIGN)-HANDLING project of
? Brahmaputra group-SMS & CPP (PROJECT of SMS, CHP, ASH HANDLING, ESP)
? Bajaj Hindustan Power plant Jhansi-SUBSTATION & CHP AND AHP PROJECTS.
?RELIANCE POWER PLANT - SINGRAULI - SUBSTATION and ASH /COAL HANDLING
PROJECT
KINDEN INDIA PVT LTD
ENGINEER-PROEJCT DESIGN AND MANAGEMENT-JUNE 2013 TO PRESENT
Sizing of Electrical Equipment like Transformers, DGs, Bus Ducts, Cable
sizing, electrical equipments, selection of PLC,DCS,
I/O LISTING, POWER SYSTEM STUDIES, FEASIBILITY AND RELIABILTY WITH
SIMULATION SOFTWARE
Working on DDR AND DETAILING OF DESIGNING AND ALSO GOING THROUGH
TECHNOCOMMERCIAL
As per demand of the project
Technical Expertise:
. Knowledge of all type of LT switchgears like MCB, MCCB, Contactors, SFU,
and Aux. contactor Relays etc.
. Knowledge of HT/LT Electrical Equipment's like circuit breakers,
Transformers, Motors, Control Panels, and Cables etc.
. Cost Estimation and Technical Scrutiny.
. Detail Design after receipt of order.
. Transformer, Power & Control Cable Selection suitable for application
requirement.
. Preparation of Detail Drawings for Single Line Diagram, Cable Schedules,
Cable Layout etc.
. Procurement of Transformer, LT Panels, Control Panels, MCC, All types of
Cables etc.
. Lighting Calculation with the help of photolux software.
. Load Flow & Short circuit Calculation with the help of ETAP.
. Preparation of Electrical Equipment layouts & Lighting Layouts
. Preparation of Load list & Equipment list Load list & Equipment list.
. Preparation of Interconnection Schedule.
. Review of suppliers drawings/ documents
. Approval of suppliers drawings
. Preparation and Checking of Bill of Material
. Inspection of Electrical Equipments viz. Cables, Motor, MCC etc.
. Coordination with customer and supplier for procurement.
< Programmable Logic Controllers (PLC) of Allen Bradley, ABB, Siemens &
Fuji make.
< DCS - Honeywell AND SUPCON make.
< Networking of Allen Bradley PLC with RS VIEW software and on demand
report generation. Energy Management System which uses 17 power monitor
II of AB make, PC with RS POWER & RS VIEW software with PLC5.
< Boiler & Turbine Management System: Data Acquisition System of
Intellution FIX which communicates with 2 nos. of 33TPH boiler, 40TPH
boiler & 18MW steam turbine generator through FCP drivers & generate data
on demand.
< 505 turbine control governor and its interfacing with protech203.
< Knowledge of boiler instrumentation controls, supplied by M/s Thermax
Fuji Electric Ltd. & Turbine controls supplied by M/s Toyo Denki
Corporation, Japan.
< AC & DC drives of different makes like Allen Bradley, Siemens & ABB.
< Wide exposure to various process control/monitoring instruments; Single
loop & Multiple loop micro-processor based process controllers, recorders
(chart type & paperless type), transmitters (pressure, temperature and
flow), Vortex flow meters, micro-processor based valve positioners, Web
guiding systems & width measurement systems.
< Pneumatic instruments of different makes; Taylor, Festo, SMC, Schrader
Bellows & MAC.
< Oil Hydraulic Units of M/s Vickers, Rexroth, Nachi, Yuken, Racine & Orsta
comprising of directional valves, check valves, electro-proportional
valves, etc.
< Maintenance of 220/33KV switch yard, 2X22MVA 220/33KV transformers, 12
nos of 2MVA 6.6KV/430V transformers, 3X1500KVA 6.6KV HT DGs, 1X1750KVA LT
DG along with PLC based synchronization system
< 1200KVA & 900KVA, 6.6KV HT motors, 1500KW,690V AC motors
< Project management of 90TPH Boiler & 18MW Turbine Generator
< Power generation through 18MW TG, 1500KVA HT DG sets, 1750KVA LT DG set &
Load distribution management
< HT & LT breakers (MOCB, SF6 & Vacuum type)
Project Planning and Project Management
. Preparing detailed project reports and project execution plans after
thorough discussion with clients, selection of sites, project evaluation
in terms of outlays and profits attached.
. Listing down the resource needs for projects, after considering the
budgetary parameters set.
. Monitoring project status during the course of periodic project review
meetings.
. Responsible of product quality and cost, industrial planning and capital
expenditure (investments, expenses and engineering cost) from concept to
mass production release.
. Build industrial scenarios according to company industrial strategy and
select the most efficient.
. Assess and select suppliers and manufacturing location from both internal
and external sources.
. Leads industrial project having ethical and full concern of our field.
. Estimates cost, margins, band & risk within quality and profit balance.
. Create the industrial overall project file which includes all industrial
key indicators.
. Follow up key indicators.
. Follow PMP Process for the project as per requirement and write
deliverables.
. Involve in work very closely to design & engineering and marketing
departments to ensure the best gaze on product/material used also
influence design & engineering department to ensure Design For
Manufacturing is optimised by bringing ideas and proposal to adapt
design.
. Influence marketing department to optimise product cost, quality and ROI
by proposing solution to rationalize or to optimise commercial offer
(number or references, late differentiation.
. Coordinates all industrial functions (tools, electronic, assembly,
advanced quality and cost) and purchasing.
. Leads and coordinates industrialization resources, internal and external
manufacturing plants as well as international resources, suppliers and
subcontractors
Operations Management:
. Undertaking Operation and maintenance of Siemens Plc S7- 400, S7-300 and
ABB 800M,SUPCON,ALLEN BRADELEY PLC AND Power Monitor.
. Executing the functions pertaining to the preparation of loop wiring,
interconnection, logic, cable schedule drawings and trouble shooting
guide for Electrical Systems.
. Equipment Handling and regular trail checks for all electrical equipment
for safety interlocks & sequence circuits, synchronization with the help
of GEX 2000, GX 98, GPP for protection and excitation purposes.
Electrical AND CONTROL --Designing and analysis
. Estimation of Plant Electrical Load. Development of Single Line Diagrams
(SLD). Control Schematics for Power Feeder, Motor Feeder, Transformer
Feeder.
. Selection and Sizing of Electrical Equipments. Cable Tray routing layout,
schedule selection and sizing.
. System Studies and Calculation i.e. Short Circuit Analysis (Fault
Calculations and Stability Studies), Load Flow Analysis, Motor
Starting Study, Harmonics Study, dc battery and battery charger, AC UPS.
. Relay Coordination of entire plant with HV / MV / LV substation/ power
generation side, Earthing & Lightening Protection Design, Sub-Station
design. Electrical Equipment/System Specification.
. Handling of ETAP,AUTOCAD AND PHOTOLUX,SKM power tool, CYME, micro station
(cable tray routing AND INSTRUMENTAION ALLOCATION)for electrical
designing, For different calculation and design aspects, substation IEC
61850 consideration while automation and communication point of view.
. Modeling of MAIN ACTIVITIES HANDLED: Electrical equipment, cable trench,
cable tray and PLANT EXTRACTION in PDMS.
. Co-ordinate with other departments (Piping, Structural & Instrument) for
clash checking with cable ladder, lighting & equipment.
. Single line diagrams, Interconnection diagram, Preparation of cable
schedule.
. Layouts pertaining to: lighting, conduit, cabling, floor trunking,
earthing, lightning protection, cable tray, General Arrangement, Cable
calculation, Trench sizing.
. Helping Engg. For preparation of Tender, bill of material requested for
purchase and preparation for purchase order.
. Maintaining records of drawings and documents in systematic way for
reference.
Automation And Control
o Accountable detailed engineering, system engineering, instrument sizing,
and preparation of instrument data sheets, specifications, layouts, loop
drawings & logic diagrams.
o Maintaining, modifying & developing logic programs & mimic screen on
SCADA platform & transferring data from different platforms through PLC.
o Preparing drawings & documents required for implementing Automation
Control related jobs of PLC S7 300, S7 200, S7 400, ABB 800M, ALLEN
BRADELEY COMPACT BUILDER, SUPCON /HONEYWELL DCS PROGRAMMING.
o Responsible for system design, PLC panels along with software generation,
networking of PLC, MIS system, Net working with AC drives etc.
SCHOLASTICS
< B.Tech. (Electrical & Electronics Engineering from RKGIT, Ghaziabad,
UPTU in 2009 with 67.5% marks.
< 12th from T.V.N, Varanasi, C.B.S.E. Board in 2002 with 70.4% marks.
< 10th from MSVM, Siwan, C.B.S.E. Board with in 2000, 90.6% marks.
Professional Training Attended:
< 15 days training program for various controls & Automation used in
Sofcon, Delhi, organized by RKGIT, GZBD.
< 6 days training program for controls & Automation used in Steel Plant,
organized by fox control (Siemens).
< Siemens AC variable drives.
< Siemens PC-10 PLC programming & maintenance.
< Simatic Step 7 software.
< 3RD year internship for 45 days of switchyard of NTPC, Shaktinagar.
PERSONAL DETAILS
Date of Birth : 16th Feb 1986
Contact Address : b2/262, a3, ASSI, BHADINI, VARANASI.