Post Job Free
Sign in

Engineer Project

Location:
Kuwait
Salary:
65000 USD
Posted:
September 20, 2013

Contact this candidate

Resume:

AHMED KHEDR

AUTOMATION ENGINEER

http://www.beyond.com/Ahmed-Khedr

Contact

Picture 12

: 009**********

Street*, ***** *

Salmiya,

Kuwait.

Picture 11

: 009**********

Picture 10

: ab77sr@r.postjobfree.com

Personal Profile

cords, sky is the limit!

Career Objective

At this stage I'm looking broader for a career opportunity that can expand my capabilities where I exert

my best to prove worth of the position. I'm very much interested in challenging the field of PLC/SCADA

as well.

My experience can be summarized as almost 7 years in Honeywell Kuwait starting as Junior Project

Engineer, then a member of the DCS team then as a lead engineer (specialized in DCS's HMI) for the

past 3 years, leading a team of 9 members of different grades.

Keywords to describe my experience: DCS, HMI, EPKS, TPS, Fieldbus, Modbus, OPC.

Key Skills

Throughout my work experience and study, the following keywords describe most of the skills:

*Function Block Logic design *Leadership and teamwork

*HMI Design with VB scripting *Customer communications & acceptance tests

*OPC *Networking basics

*Modbus *Microsoft Office Word, Excel, Powerpoint

*Fieldbus *Matlab

Education

Bachelors Degree– Electronics and Electrical Communications

Faculty of Engineering, Cairo University, Cairo, Egypt

2000-2005

I graduated with "Distinction with honor" grade with a Bachelor's degree of the above mentioned subject.

During these 5 years I had successfully completed (with high grades) the following modules:

Electronics, Communications, Electrical low frequency circuits, Active Circuits, Micro-waves, Fiber Optics,

Fundamentals of process control, Signals and systems, Fundamentals of Operating Systems, Networks,

and GSM.

In addition, we finished the graduation project with excellent grade, for design and control of a robot.

Work Experience

Honeywell Kuwait, Kuwait

Full Time

Lead HMI/DCS Engineer (Building Control Schemes, Developing HMI Displays, Interfacing third party,

leading 9 members of the graphics team)

Aug 2006 to Present

I’m currently an Experion PKS System Engineer/Projects Engineer at Honeywell Kuwait, which I’ve joined

on August-2006, with the experience of a various projects of EPKS (Basically releases R211, R301, and

R310 with control of HPM, C200 with PMIO or Foundation Fieldbus I/O) and some TPS background. Prior

to Honeywell I had a short experience with Invensys Egypt (Triconex Division) as an application engineer,

and another short stay @ Cairo University as a research assistant.

Achievements

My experience with Honeywell Kuwait is full of the achievements that I'm proud of, out of which I'm proud

the most ot gain the management's confidence to assign me a leading role, in addition to being a senior

member of the organization.

I've successfully finished a number of projects/subprojects with the following customers:

EQUATE petrochemical (Kuwait) / Ministry of Electricity and Water (Kuwait) / Kuwait Oil Company /

Petrolium Coke Industries Company (Kuwait) / Kuwait Paraxylene Production Company / Kuwait National

Petroleum Company

The jobs closed with the above mentioned customers include my following roles:

Developing inteface logic between DMC+ and DCS for safe shedding

Developing and leading graphics team to build, implement, and test the HMI set of displays and

services

Coordinating project activities

Interfacing third party to DCS server and controller

Commisioning and customer/factory acceptance tests

Migrating customer's 4000+ displays from one release to latest with necessary team

management and customer testing/acceptance.

Languages

Arabic

Picture 9

(Fluent)

English

Picture 8

(Advanced)

Lithuanian

Picture 7

(Beginner)

Professional Memberships

Foundation Fieldbus

Picture 6

Identified for the completion of the FF professional course at Lee College, Baytown, Texas

Honeywell

Picture 5

Certified Control Application and HMI Application Engineer

Activities and Interests

Reading about technology new outcomes

Picture 4

Watching/playing football

Picture 3

Shopping (Electronics)

Picture 2

References

References available on request.

Honeywell Experience Details (Till Dec 2012)

• Aug-Oct ’06

• Self-Learning + TPS/EPKS Basics training

My first steps with Honeywell

• Oct ‘06-Apr ‘07

• Equate Petrochemicals, Kuwait

R210 Graphics modifications (Static drawing, dynamic linking, VB

scripting)

US to EST upgrade and related activities.

HMI Web Patches + Microsoft Updates installation

May-Jul ‘07

OL2K DCS iFAT (R210, C200, PMIO) @ Honeywell Amsterdam, the

Netherlands

LPK: I/O assignments + Bulk Build of I/O CMs

EG2: Serial Interface arrangements, assignments, address verification with

Triconex, Distribution of signals over CMs, minimizing peer-peer signals.

OPCI list creation and verification

Database punch list clearance with customer (DOW-OL2K)

Jul-Sep ‘07

Equate & OL2K site support

US to EST(R210) upgrade

Network activities (network optimization, domain controller group policies

and machine specific securities: support, checklist application)

Sep-Oct ‘07

Customized Microsoft Domains + CISCO Networks training

Added more knowledge about windows domains, domain controller, …etc

Oct-Dec ‘07

PCIC, Coke Calcinations Project (R301.1, C200)

DCS Power ON, SAT, startup and commissioning

Dec ’07-Feb ‘08

Equate and OL2K

Administrative activities, Site support

Feb-Mar ‘08

KPPC Aromatics DCS iFAT (R301.1, C200, FF I/O) @Honeywell Milan,

Italy

Honeywell Kuwait representative. Document follow up and collection,

acquiring info and technical details before DCS Power ON and site activities in

Kuwait.

Mar-Jun ‘08

PCIC

Database Modifications, Batch-Control (SCM) corrections and creation,

Displays modifications

Third Party Communication establishment ( RS232, RS485, MODBUS

TCP, Terminal Server )

Complete backup and recommendations to customer.

Jun-Nov ‘08

KPPC Aromatics (Tecnimont-SK consortium)

DCS Power ON, Pre-SAT activities, Hardware problems troubleshooting

and replacements, Database and graphics modification/creation, FF devices

commissioning.

Nov ’08-Jan ‘09

KOC (SK) COCC, GC09 Misc Activities

GUS graphics modification, lcn logic modification, Site Support

Feb ‘09

Matrikon OPC Hands-ON Workshop

Level 1, 2, 3, in Dubai

Mar-Aug ‘09

OL2K/Equate Utilities Steam-Grid Integration Project

Remote I/O installation, assignment, and configuration

PMIO of Equate HPM and OL2K C200 - signal splitting and I/O exchange

Summary display creation

Existing displays modification

Boiler Master building, logic and function design, control and testing

(R211, CMs)

Execution Period and Phasing optimization/design

May ‘09

OPM Training @ Brussels

R301-R310

Jul ‘09

Equate & OL2K Server/Stations Optimization – Led by TAC

Assisted and participated in most of the optimization process.

Aug ‘09

Equate & OL2K Server/Stations Optimization – Led by TAC

Assisted and participated in most of the optimization process.

Aug ‘09

KOC GC09, GC10, GC20, GC22

Site support, Hardware/Software troubleshooting, replacing C200

controllers.

Sep ‘09

KCC Plants cape to EPKS(R310) migration:

Validation and modifications of the migrated DSP displays

Sep’09 –Nov ‘09

Equate/OL2K OPM project preparation

MRT report collection, ERDB Checker, RTools, Displays migration and

validation testing. Displays optimization.

Dec ‘09

Equate EG-II, DCS-APC strategy integration.

Strategy modification for proper handover on shedding, and corresponding

graphics modification

Jan ‘10

KOC BS-131 Gas Pipeline to LPG plant at MAA

Gus displays modifications, additions, and creation (Graphics team-lead).

Feb ‘10

OPCTI training

OPC training level 1 & 2, OPCTI certified

Feb ’10

Completion and commissioning of Equate EG-II APC/ACE works

With customer’s satisfaction and letters of appreciation

Mar – Dec ’10

KOC – Al-Khadda BS140&150

KOC BS-131 new 40” Pipeline

Equate and OL2K OPM

HMI Team Lead. Graphics building and migration (LCN to HMI Web, and

HM Web R211 to R301)

July ‘10

Equate Seawater Cooling Towers: Migrating DCS CMs and I/Os between

controllers

For optimization and more reliability. Moved signals from one controller

to another, and exchanged CMs between 2 controllers (Hot cutover)

September ‘10

Equate Utilities: Migrating CMs and IOs to additional controller.

Loading optimization. Similar job to SCT above

Nov ‘10

Equate MTO (Siemens-Honeywell Communications)

Implementing HMI displays (Lead), and testing/verifying/troubleshooting

communications (SCADA-PHD-PI).

Jun’10- Current

Replacement of DCS System (ABB) at Az-zour South Power and Water

Distillation Station.

Replacing the distillation DCS system. Currently in the FDS submission

phase, launching the HMI works.

Jan ‘11

EXP-50001-WS (Brussels)

Advanced EPKS W/S (AC and TAC)

Throughout ‘11

Equate OPM (R211-R311)

Completed with HMI team successful migrations and customer dual

primary checks of 12 Servers (ESVs and ESVTs) ~ 4000 displays.

Jul’11

OPM

BRAVO Award of Honeywell ME as part of migration team.

Sep’11

Successful DCS FAT of Azzour

HMI Part – 2 distillers

Nov’11

Successful DCS FAT/iFAT of KNPC’s MAA FUP in Houston, TX

Leading the HMI checks + AspenTech’s DMC+ interface logic and

displays

July-Dec’11

KNPC MAA’s Further Upgrade Project (FUP)

Leading HMI team to Build, test, and install displays of 2 units (ESV and

ESVT, in progress). Building the generic/dynamic interface displays of

AspenTech’s APC (DMC+) in Experion HMI Web.

Jan’12

FUP

Successful Critical Shutdown of Workstation 3, Startup and

commissioning. Closing all HMI and APC FAT/iFAT punch items and getting

smooth operation handover.

Feb’12

Azzour South Power Station – Water Distillation plant – Stage 1 : Distillers

7&8

Successful Shutdown, Startup and commissioning. Leading HMI activities

and ensuring smooth operation handover.

Jan-Apr’12

Equate OPM: R311 to R400

Leading HMI Migrations and tests.

Jun-Jul’12

Foundation Fieldbus Professional – Lee College, TX

Certified PAS HMI Engineer

Certified PAS Control Engineer

Apr’12-Jun’13

Leading HMI activities of FUP project (WS-4, 5&6) for ES-Cs and ES-Ts.

Coordinating/Supervising Matrikon-OI Pilot job activities in KOC-GC20

(till Dec’12)

Coordinating/Supervising Site-Survey, and implementation of an F&G

integration/addition activity in KOC (various Gathering Stations and Booster

Stations – 6 sites). Contractor is IMCO.

Project/DCS Lead for a green-field project of Ministry of Electricity and

Water titled “Construction and Maintenance of 9 Water towers and annexed works

at Jaber Al-Ahmed City”. The project utilizes Filedbus and Profibus I/O.

May’13

Acquired a web-based training of leadership attributes, time management,

and fundamentals of financial management (~10 hours).