CURRICULUM VITAE
PRASANTA KUMAR NAYAK
E mail:ab6aas@r.postjobfree.com
ab6aas@r.postjobfree.com
Mobile No: 91-889*******
Looking for a challenging career in the field of CFBC Boiler Operation in THERMAL POWER
PLANT COMMISSIONING,OPERATION,MAINTENANCES & PROJECT
MANAGEMENT.Capacity of Boiler 155 TPH
Total Years of Experience: More than 8 years.
Total Years of Experience In Operation & Maintenance Of Thermal Power Plant : Above 5 years.(
Operation & maintenance of WHRB, AFBC BOILER and CFBC (155 TPH) boiler & auxiliary
and 40MW, 20MW & 50MW steam turbine unit.
Total years of Experience in Project &Commissioning Of Thermal Power Plant :3 Years,
(Commissioning of 2X155 TPH cold cyclone CFBC boiler & 2X50 MW steam turbine unit.)
Executive Summary
An expert professional with Diploma in Mechanical Engineering having around 8 years of
experience in Commissioning, Operation, Maintenance & Project of thermal power station.
Complete operation & maintenances of steam generator unit (WHRB, AFBC & CFBC) with
its auxiliary & steam turbine unit & its auxiliary as well as BOP of unit.
Fully comfortable with DCS OPERATING system.
Complete knowledge of pre commissioning activity and commissioning activity of complete
unit including steam generator unit (2X155tph CFBC) and turbo generator unit (2X50 MW) as
well as BOP of complete unit.
Understanding of all aspects governing operational activities and up to date knowledge of
latest technological advancements, regulations/ guidelines and statutory compliances in the
industry.
Sound knowledge hydraulic test, refractory dry out, alkali boil out, steam blowing,
safety valve floating, trial run of equipment and protection & interlock testing and in
turbo generator unit like oil flushing, vacuum pulling, over speed testing and
protection & interlock testing in different commissioning activity of steam generator
unit like etc.
Capable of taking quick decision during plant emergency during the shift.
Prepare & review shift wise MIS report with plant GM and evaluation of different plant
performance parameter.
PROFESSIONAL EXPERIENCE
Organization : FACOR POWER LTD ( 2X50 MW ), Bhadrak, Orissa
Designation : SR. ENGG (operation)
Duration : From Oct 2010 till date
Website : www.facorgroup.in
Company profile: Facor group incorporated in 1955 is one of the India’s largest producer &
exporter of ferro alloys with a annual production capacity 65000 ton charge chrome &
250000 ton chrome ore. The Group’s First power project is developed by Facor Power Ltd
which is a subsidiary of Facor Group is a coal based thermal power plant of 2x50 MW at
Bhadrak, Orissa.
Current Expansion Project: The Group plan to expand in power sector and to capitalize
on the opportunity in this sector. Its major expansion plans are
45 MW thermal power plant at Garividi, Andhra Pradesh
600 MW super critical power plant at Chhattisgarh.
ROLES & RESPONSIBILITY
(SR.ENGG Operation)
Initially involve in pre commissioning and commissioning activity of (155x3) TPH Make
ThyssenKrupp COLD CYCLONE CFBC BOILER & (2X50) MW STEAM TURBINE Make
BHEL as well as BOP of the unit.
Complete knowledge of cold, warm & hot start up of overall unit.
Monitor critical operational parameters of CFBC Boiler including its water & coal quality, LOI
as well as for STG unit including sp. Steam consumption, turbine heat rate etc.
Monitor the TG loading & coordinate in load distribution including export to SLDC .
Prepare the shift wise MIS report and present the same to plant operation GM
PREVIOUS COMPANY PROFILE:
Organization : BHUSAN STEEL & POWER LTD (20MW STG, 12MW
BPTG3*9MW TB), Meramundali, Dhenkanal.
Designation : ENGINEER (operation)
Duration : From 14th October 2009 to 16th October 2010.
ROLES & RESPONSIBILITY (Engineering Operation)
Worked as assistant shift in charge of 20 MW STG,12MW BPTG & 3*9MW TB unit.
Complete operation & maintenance activity of 3*75 TPH AFBC boiler unit..
Monitor critical operational parameter of overall unit & take corrective action to avoid break
down time of overall unit.
Prepare shift wise MIS report and present the same to operation GM.
Prepare job list & bar chart of planned shutdown of the unit with spare parts requirement & its
availability & manpower management and try to complete the shutdown of the unit within
definite time & budget.
Organization : BHUSAN POWER & STEEL LTD (40MW ), Thelkuli,Sambalpur.
Designation : ASST. ENGINEER (operation)
Duration : From 1st April 2007 to 10th October 2009.
ROLES & RESPONSIBILITY (Engineering /Mechanical/Operation)
Worked as assistant engineer of boiler DCS operation of 40 MW unit.
Complete operation & maintenance activity of 4*55 TPH WHRB boiler unit.
Comfortable with cold startup, hot startup & emergency condition.
Monitor critical operational parameter of overall unit & take corrective action to avoid break
down time of overall unit.
Prepare shift report and present the same to operation Shift in charge.
Organization : M/S TEST METAL ENGINEERING PVT TLD.
Designation : ENGINEER (Maintenance)
Duration : From 10
th
February 2004 to 30th March 2007.
Worked as Maintenance Engineer in power plant. Responsible for Maintenance daily &
annual maintenance of our different clients at different sites from 10th February2004 to 30th March
2007.
EDUCATIONAL DETAIL
2003 Diploma in Mechanical Engineering
10th from Board of Secondary Education, Orissa
2000
Personal Dossier
Father’s name : Mr. Kartikeswar Nayak
Date of Birth : 08th April 1985
Religion : Hindu
Marital Status : Married
Nationality : Indian
Address : Sergarh,Balasore, Odisha.
Linguistic Abilities: English, Hindi & Oriya
Notice Period : 3 Months
Declaration
I, PRASANTA KUMAR NAYAK, hereby declare that the information furnished above is true to
the best of my knowledge
Place: Balasore (Prasanta Kumar Nayak)
Date:05/05/2013