BHAGIRATHI KASHYAP

Contact: 91+982*******, 91+975*******

*****************@*****.*** *****************.**@*****.***

BOILER OPERATION ENGINEER (BOE)

OBJECTIVE: - Looking for a challenging and promising career involving technology that can utilize

my existing skills & can provide an opportunity as a mechanical eng. to achieve the goal of an

organization

PRESENT ORGANIZATION MARUTI COAL CLEANING & POWER LTD (300MW PF BOILER).

POST:-ASSIST MANAGER MECH (OPERATION SHIFT INCHARGE) IN 300 MW

POWER PLANT

DURATION: - 29.05.2012 to till date.

MY TOTAL EXPERIENCE

17YEAR EXPERIENCE(13year in power plant operation and 4year experience in maintance work in

210mw and 500mw pf power plant boiler and auxiliary( such as air heater coal mill fan) and chp

crusher

Equipment Handling Experience

BOILER

Thermal Power Plant, Capacity 451*2=902 TPH, 141 kg/cm^2 Pressure, Main stream and reheat

steam temperature of 540

Turbine:

135*2=270mw steam turbine (HURBINE) is a high pressure, intermediate reheat single cylinder,

single rotor, impulse and condensing type, turbine

Also we(shift in charge) are handle Ash handling plant

MY JOB RESPONSIBILITY

1 My main object operation of thermal power plants, and balance of plant with optimum

efficiency.

2 Supervision of Cold startup, hot startup, Warm startup, Normal operation and emergency

handling and safe shut down of unit.

3 Minimization generation cost.

4 Supervision plant performance in shift and power generation as per target and achieved desired

PLF.

5 Guide to desk Engineer for safe operation and at the time of emergency operation.

6 Analysis of trouble shooting and arresting it by coordination of electrical,C&I and mechanical

maintenance

7 Proper maintain safety standard to under worked manpower

8 To coordinate different department and associate man proper utilization.

9 Reduction of down time of machinery/equipment by preventive maintenance

10 To improve the efficiency of the plant by Monitoring and regular operational parameter of

plant.

11 To help in addressing in maintenance problems arising.

12 Load scheduling of plant for next day,to see of plant condition

13 To assist in addressing in maintenance problems arising. Monitoring any abnormality

equipment such a My main object operation of thermal power plants, and balance of plant with

optimum efficiency.

14 Supervision of Cold startup, hot startup, Warm startup, Normal operation and emergency

handling and safe shut down of unit.

15 Planning & implementing the preventive & breakdown maintenance schedules; conducting

failure investigation analysis to identify gaps & take corrective measures so as to reduce

equipment downtime & maximize plant availability.

16 Monitoring and optimizing processes, troubleshooting problems of Boiler Feed Pumps, Cooling

Tower pumps, Gate Valves & Globe Valves.

17 Directing, leading and motivating workforce; imparting continuous on job training for

accomplishing greater operational effectiveness/ efficiency.

18 Responsible for operation of boiler water-treatment, Cooling tower and other utilities to

maintain the quality of steam and water.

19 Responsible for proper isolations of equipment/system for preparing permit to work, sanction

to work, and Access permits.

20 Coordination with Maintenance staff in resolving the plant problems.

21 Within the sphere of power plant administration I am responsible for administration of permit

to work system, reporting of plant incidents, production of generation statistics and log sheets.

22 Responsible for bringing back the station to normal in station blackout as soon as possible in a

safe and efficient manner.

23 Monitoring of overall station performance, monitoring of equipment’s performance which

includes steam turbine compressors, steam turbine condenser, Heat recovery boiler, cooling

tower etc for any degradation and to take corrective action for the improvement of station PLF

and efficiency.

24 Coordination with field operation engineers in monitoring field activities and instructing them

as and when required.

25 Responsible for the safety and fire protections in the plant area and periodic checking for their

healthiness.

26 Inspections of steam drum internals.

27 Drum and Main steam line safety valve internal inspection.

28 Checking of Steam, Water & Auxiliary Turbine Piping as per IBR Standards.

29 Pre-commissioning checking of fans,Pump, Piping and its supports,duct supports,

30 Checking of starting permissive and trip logic of boiler.

31 Inspections of Main stream line and boiler supports inspection and set the spring hanger

supports.

32 Inspections of turbine lube oil and control oil, overhead oil piping and acid cleaning of above oil

system piping.

33 Checking of starting permissive and tripping logic of Turbine.

34 Reduction of down time of machinery/equipment by preventive maintenance

35 To assist in addressing in maintenance problems arising. Monitoring any abnormality

equipment such as Boiler, Turbine and their auxiliary, of plant,.

36 To make overhouling job list(equipment defact list) s Boiler, Turbine and their auxiliary, of

plant,.

PAST EXPERIENCE :-

1 Worked in M/s Prakash Industry LTD.Champa (C.G.) (AFBC Boiler & Turbine Operation) from 04

April 2000 to 25 May 2012 (12 Years) as Sr. Engineer power plant

2 Worked in M/s U. B. Engineering Ltd. (PF Boiler Maintenance) from 07 May 1996 to 30 Sep.1996 (5

Months) as Maintenance supervisor.

3 Worked in M/s Precision Engineering (Coal Mills and Coal Crusher maintenance) from Jan. 1997 to

15 April 1999 (2.4 years) as Maintenance supervisor.

4 Worked in M/s Mitsui Babcock Energy (India) Pvt.Ltd (Maintenance of Boiler & its auxiliary ) from

20 April 1999 to 22 Oct. 1999 (6 Months)

PAST WORK EXPERIENCE

1. I had worked 2year as turbine and boiler field engineer

2. Operating knowledge of 25mwX04 simens make impulse reaction turbine.

3. Operating of AFBC BHEL make 110TPH boiler and its working pressures 100Kg/cm. and temp

480+

4. Operating of knowledge of ion exchange principal DM. plant and their capacity 12 TPH and

25TPH X 2NO

5. Overhauling & Maintenance of B.H.E.L. make 500 MW and 210mw Boiler such as (super

heater water wall economizer and steam cool wall and their header)

6. Maintenance of coal crusher machine in NTPC its. Crushing capacity 1250 T/Hr. crushing size

200 mm. to 20 mm.

7. Maintenance of roller pulverized coal mill in NTPC Korba in 500 MW. Coal mill pulverized

capacity 70 T/Hr. per coal mill in 200 MW coal mill pulverization capacities 450 T/Hr. per coal

mill

8. Doing Both type(tubular and rotary type) Air heater maintance

9. Overhauling & Maintenance of F.D P.A FAN

10. Knowledge of Valve maintenance of pressure parts

11. Operating of 10 mw wasting house make impulse turbine operating of 10 mw wasting house

make impulse turbine operating of 10 mw wasting house make impulse turbine.

12. Operating of was heat recovery boiler BHEL making 46.8TPH X 02no & it’s working

pressure42.kg/cm & temp 410’C.

11Commissioning knowledge of waste heat recovery boiler

PRESENT COMPANY PROFILE:-

ISO, 14001:2004 & OHSAS 18001 certified company, a reputed .coal cleaning & power company in

Dipka Korba (C.G.), with 270 MW cfbc boiler running and 300 MW PF Boiler under project. it will be

complete to march2014.

TECHNICAL QUALIFICATON

Boiler Operation Engineer : B.O.E. LIECENCE NO58/2012from Chhattisgarh Boiler Board

DIPLOMA : Diploma in Mechanical Engineering

Board : M.P. Board of technical education Bhopal

Year of Passing : 1995

Degree B.A : from gurughasidas vishvidalay

PERSONNEL PROFILE:

MOTHER’NAME : LATE SMT PHIRATIN KASHYAP

Father’s name : LATE SHRI D.L.KASHYAP

Date of Birth : 01.07.1975

Nationality : Indian

Sex : Male

Marital status : Married

Address : BHAGIRATHI KASHYAP

ARYAN COLONY DIPKA BATARI

POST- DIPAKA DISTIC KORBA C.G

DECLARATION :-

I hereby declare that all the statement above are true and correct to the best of my knowledge

and belief.

Thanking you Signature of

candidate

Date - …11/08/2013 (Bhagirathi

Kashyap)



Contact this candidate