LEONARD RASKIN

**** ******* ****

SILVER SPRING, MD 20910

(H) 301-***-**** (C) 240-***-****

E-MAIL: a29kvx@r.postjobfree.com

CURRENT Fairfield Construction, Dallas, Texas/San Diego California

Senior Project Manager/Consultant

• Primary Senior Project Manager for the project management, and construction of three high-rise commercial, residential projects (Silver Spring, MD, Arlington, VA, and Washington, DC).

Projects were completed on time and within budget.

• Supervised two project engineers, an administrative assistant, and a project manager.

• Project involved: High rise concrete structures consisting of four, three, and two levels below grade for parking, and 10, 11, and 15 stories above grade for residences.

• Primary contact and negotiator with all local government officials and the utiity companies.

• Established construction schedules and scope of work for pricing, bidding, and award of sub-contracts for these projects.

• Managed the renovation of two I.M. Pei residential high-rise buildings.

• Currently serve as a construction management consultant for the Silver Sping and Arlington projects.

2004-2006 University Town Center/Prince George’s Metro Center, Hyattsville, MD

Senior Project Manager

• Assisted in the design and development of a large multi-purpose project consisting of a four-story underground parking facility, a 16-story high rise student residence hall, several individual multi-story condominium structures, retail facilities, and existing office buildings. Work included the associated infrastructure roads (State of Maryland, County, and private), water services, sanitary and storm services, telephone, electric, and cable.

• Served as primary contact and negotiator with local government officials (WSSC, various Prince George’s County officials) in the expeditious issuance of permits, including building, occupancy, waivers, and public works.

2003-2004 WCS Construction LLC, Washington, D.C.

Senior Project Manager

5-story, wood-framed, 120-unit condominium

• Interfaced with the owner and design consultants to coordinate project drawings.

• Worked with owner to procure project permits.

• Oversaw the formulation of the Construction Contract between owner and contractor.

• Prepared and maintained project schedule.

• Solicited, scoped, and participated in the awarding of subcontracts, including demolition, excavation, concrete, structural wood framing, supplies of lumber and trusses, masonry, roofing, windows, exterior siding, structural and miscellaneous metals, plumbing, mechanical, sprinkler, and electrical.

2000-2002 S.E. Foster Construction Company, Arlington, VA

Project Manager

$50M, 340-unit luxury condominium community consisting of structural concrete and wood framed buildings third party construction

• Directed the construction of the last 108 of the units as project manager and supervised two project superintendents.

• Managed customer service for the entire 340-unit project, including warranty, punch, and walk-through items.

• Developed the option packages including the pricing.

• Negotiated change orders with the owner and subcontractors.

• Reviewed the applicable shop drawings.

• Prepared and presented monthly requisitions to the owner, architect, and lender.

2000 Landow and Company, Bethesda, MD

Project Manager and Superintendent

9-story, 149-unit, luxury apartment building

• Directed preconstruction and construction.

• Examined drawings for coordination and to ensure reduction of potential construction problems and costs during project.

• Reviewed sub-contractor prices, scope of work, and awarded subcontracts for the project. These included sheeting and shoring, excavation, concrete, roofing, windows, masonry, elevators, sprinkler, plumbing, mechanical, electrical, and miscellaneous metals.

• Led design consultants to produce error-free drawings.

• Advised and implemented the most economical methods, materials, and designs.

1997-2000 Sigal Construction Corporation, Washington, D.C.

Project Manager

Renovation and addition of 4 stories to an existing 8-story office building; construction of a 5-story, free standing office building

Total costs in excess of $30M

• Scoped and participated in subcontract negotiations for concrete, miscellaneous metals, curtain wall, elevators, sprinkler, plumbing, mechanical and electrical subcontracts for both projects.

• Prepared and presented the monthly requisitions to the owner.

• Prepared and managed the construction schedule for these projects.

1991-1997 Rockwell International, Westfields Facility, Chantilly, VA, The National Reconnaissance Facility

Contract Administrator

Project consisted of over 1M square feet of office space, two parking garages, and several additional accessory buildings

• Managed contract for compliance.

• Reviewed schedule.

• Performed conceptual estimates.

• Examined change orders compliance to revised drawings and pricing.

• Quality-controlled construction drawings for their constructability and accuracy.

• Interfaced with Fairfax County authorities for permits and inspections

• Supervised a staff of six.

• Established a user-friendly database structure for the control of over 10,000 entries of construction-related documents, contract drawings, shop drawings, and construction-related questions.

• Obtained high security clearance for this project.

1985-1991 Richmarr Construction Corporation, Washington, DC

Senior Project Manager

• Conducted design, planning, scheduling, estimating, permitting, and land development and oversaw high-rise commercial/residential construction projects both administratively and at the construction site (included the initial construction phases and the tenant build-out).

• Supervised four superintendents.

• Interfaced with government authorities in design, permitting, inspections, and bond release.

• Participated in writing scopes of work and contract negotiations for several aspects of projects--site utilities, excavation, sheeting and shoring, structural steel, precast concrete facial panels, and other miscellaneous items

1977-1985 Lemar Construction Company, Washington, DC

Owner

• Started company specializing in commercial renovations.

• Project locations include: Walter Reed Army Medical Center, Naval Observatory, Naval Security Station, Andrews Air Force Base, Marine Barracks, and the Naval Research Laboratory.

1970-1977 The George Hyman Construction Company, Bethesda, MD

Holy Cross Hospital, Silver Spring, MD

Superintendent

• Oversaw a major hospital six story addition- consisting of the emergency department, radiology department, pathology department, and patient care facilities, two independent parking garages and major site work which included a mass fill operation to construct on-site parking areas.

• Supervised 8 foremen and 12 subcontractors.

• $12M additions and alterations.

National Visitor Center, Union Station, Washington, D.C.

Project Manager and Superintendent

• Remodeled Union Station Railroad Station into the National Visitors’ Center for the National Bicentennial Celebration.

• Completed historic renovations.

• Accomplished remodeling while railroad station remained in operation.

• Developed many cost-saving techniques to renovate this historic structure, including designing and constructing movable scaffolding to paint the 100+ foot ceilings, removing the main floor to construct an audio-visual theater.

• Installed hand-dug footings down to the original grades of the Washington, D.C. area in 1900.

• Demolished east end of original Union Station and many passenger platforms to construct a road from front to rear of the building.

• Supervised 5+ foreman and 10+ subcontractors.

• Managed sequencing of the Union Station Parking Garage Project.

Washington Hospital Center, Washington, D.C.

Superintendent and Project Manager

• Constructed the 5 story Intensive Care Facility (the first intensive care facility in a single building), underground parking facility and a 6 story multi-purpose medical facility consisting of operating rooms, radiological therapy and diagnostic facilities and patient examination areas.

• Remodeled operating rooms, including two open heart surgery rooms.

• Remodeled the complete Outpatient Department including a trauma emergency department suite, pharmacy, and hearing and speech department.

• Constructed a post-tensioned, concrete structure with precast façade.

• Supervised 5+ foremen and 15+ subcontractors.

AFL-CIO Labor Studies Center

George Meany Center, Silver Spring, MD

Additions and Alterations Superintendent

• Renovated a Catholic Seminary into a labor studies educational center.

EDUCATION

Bradley University Peoria, Illinois BS Construction Management

OTHER RELEVANT EXPERIENCE:

Senior Project Manager for the construction of:

• Olmsted Building, Arlington, VA – 14-story office building: $25M Richmarr Construction-A concrete and steel building (the one which caught on fire)

• CenterPointe Office Buildings Complex, Fairfax, VA – Twin 12 story office buildings: $30M Richmarr Construction-A structural steel framed building

• 2501 Porter Street, Washington, DC – 202-unit luxury apartment house: $15M Richmarr Construction-A concrete framed building

• Winston House, Washington, DC – 196-unit luxury apartment house: $15M Richmarr Construction-A concrete framed building with underground parking

• SpringPoint Industrial Center, Burtonsville, MD: $12M Richmarr Construction

• Ashburn Village Sports Pavilion, Ashburn, VA: $10M Richmarr Construction

• Southern Building, Washington, DC – historical renovations and addition of 2 floors to existing building: $14M Richmarr Construction

CERTIFICATION:

• State of Maryland Erosion and Sediment Control

ADDITIONAL EDUCATIONAL CLASSES:

• Basic Real Estate Appraisal Principles