Job Description
Top Skills' Details
1. 5+ years as a cell site of field tech
2. Ericsson experience (Must Have)
3. Projects include Macro's + Small Cell
4. Verizon experience nice to have
Job Description
Projects Supported:
Small Cell 5G Only
Small Cell 4G Only
Small Cell 4G & 5G (C-Band or 5GmmWave)
ODAS Node
IDAS Node
Macro New Build (assumes 4G and C-Band)
Macro Carrier Add (includes C-Band)
Macro RELO
Macro Drop & Swap
Macro C-Band Prep/Conversion
Macro Sector Add
Baseband Upgrade
The below tasks cover the major projects:
Small Cell, IDAS, ODAS 5G Milestone Integration Tasks
- Order License Key File (LKF) via IOP
- Import LKF to Ericsson Network Manager (ENM) via IOP
- Generate SiteInstall file (integration file) via IOP
- Install SiteInstall file onto 5G radio
- Once integration file reaches 65% install completion, click on the integrate icon
- When integration file reaches 100%, the radio is ready to verify connectivity to ENM
- Use ENM Scripting Server to verify that the ENM and radio are communicating
- Verify node is synchronized
- Verify node is on the latest software version, if not upgrade via ENM
- Run Post Integration Script via ENM Scripting Server
- Run Post Upgrade Script via ENM Scripting Server
- Verify PTP timing
- Repeat above steps for each 5G radio
- Assuming there are no issues, hand over the project to System Performance (SP) to build anchors and run their scripts
- SP will hand the project back to NA to finalize the activations process
- Test all radio/sectors and do speed and ping tests
- Enter testing data into IOP
- Complete all IOP Quality Check List Tasks
- Activate Call Signs in IOP [FINAL TASK & PAY POINT)
Small Cell, IDAS, ODAS 4G Milestone Integration Tasks
- Verify power, SFP, and overall Hub readiness to integrate baseband (reference RiPort Map)
- Order License Key File (LKF) via IOP
- Import LKF to Ericsson Network Manager (ENM) via IOP
- Generate SiteInstall file (integration file) via IOP
- Install integration file onto baseband
- Once integration file reaches 65% install completion, click on the integrate icon
- When integration file reaches 100%, the baseband is ready to verify connectivity to ENM
- Use ENM Scripting Server to verify that the ENM and baseband are communicating
- Verify node is synchronized
- Verify node is on the latest software version, if not upgrade via ENM
- Run Post Integration Script via ENM Scripting Server
- Run Post Upgrade Script via ENM Scripting Server
- Run 4X scripts in SAT Tool (if not done via the install files)
- Verify PTP timing
- Check RSSI on each radio/sector
- Verify light levels on fiber
- Assuming there are no issues, hand over the project to System Performance (SP) to build Golden Parameters and run their scripts
- SP will hand the project back to NA to finalize the activations process
- Perform E911 testing
- Complete all IOP Quality Check List Tasks
- Activate Call Signs in IOP [FINAL TASK & PAY POINT)
Macro New Build, RELO and Drop-and-Swap 4G & C-Band Milestone Integration Tasks
- Verify power, SFP, and overall Hub readiness to integrate baseband (reference RiPort Map)
- Verify fiber path
- Integrate IXRe at cell site (work with MSC)
- Order License Key File (LKF) via IOP
- Import LKF to Ericsson Network Manager (ENM) via IOP
- Generate SiteInstall file (integration file) via IOP
- Install integration file onto baseband
- Once integration file reaches 65% install completion, click on the integrate icon
- When integration file reaches 100%, the baseband is ready to verify connectivity to ENM
- Use ENM Scripting Server to verify that the ENM and baseband are communicating
- Verify node is synchronized
- Verify node is on the latest software version, if not upgrade via ENM
- Run Post Integration Script via ENM Scripting Server
- Build ERAN via feature activation tool for carrier aggregation
- Run Post Upgrade Script via ENM Scripting Server
- Run 4X scripts in SAT Tool (if not done via the install files)
- Verify PTP timing
- Build RETs via IOP (scan & troubleshoot with tower crew if not visible in IOP)
- Check RSSI on each radio/sector
- Verify light levels on fiber
- Assuming there are no issues, hand over the project to System Performance (SP) to build Golden Parameters and run their scripts
- SP will hand the project back to NA to finalize the activations process
- Perform E911 testing
- Drive test site and test all sectors, to include speed tests
- Complete all IOP Quality Check List Tasks
- Punch down environmental alarms
- Update FUZE Compliance (hazard materials on site)
- Apply stickers and signage
- Install and wire up Centeron Fuel Monitor
- Activate Call Signs in IOP [FINAL TASK & PAY POINT)
Macro Carrier Add C-Band Modification Milestone Integration Tasks
- Verify power, SFP, and overall Hub readiness to integrate baseband (reference RiPort Map)
- Integrate IXRe at cell site (work with MSC)
- Order License Key File (LKF) via IOP
- Import LKF to Ericsson Network Manager (ENM) via IOP
- Work with tower crew for radio swap out (RUL/RUS to 4449 and/or 8843)
- Use scripting tool and SAT Tool to add and delete radios from existing baseband
- Generate SiteInstall file (integration file) via IOP
- Install integration file onto new baseband (6648)
- Once integration file reaches 65% install completion, click on the integrate icon
- When integration file reaches 100%, the baseband is ready to verify connectivity to ENM
- Use ENM Scripting Server to verify that the ENM and baseband are communicating
- Verify node is synchronized
- Verify node is on the latest software version, if not upgrade via ENM
- Run Post Integration Script via ENM Scripting Server
- Build ERAN via feature activation tool for carrier aggregation
- Run Post Upgrade Script via ENM Scripting Server
- Run 4X scripts in SAT Tool (if not done via the install files)
- Verify PTP timing
- Build RETs via IOP (scan & troubleshoot with tower crew if not visible in IOP)
- Check RSSI on each radio/sector
- Verify light levels on fiber
- Assuming there are no issues, hand over the project to System Performance (SP) to build Golden Parameters and run their scripts
- SP will hand the project back to NA to finalize the activations process
- Drive test site and test all sectors, to include speed tests
- Perform E911 test (if required…usually at a 700MHZ only site getting upgraded)
- Complete all IOP Quality Check List Tasks
- Punch down environmental alarms
- Update FUZE Compliance (if any new hazard materials were added to site)
- Apply stickers and signage (for new cabinets)
- Activate Call Signs in IOP [FINAL TASK & PAY POINT)
Full-time