DAMODHARAN NAGALINGAM Instrumentation Engineer

* ** *

Location: Chennai, Tamilnadu, India. Email: adm4rf@r.postjobfree.com Mobile / WhatsApp: +91-900*******. adm4rf@r.postjobfree.com Res Tel No: +91-944*******. Passport: L9274746 until 28th May, 2024 LinkedIn: linkedin.com/in/damodharan-nagalingam-359a1b153 Skype: nkdamodharan CAREER OBJECTIVE

Comprehensive Professional Experience in the field of Instrumentation Engineering Seeking a challenging assignment in Oil & Gas Industry, where in my expertise attributes and skills can be utilized, enhanced in obtaining personal career objective and those of employer. CORE COMPETENCIES

• Project Planning & Execution • Leadership • Specialist Follow-up

• Project Progress Monitoring • Documentation • T&C and Start-up

• Manpower Planning • Team Working • Procurement & Installation

• Construction & Maintenance • Troubleshooting • Site Activities & Supervision PROFESSIONAL SNAPSHOT

Execute all jobs as per Specification, Standards, Scheduled task and Safety Procedures. Involved in SAT and Commissioning for Mechanical equipments, ICSS and its Consoles. Attended the DCS FAT during KOC Project, Kuwait.

Installation and Procurement of Instruments and other supporting materials as per the specification and Standards of the Projects.

Preparation & Review of Instrument documents – Process PID, IO List, Index, ILD, Junction Box / LCP Layout Drawings, Data Sheet, BOM, Inst Cable Plan Route, Hook-up drawings, Cause and Effect Drawings.

Prepare the Material Submittal, Method Statement, O&M Manual, and Project Schedule and submit to client for Approval.

Involved and attend the HAZOP Study for the Projects with the client. Installation of MCCP, AHU’s, FAHU, FCU Fire Shutdown Panel, Damper Control panel, Diesel Filling System (Level Transmitter and Leak detectors) and having the knowledge of Control wirings of these Panels to be interface with Fire Alarm System and IBMS. Knowledge in ELV Systems like IBMS, Fire Alarm, PA, CO Detection and Tel & Data etc and Prepare the Shop Drawing, Method Statement, Inspection Check List, RFI, O&M Manuals for ELV Systems.

Support the Commissioning, Electrical team for Start-Up’s accordance with safety procedures. Knowledge in ISA Standards and codes, Ingress Protection and Group Classifications. Involved in Techno Commercial Offers discussion with the Vendor Specialist. Responsible for conducting QA / QC Inspection.

Coordination with System Specialist for Installation, Inspection, T&C Activities. CAREER CONTOUR

Instrument Loop Test Coordinator March 2019 to May 2020 JGC – Tecnimont Sonatrach Hassi R’Mel Boosting Ph-3 Project, Algeria.

The Project works includes Construction, Installation, Loop Test, Functional Test Testing & Commissioning and Handing over the System.

Coordination with Civil team for Opening and Closure of Trenches.

Supervision for Signal, Power and FO Cable Pulling for all types of equipments and Instruments from JB & LCP to LER and CCB as per the Project / Construction Specifications & Standards.

Installation of DCS, ESD, FACP and FGS Cabinets at LER and CCB.

Laying, Termination of Power and Signal Interconnection cables for ICSS Panels and Consoles.

Laying and Termination of ICSS System cables like Prefab, Ethernet and FO Cables. DAMODHARAN NAGALINGAM Instrumentation Engineer

2 of 3

Coordination with Mechanical and Electrical team to complete the task for Termination, Loop checking and Commissioning of Mechanical and Electrical Equipments.

Supervision for Glanding and Termination in JB’s, LCP’s, ICSS Cabinets and its consoles.

Conduct the SAT with Client for all Mechanical equipments which includes Mapping, Loop checks, testing and commissioning and Start-Up.

Responsible for the Preparation of the Loop folders and responsible to Conduct Loop Test of all Instruments at site.

Responsible for daily Reports and Submit to the Top Management and Client.

Attend daily meeting to discuss about the daily activity and further Project Targets.

Attend the construction daily meeting with other teams to discuss about the complication at the site.

Responsible for the Project Closure documents (SAT & Loop Folders etc) and handed over to QC after take the final sign off from the client.

Conducting the Tool Box Talk before prior to Start the work.

Maintaining the house keeping at the work Place after completion of the daily activities and conduct the wind up meeting after closure of the works.

Responsible to conduct the Loop Test and Functional Test for ESD, Fire and Gas System.

Conduct daily meeting and weekly meeting with Sub-Contractors about the execution of the Project Forecast.

Instrument Engineer March 2015 to Dec 2017

Trags Engineering

• The Project works includes the design, construction, installation, commissioning of proposed modification of Eye Wash and Shower Bath Project at Qatar Fuel Additives, Mesaieed, Qatar

• The Project works includes the design, construction, installation, Testing and commissioning of proposed of ELV Systems (Fire Alarm, CO Detection System & BMS, PA, SMATV, Telephone & Data, CCTV and Access Control System) at Nozul Commercial Development Project and General Takaful Project, Qatar.

Project Engineer - Instrument Feb 2014 to Feb 2015 Global Techno Services

• Carrying out Projects & AMC for ELV Systems and provide full technical support compliance with Project Specification in Procurement, Installation and Testing Commissioning. Deputy Manager - IBMS May 2010 to Jan 2014

Maclellan Integrated Services Nokia India Ltd, Chennai

• Operation, Maintenance and Projects of all ELV Systems (Fire Alarm, BMS, PA, Audio Video System, SMATV, CCTV and Access Control System.

Instrument Engineer Dec 2007 to April 2010

Almeer Technical Services Co WLL Kuwait Oil Company (KOC), Kuwait

• Improvement to Header ESD Systems at South & East Kuwait GC’s,

• Facility in Modernization & Up-gradation Project of Eight Gathering Centers. (EF-1501)

• Corrosion and Scale Monitoring & Inhibitor Injection Package for SEK GC’s. (EF-1445)

• Effluent Water Disposal Plant Project (EF – 1090).

• Rectification of Fire & Gas System at 15 GC’s & BS’s (Project EF – 1483).

• Carrying out Instrument Maintenance and Shut Project’s at KNPC, Kuwait Mina Al Ahmadi Refinery (New ERP and AGRP Gas Plant’s)

Engineer Feb 2006 to Nov 2007

Transfield Hofincons Qatar Petroleum, Qatar (Dukhan Fields) & KNPC, Kuwait.

• Maintenance Data Acquisition and Optimization for SAP Implementation Project Engineer Dec 2004 to Feb 2006

Haden International Group India (P) Ltd Cipla, Goa.

• Operation, Maintenance and Projects for ELV Systems and Utility. DAMODHARAN NAGALINGAM Instrumentation Engineer

3 of 3

Application Engineer Dec 2001 to Dec 2004

Divya Process Instruments Petrochemical and Pharmaceuticals Industry, Chennai.

• Servicing, Calibration, Loop Checking and Troubleshooting of the different types of Process Instruments (Temperature, Pressure, Flow and Level), Making of RTD, Thermocouples, Dry Block Temperature Calibrator & Oil Bath, Temperature Transmitters, Indicators & Controllers, Level Indicators & Switches and Handling Minor industrial Project. ACADEMIC CREDENTIALS

B.E in Electronics & Instrumentation from Hindustan College of Engineering, Chennai, University of Madras, Chennai, Tamilnadu, India First Class – 2001. Diploma in Electronics & Instrumentation, State Board of Technical Education and Training, Chennai, Tamilnadu, India - First Class with Honors – 1998. CERTIFICATIONS & AWARDS

Appreciation Award for JGC Safety Day -2019 Competition. Appreciation Award Outstanding JGC SBC Staff for the month of August-2019. Appreciation Award for Implementation of Environment Management Program, Nokia Consolation Prize Award for the Nokia OHS Spot Hazard Competition - 2013. Certification of PLC AND SCADA ( Training & Programming ) DOTE, Chennai In-plant Training at EID PARRY INDIA LTD, Ennore, Chennai, Tamilnadu, India. SIGNIFICANT HIGHLIGHTS ACROSS THE TENURE

Huge Troubles and Alarms in Siemens and Tyco Fire Alarm are reduced to minimum with short duration of time using less manpower for NFPA Audit at Nokia Phase I and II which was held during 2011.

Suddenly Nokia Phase III 226 No’s of office area camera’s are down due to Faulty of network switch and replaced without cost impact (Saved INR 2 Lakhs). Installation, Testing and Commissioning of Four No’s of Tripods at Nokia Plant within one day for VIP visit from Finland.

Complete EST Fire Alarm System Loop Test and commissioning with all its interfacing signals and take the approval from consultant and made online submission for QCDD Inspection and it was completed within the period of 15 days as per the task given by Client and Consultant. Laying Prefab, Ethernet and FO Cable for ICSS Cabinets at LER within one week for ICSS SAT as per the Client information.

Date: (Damodharan Nagalingam)



Contact this candidate