Linkedin profile : https://www.linkedin.com/in/chetan-aggarwal-a2298a1a Personal statement

A structural engineer with more than twenty years’ experience in the civil engineering consultancy industry. Have experience in structural design of mega hydro power structures like dams, barrages, intakes, powerhouses, tunnel linings etc. Also has experience in metro stations and bridges. Hands on experience in prominent FEM analysis software like MIDAS FEA and STAAD Pro. A skilled leader with high level structural design experience and the utmost understanding of working to budgets and timelines. Core skills

• Client focused

• Detailed knowledge of structural design and delivery

• Working knowledge of Indian, USACE and other International codes of practice

• Strong analytical skills, attention to detail and commercial awareness Employment History

Principal Structural Engineer – AF Consult India Pvt. Ltd, Noida

(May 2019 - Present)

Responsible for the planning, analysis and structural design of a range of multi-disciplinary projects including Hydropower Dams, powerhouses, Tunnels, Water retaining structures etc. Duties

Performing analysis and design calculations. Preparing finite element models. Ensuring all designs that were signed off met with the appropriate codes of practice and standards

Liaising with clients and adapting to meet their requirements

Finding and implementing solutions to environmental concerns

Managing and training staff in the area of structural analysis and design

Leading the design process of all forms of construction

Analysing, updating and working to budgets and time frames Senior Associate – SMEC India Pvt. Ltd, Gurgaon

(February 2014 – April 2019)

Duties

Same as in my current company mentioned above

Senior Manager (Structural Design)- SNC LAVALIN India Pvt., Ltd, New Delhi

(February 2010 – January 2014)

Duties

Same as in my current company mentioned above

Senior Engineer (Structures)- SMEC India Pvt., Ltd, Gurgaon

(2007 – 2010)

Duties

Same as in my current company mentioned above

Engineer Structures – Eigen Technical Services Pvt. Ltd., Gurgaon

(2006 – 2007)

Duties

Structure analysis, design & detailing of Multi-storey Buildings Civil/Structural Engineer – Tekton Design Associate (Pvt.) Ltd., Male’, Republic of Maldives

(2004 – 2006)

Duties

Structure analysis, design & detailing of buildings and island resorts.

Preparation of BOQs & Tender documents

Site inspections.

Scrutinizing bills of contractors and preparing interim statements.

Preparation of Project time schedules.

Attending progress meetings and providing consultancy to client & contractor. Structural Engineer – Centre for computational Engineering, Chandigarh, India

(2002 – 2004)

Duties

Structure analysis, design & detailing of buildings. Field Engineer – Jai Prakash Industries Ltd., India

(1999 – 2001)

Duties

Responsible for preparation of bar bending schedules coordination with contractors and execution of work at different sites of underground power house complex. Work Undertaken that Best Illustrates Capability to Handle the Tasks assigned

Name of assignment or project: Head works of Shongtong Karchham Hydro Electric Project( 450 MW)

Location: Kinnaur, Himachal Pradesh, India

Client: Himachal Pradesh Power Corporation Limited, India Main project features: Shongtong Karchham Hydro Electric Project, a run-of-river scheme, on the river Satluj in Distt. Kinnaur of HP, envisages construction of 102.50 m long diversion barrage, near village Powari, to divert 406 cumecs discharge to four sedimentation chambers, each 300 m long. Slight movement of hill(creep) in valley direction has been observed on the right bank of river. Barrage, right side training walls are designed for this creep pressure to transfer it from right bank to left bank rock . Project is under construction. Major Activities performed : Finite element model and structural design of all the components of the head works of the project. Few snap shots of comprehensive FE models: Name of assignment or project: Power House structural analysis and design of Shongtong Karchham Hydro Electric Project( 450 MW)

Client: Patel Engineering Limited, Mumbai,India

Major Activities performed : Finite element model and structural design of each unit bay, turbine-generator foundation, rock anchored crane beam in transformer hall, transformer hall building frame, control room building etc. Few snap shots of FE models: Few snap shots of other FE models in Shongtong Karchham HEP: Name of assignment or project: Nikachhu Hydro Electric Power Project Location: Trongsa,Bhutan

Client: Hindustan Construction Company Limited

Main project features: Project is on River Nikachhu. It is a The major project components are a concrete dam, Desilting Cavern complex, Head race tunnel, Surge shaft, Valve house, Pressure shaft, Powerhouse Complex to house 2 nos. of 59MW vertical Pelton units each, Tail race tunnels and Outfall structure.

Major Activities performed: Finite element model and structural design of RC turbine- generator foundation. Snap shots of FE models of project: Name of assignment or project: Vishnugad Pipalkoti Hydro Electric project, Location: Uttrakhand, India

Client: Hindustan Construction Company Ltd., India Main project features: Project is under construction. The major project components are a 65m high concrete dam, Desilting Cavern complex, Head race tunnel, Surge shaft, Valve house, Pressure shaft, Powerhouse Complex to house 4 no’s of 111MW vertical Francis units each, D/s Surge Chamber, Tail race tunnels and Outfall structure Major Activities performed : Finite element model and structural design including dynamic timehistory analysis of dam. A typical FE report, I prepared, of a dam based on this project can be accessed at : https://drive.google.com/file/d/1C4PY0QNC0U46STajFpAJUItlkpmGFZKI/view. Few snap shots of comprehensive FE models:

Name of assignment or project: Tehri Hydro Electric Power cum pumped storage project Location: Tehri,Uttrakhand, India

Client: Hindustan Construction Company Limited

Main project features: Project is on River Bhagirathi. The project envisages impounding of surplus monsoon water of the river for utilizing it in a regulated manner for hydropower generation and irrigation. The mega project when completed will have an installed capacity of 2400MW . Major Activities performed: Finite element model and structural design of RC turbine- generator foundation. Snap shots of FE models of project: Name of assignment or project: Shahpur kandi dam project, Punjab, India Location: Pathankot, Punjab, India

Client: Soma Enterprise Limited

Main project features: Shahpurkandi Dam Project has been declared as ‘National Project’ by Ministry of Water Resources, Govt. of India during February 2008. It comprises of 55.5 high concrete Dam, 7.70 Km long Hydel Channel, 2 nos. Head Regulators 2 no. Power Houses of total 206 MW capacity. The project is on River Ravi.

Position held: Sr. Structural Engineer

Major Activities performed: Structural design of Dam overflow and non over flow blocks. Finally vetted by IIT Mumbai. Construction of dam is in progress. Few snap shots of FE models of project:

Name of assignment or project: Top Down Construction in NH-54 at Jatinga,Assam Location: Stretch on National Highway NH-54 near Jatinga Assam Client: Hindustan Construction Company, Mumbai

Main project features: National Highway no. 54 is to cross a small hillock near Jatinga in Assam. The level of the road is to be about 40m below the highest level of the hillock, which slopes down gently on the two sides along the road alignment. Another road, perpendicular to NH-54, passes over the top of this hillock. The NH-54 road stretch which is to cross this hillock is about 300m long.

Position held: Structural Engineer

Major Activities performed: Structural design of RCC Top Down Structure. Name of assignment or project: Dagachhu Hydro Power Project Year: March 2010 to May 2013

Location: Dagana District, Bhutan

Client: Hindustan Construction Company, Mumbai

Main project features: Installed Capacity - 114 MW; Diversion structure - 36 m high, Concrete Gravity Dam; Headrace Tunnel - 4.4m Dia and Underground Powerhouse. Project commissioned in 2015.

Position held: Structural Engineer

Major Activities performed: Structural design of RCC Retaining walls, bridges, aqueducts, Water intake RCC structure, Desilting Structure, Water channels, River training walls and control room buildings.

Name of assignment or project: Kutehr Hydro Electric Project Year: 2010 to 2012

Location: Himachal Pradesh, India

Client: JSWEL

Main project features: Installed Capacity - 3 x 80 MW; Diversion structure - 24 m high Barrage; Headrace Tunnel - 15 Km long, 6.2 m dia, Concrete lined circular and Underground Powerhouse. Position held: Structural Engineer

Major Activities performed: Involved in preparation and evaluation of construction tender

.Structural analysis and design of Barrage, substation building, Tunnel portal structures and tunnel lining, retaining walls etc. .

Name of assignment or project: Pare Hydro Electric Project Year: April 2010 – June 2010

Location: Arunachal Pradesh, India

Client: NEEPCO

Main project features: Installed Capacity - 2 x 55 MW; Diversion structure - 78 m high Concrete Dam; Headrace Tunnel - 7.5 m dia, 2.81 km long Horse shoe shaped and Surface Powerhouse. Position held: Structural Engineer

Major Activities performed: Involved in review of stability of Water intake structure as proposed in DPR, Structure analysis, design & detailing of Service bay structure of Power house complex. Name of assignment or project: Srinagar Hydro Electric Project Year: July 2008 – Feb 2010

Location: Uttranchal, India

Client: GVK

Main project features: Installed Capacity - 330 MW; Diversion structure - 95m high Concrete Gravity Dam; Headrace Tunnel - 2 nos., 1.01 km & 1.14 km long, 9 m dia, Circular and Surface Powerhouse.

Position held: Sr. Engineer- Structures

Major Activities performed: Involved in Structure analysis, design & detailing of Power channel, Cross drainage works, Bridges, Forebay Tank, Forebay Intake, bypass channel structures. Type of structure analysed and design : 2 to 20m high cantilever retaining walls with/without counterforts, cross drainage box culverts, column-beam-slab frame structure, isolated/raft foundations for power channel,CD works, Forebay tank, forebay intake and bypass channel structurtes, RCC/PSC girder super structure(For 2 lane bridges), Raft/Pile for substructure of bridges(4 nos).

Name of assignment or project: Kameng Hydro Electric Project Year: 2009

Location: Arunachal Pradesh

Client: NEEPCO

Position held: Sr. Engineer- Structures

Major Activities performed: Involved in Structure analysis and design of piles to resist lateral load for slope stabilisation of power house slopes

Name of assignment or project: Nyabarongo Hydro Electric Project Year: 2009 - 2010

Location: Republic of Rwanda

Client: Angelique International Ltd.

Main project features: Installed Capacity - 28 MW; Diversion structure – 41 m high Concrete Gravity Dam; Headrace Tunnel - 4 m dia, 1.2 km long D shaped and Surface Powerhouse. Position held: Project Coordinator

Major Activities performed: Responsible for DPR review and detailed design of power house, Tail race channel, Water intake structures. Project coordination. Name of assignment or project: Ting Ting and Tashiding Hydro Electric Projects Year: 2008

Location: Sikkim, India

Client: Dans Energy Pvt. Ltd.

Main project features: Ting Ting and Tashiding Hydro electric projects envisage the construction of 96 MW Hydro Electric Project each.

Position held: Sr. Engineer (Structures)

Major Activities performed: Involved in Preliminary structural design of power house, tail race channels, HRT intake structure and preparation of DPR. Name of assignment or project: Rohtang Road Tunnel Year: 2007-2008

Location: Himachal Pradesh, India

Client: BRO

Main project features: The Rohtang Tunnel project envisages the construction of a 8.8 km long highway tunnel in high Himalayan ranges near Manali (HP) to by pass the Rohtang pass on Manali

– Leh Road. The south portal of the tunnel is located at an altitude of 3055m (amsl) about 25 km north of Manali and the north portal is located across Rohtang pass on the left bank of the river Chandra at an altitude of 3080m (amsl) at 78.7 km away from Manali. The tunnel work comprise all civil, mechanical and electrical works in 8.8 km long bore two lane bi-directional highway tunnel with the finished width of 10m at the tunnel walk ways level Position held: Engineer- Structures

Major Activities performed: Was involved in Structure analysis, design & detailing of portal structures comprising of office cum ventilation building and avalanche protection structure. Name of assignment or project: DLF SEZ IT park at Silokhera, Gurgaon, India; 16 storey DLF Commercial Complex, Gachibowli, Hyderabad, 25 stories DLF complexes “Magnolias” and

“Summit” at Gurgaon, India

Year: 2006-2007

Client: DLF

Position held: Senior Design Engineer

Major Activities performed: Structure analysis, design & detailing of Multi-storey Buildings. Name of assignment or project: Residential buildings, Commercial buildings, Government / NGO Projects, Island Resorts, Mosques in Maldives

Year: 2004 - 2006

Location: Maldives

Position held: Civil / Structural engineer

Activities performed: Involved in:

• Structure analysis, design & detailing.

• Preparation of BOQs & Tender documents

• Site inspections.

• Scrutinizing bills of contractors and preparing interim statements.

• Preparation of Project time schedules.

• Attending progress meetings and providing consultancy to client & contractor. Name of assignment or project: Nathpa Jhakri Hydro Electric Project Year: 2002 - 2004

Location: Himachal Pradesh, India

Position held: Design engineer

Activities performed: Job responsibilities included:

• FEM analysis of Concrete casing around turbine using ‘Ansys’ Software.

• Structure analysis & design.

• Site inspections.

• Technical coordinator for 3D model of Nathpa Jhakri Hydro Electric project. Name of assignment or project: Multistorey Punjab Urban Development Authority office complex, Amritsar, Multistorey complex of Gandhi Vineeta Ashram, Jalandhar, Sports complex at Panchkula and Gurgaon, Design of water distribution network of a township in Ropar (Punjab) and Sec-51A,Chandigarh

Year: 2002 - 2004

Location: Punjab and Haryana, India

Position held: Design engineer

Activities performed: Involved in Structure analysis & design and Site inspections. Name of assignment or project: Baspa Hydro electric project Year: 1999 - 2000

Location: Himachal Pradesh, India

Main project features: Installed Capacity - 300 MW; Diversion structure –Concrete Gravity Dam; Headrace Tunnel - 4m dia, 7.95 km long, modified Horse shoe shaped and Underground Powerhouse.

Position held: Field Engineer

Activities performed: Responsible for preparation of bar bending schedules, coordination with contractors and execution of work at different sites of underground power house complex. Few more snapshot of FE models of the structures I analysed: 1) Pakaldul CFRD, J & K, India(Pre Bid stage design) 2) Warped training wall for Shahpurkandi canal inlet 3) Batkulan HEP – Penstock Bifurcation

4) DLF Silokhera SEZ building

5) HURL Barauni(Bihar) – Steel Bridge for a water supply scheme 6) Kundah PSP – Intake Structure

7) Kutehr HEP – Barrage

Education

Regional Engineering College, Hamirpur, H.P., India

(now known as “National Institute of Technology, Hamirpur”) B. Tech. (Civil Engineering)

(1995 – 1999)