PROFESSIONAL RESUME

JOSE B. FUENTES

+63-928-***-****

PARTICULARS

YEARS OF EXPERIENCE : 37 YEARS

PERSONAL EMAIL ADDRESS : ada2sv@r.postjobfree.com

EDUCATIONAL ATTAINTMENT

BACHELOR OF SCIENCE IN ELECTRICAL ENGINEERING

Technological Institute of the Philippines

SPECIALIZED FIELD

INSTRUMENTATION AND CONTROL : ENGINEERING DESIGN, CONSTRUCTION, START-UP AND COMMISSIONING

ELECTRICAL : ENGINEERING DESIGN, CONSTRUCTION, START-UP AND COMMISSIONING

FIRE AND GAS : ENGINEERING DESIGN, CONSTRUCTION, START-UP AND COMMISSIONING

HVAC SYSTEM : MAINTENANCE, CONSTRUCTION, START-UP AND COMMISSIONING

PIPING AND STATIC EQUIPMENT : MAINTENANCE, CONSTRUCTION, START-UP AND COMMISSIONING

PIPELINES : HYDROCARBONS AND MULTI PRODUCTS PIPELINE CONTROL SYSTEM DESIGN

FAT/SAT : TESTING & PERFORMANCE MONITORING

ENGINEERING & MAINTENANCE - STEEL INDUSTRIES (CONTINUOUS GALIVANIZING LINE)

SAFETY STUDIES : HAZOP, HAZID, IPF, FIRE & GAS MAPPING, RISK ASSESSMENT, Others

YEARS OF EXPERIENCES

DESIGN AND ENGINEERING : 24 YEARS – INCLUDING CONSTRUCTION ENGINEERING SUPPORTS OPERATION AND MAINTENANCE : 05 YEARS

HOOK-UP/CONSTRUCTION : 08 YEARS

PROJECT QA/QC : Part of HOOK-UP/CONSTRUCTION/CONSTRUCTION ENGINEERING

START-UP AND COMMISSIONING : Part of HOOK-UP/CONSTRUCTION/CONSTRUCTION ENGINEERING

PROJECT MANAGEMENT : Part of ENGINEERING/ HOOK-UP/CONSTRUCTION

SUMMARY OF WORK EXPERIENCES & DESCRIPTIONS

1.Project Management (Engineering and Construction)

2.Design Basis Scoping Paper Preparations for brownfield or facility improvement

3.Project Planning, Resource loading and Scheduling

4.ISO 9001 2008 & 2015 – QMS and AUDITING Project Implementation

5.Steam and Gas Turbine/Generator Control and Monitoring (GE/HITACHI/AVON/ROLLS ROYCE)

6.Air and Gas Compressors Control and Monitoring (Various Make and Model)

7.Gas and Liquid Onshore Pipeline Engineering

8.Leak Detection System (Acoustic, Pressure Point Analysis and Mass Balance) Technology application

9.Desalination and Water Treatment Plant

10.Chemical Injection System Design

11.Power Generation (simple and combine cycle) Design

12.Cathodic Protection System installation and testing

13.Building Automation System Operation and Maintenance

14.Fire, Gas and Access Control System Design, operation and maintenance

15.Gas and Liquid – Royalty/Custody/Fiscal Metering System (FMC/DANIEL/KHRONE/ELSTER)

16.Plant Emergency Shutdown System (TRIPLEX/TRICONEX/ABB PLANT GUARD)

17.Plant Distirbuted Control System (Honeywell/Emerson/Foxboro/ABB Symphony/AEG/Yokogawa)

18.Plant Wide Automation and SCADA System

19.HVAC Design and Control for both chilled water cooling and DX direct expansion

20.LEV FUME hood design and engineering

21.Electrical, C&A – Start-up, Commissioning and performance testing

22.HAZOP/HAZID/LDR/SRA/CONSTRUCTABILITY/IPF study and SIL Studies

23.Rejuvenation, upgrade and facility improvement work scoping.

24.FAT, SAT, Pre-commissioning and Reliability/Performance Testing

25.Vendor or Third Party Coordination, Techno-Commercial Review

26.Novated Materials and Long lead Items determination for early project executions

DETAILED ENGINEERING AND CONSTRUCTION INVOLVEMENTS

PROJECT MANAGEMENT (ENGINEERING AND CONSTRUCTION)

A)PREPARATION OF PROJECT STATUS REPORTS, CASH FLOWS and S-CURVES

B)REVIEW OF TWO WEEKS LOOK AHEAD SCHEDULES AND MANPOWER SCHEDULING

C)REVIEW OF CONTRACTS, TENDER REQUIREMENT AND CONTRACTOR’S LEVEL-3& 5 SCHEDULES

D)PARTICIPATE, UPDATE AND PREPARATION OF SCHEDULE RISK ANALYSIS

E)COORDINATION MEETING TO RESOLVE ISSUES WITH NEGATIVE VARIANCES

F)DEVELOPMENT OF RECOVERY PLANS AGAINST NEGATIVE PRODUCTIVITY AND VARIANCES

G)PREPARATION OF PROJECT TECHNOCOMMERCIAL BIDS AND SUBMITTAL PACKAGES

H)MONITORING OF WEEKLY PROGRESS AND VALUE OF WORK DONE

I)COST ESTIMATE AND MANHOUR ESTIMATES FOR EXPENDITURE REPORTING

J)ATTENDED MONTHLY WEEKLY AND MANAGEMENT MEETINGS.

K)COORDINATION WITH CLIENT PROJECT FOCAL POINTS AND PROJECT ENGINEERS

L)ESTABLISH MANHOUR ALLOCATION, VARIANCES AND SPENT PER PROJECT BASIS

M)ATTENDED BI-WEEKLY PROJECT PROGRESS MEETING

N)ATTENDED GLOBAL INTERFACES FOR MEGA AND GREENFIELD PROJECTS

O)IMPLEMENTATION OF ISO 9001 : 2008 QMS, PROCEDURES, FORMS AND MANUALS

P)PARTICIPATE IN PROJECT INTERNAL AND EXTERNAL AUDITING

Q)PARTICIPATE IN THIRD PARTY ISO 9001:2008 STAGE I/II AND SURVEILANCE AUDITING

R)IMPLEMENTATION OF PROJECT CONTROL OVERALL PROCEDURES

S)ATTENDED COST PROPOSAL CHALLENGE AND MANHOUR ESTIMATE

FEED AND DETAIL DESIGN DEVELOPMENT

A)HVAC SYSTEM DESIGN AND INTRUMENTATION

B)STEAM AND GAS TURBINE CONTROL

C)AIR AND GAS COMPRESSOR MONITORING, CONTROL and PROTECTION

D)THERMAL POWER PLANT

E)SIMPLE and COMBINE CYCLE POWER PLANT

F)DESALINATION PLANT

G)WASTE WATER and SEAWATER TREATMENT PLANT

H)GAS CHROMATOGRAPHS

I)GAS and LIQUID PIPELINES LEAK DETECTION SYSTEM

J)HIPPS – HIGH INTEGRITY PRESSURE PROTECTION SYSTEM

K)HYDROCARBONS AND WATER PIPELINES INSTRUMENTATION AND CONTROL ENGINEERING

L)HYDROCARBONS METERING SYSTEM (GAS/LIQUID)

M)HYDROCARBONS PIPELINE BOOSTER AND SHIPPING PUMPS

N)SALES/ETHANE GAS PIPELINES COMPRESSOR AND ANTi-SURGE CONTROL SYSTEM

O)HYDROCARBONS PIPELINES HIPPS PROTECTION SYSTEM

P)HYDROCARBONS PIPELINES SURGE RELIEF SYSTEM

Q)HYDROCARBONS PIPELINES CONTROL AND MONITORING UTILIZING RTU/PLC/SCADA

R)MULTI PRODUCT PIPELINES PRESSURE RELIEVING STATIONS

S)MULTI PRODUCT PIPELINES LEAK DETECTION SYSTEM

T)MULTI PRODUCT PIPELINES H2S AND COMBUSTIBLE GAS DETECTION SYSTEM

U)SALES GAS PIPELINE CYCLONE FILTRATION SYSTEM FOR BLACK POWDER APPLICATION

V)HYDROCARBONS PIPELINES CORROSION MONITORING SYSTEM

W)HYDROCARBONS PIPELINES CORROSION INHIBITOR SYSTEM

X) HYDROCARBONS PIPELINES DRAG REDUCING AGENTS

Y)MULTI PRODUCT PIPELINES EMERGENCY SHUTDOWN SYSTEM

Z)MULTI PRODUCT PIPELINES HEAT TRACING SYSTEM

AA)WELLHEADS/FLOWLINES/UPSTREAM/DOWNSTREAM PIPELINES CONTROL AND MONITORING

BB)METHANOL JETTY LOADING SYSTEM INCLUDING METERING AND CAPSTAN

CONSTRUCTION/START-UP AND COMMISSIONING

A)OIL AND GAS UPSTREAM/DOWNSTREAM

B)OIL AND GAS WELLHEADS/WELLSITES

C) OIL AND GAS PIPELINES AND IN-PLANT

D) POWER GENERATION/DESALINATION PLANT

E) PETROCHEMICAL PLANT

F)WATER TREATMENT/INJECTION

G)HVAC SYSTEM

H)BALANCE OF PLANTS (METERING SYSTEM, NITROGEN PLANT, TANK FARM, FUEL TREATMENT PLANT, ETC)

OPERATION AND MAINTENANCE

A)AEG-AUTOMATIC MONITORING SYSTEM (AMCS)

B)SCADA – SUPERVISORY CONTROL AND DATA ACQUISITION

C)HVAC SYSTEM, VENTILLATION SYSTEM and GREEN HOUSES AUTOMATION SYSTEM

D)IRRIGATION, HVAC, LIGHTING ENERGY MANAGEMENT SYSTEM

E)BUILDING AUTOMATION SYSTEM

F)STEEL INDUSTRY - ZINC AND ALUMINUM COATING

TRAININGS AND SEMINARS ATTENDED

TRAINING DESCRIPTION

CONDUCTED BY

LOCATION

DATE ATTENDED

FROM

TO

ISO 9001:2015 AWARENESS (QUALITY MANAGEMENT SYSTEM )

PHILSTEEL CORPORATION

BATANGAS

09. November 2019

09. November 2019

BOSIET/OPITO SEA SURVIVAL AND FIRE ESCAPE

BSTS

MALAYSIA

13.April 2015

15.April 2015

INTERNAL QUALITY AUDITING

PIPETECH

SAUDI ARABIA

13.October 2010

13.October 2010

ISO 9001:2008 QUALITY MANAGEMENT SYSTEM

PIPETECH/MAAZ

SAUDI ARABIA

13.October 2010

13.October 2010

BASIC SAFETY TRAINING AND ORIENTATION

SAUDI ARAMCO

SAUDI ARABIA

31.May 2009

31.May 2009

PROJECT MANAGEMENT MODULE - ONE WAY ELEMENT

WORLEYPARSONS

SAUDI ARABIA

14.March 2009

16.March 2009

COMPRESSOR CONTROL TRANINVIEW AND LOGIC DEVELOPMENT TRAINING PROGRAM

CCC – Compressor Control Corporation

ABU-DHABI

14.April 2006

17.April 2006

H2S AND BREATHING APPRATUS TRAINING PROGRAM

QATAR PETROLEUM

QATAR

December 2005

December 2005

HUET - OFFSHORE SEA SURVIVAL AND FIRE SCAPE CRASH TRAINING PROGRAM

SMTC

MALAYSIA

29.November 2004

01.December 2004

Symphony CADEWS – ABB (elsag Bailey) SAMA, Logic and configuration files development software for ABB-SYMBPHONY UCS system.

ABB ENERGY AUTOMATION SPA

SAUDI ARABIA

18.February 1998

20.February 1998

Fire, Security and Access Control System Crash Training Program

AEG-TELEFUNKEN

SAUDI ARABIA

07.February 1986

28.February 1986

Building Automation System Crash Training Programs

Power Failure Re-start Application Programming

Automatic Temperature Control Process applications

MICOS 3000R Direct Digital Controller for HVAC system and Greenhouse

Automatic Monitoring and Control System Overview

Energy Management system for Irrigation, HVAC, and other plant application.

Hierarical Structure of ATM-80 Host Computer system and its Master and Slave Redundancy Requirement

Main and Supervisory Consoles Operations, Configurations and Downloading

CRUDE/DIESEL OIL CUSTODY METERING APPLICATION AND START-UP

ROSEMOUNT PETROLEUM

SAUDI ARABIA

November 1995

ROSEMOUNT FAMILY SMART TRANMITTERS APPLICATIONS

SAUDIFAL

SAUDI ARABIA

January 1997

FOXBORO I/A – DCS and CMMS conceptual Application

FOXBORO RAYTHEON EBASCO

SAUDI ARABIA

January 1997

HONEYWALL BALLAST CONTROL SYSTEM APPLICATION FOR 5000 DWT coal carrier - PNOC

PHILIPINE NATIONAL OIL COMPANY

PHILIPPINES

15.January 1984

20.March 1984

Fundamental of Pneumatic and Electronic Process Controls for HVAC instrumentation

UNITECH ENGINEERING CORPORATION

PHILIPPINES

10. December 1983

15. December 1983

EMPLOYMENT HISTORY

1.Company Name : STEEL CORPORATION OF THE PHILIPPINES

Date Employed : September 24, 2018 to March 16, 2019

Position Held : PLANT ENGINEERING & MAINTENANCE HEAD

Country of Assignment : Balayan Batangas, Philippines

2.Company Name : ADSI ENGINEERING SDN BHD

Date Employed : July 18, 2016 to July 08, 2017

Position Held : TECHNICAL DIRECTOR

Country of Assignment : Sarawak Malaysia

3.Company Name : PETRONAS CARIGALI SDN BHD

Date Employed : September 03, 2014 to June 30, 2016 (last day of work)

Position Held : PROJECT MANAGER

Country of Assignment : Sarawak Malaysia

4.Company Name : PUSB ENGINEERING SDN BHD.

Nature of Business : Consulting and Engineering Firm

Date Employed : May 01, 2013 to August 31, 2014

Position Held : ENGINEERING MANAGER

Country of Assignment : Sarawak Malaysia

5.Company Name : PUSB ENGINEERING SDN BHD.

Nature of Business : Consulting and Engineering Firm

Date Employed : February 05, 2013 to April 30, 2013

Position Held : HEAD OF DEPARTMENT [C&A and ELECTRICAL]

Project Assignment : Sabah & Sarawak (Miri/Bintulu) Operation

6.Company Name : SASEC ENGINEERING AND CONSULTANTS CO.

Nature of Business : Consulting and Engineering Firm

Date Employed : July 18, 2011 to August 4, 2012

Position Held : TECHNICAL MANAGER

Project Assignment : Kingdom Wide O&G Operation

7.Company Name : WORLEYPARSONS - Petrocon Arabia Limited

Nature of Business : Consulting and Engineering Firm

Date Employed : February 18, 2011 to May 08, 2011

Position Held : LEAD ENGINEER (Instrumentation/Electrical/Communication)

Project Assignment : WORLEYPARSONS OFFICE – (PIPELINE DEPARTMENT)

8.Company Name : PIPELINE TECHNOLOGIES & SERVICES (PIPE-TECHS)

Nature of Business : LDS SYSTEM Distributor/Manufacturer/System Integrator

Date Employed : June 27, 2010 to December 24, 2010

Position Held : ENGINEERING MANAGER

Project Assignment : PIPE-TECH OFFICE AL-KHOBAR OFFICE

9.Company Name : WORLEYPARSONS - Petrocon Arabia Limited

Nature of Business : Consulting and Engineering Firm

Date Employed : June 17, 2006 to 02.October 2009

Position Held : LEAD ENGINEER (Instrumentation/Electrical/Communication)

Project Assignment : WORLEYPARSONS OFFICE – (PIPELINE DEPARTMENT)

10.Company Name : CEGELEC/PEL Company LTD. Abu Dhabi-UAE

Nature of Business : EPC Contractor

Date Employed : February 20, 2006 to May 08, 2006

Position Held : I&C – TURBINE CONTROL SPECIALIST

Project Assignment : Abu Dhabi (GASCO BAB and ASAB NGL Plants)

11.Company Name : WORLEYPARSONS - Petrocon Arabia Limited

Nature of Business : Consulting and Engineering Firm

Date Employed : February 18, 2005 to 02.February 2006

Position Held : LEAD ENGINEER (Instrumentation/Electrical/Communication)

Project Assignment : WORLEYPARSONS OFFICE – (PIPELINE DEPARTMENT)

12.Company Name : Ranhill Worley-Miri Sarawak Malaysia

Nature of Business : Consulting and Engineering Firm

Date Employed : November 10, 2004 to February 08, 2005

Position Held : Senior Instrument and Control Engineer

Project Assignment : PCSB MDO Office – Miri Sarawak Malaysia

13.Company Name : WORLEYPARSONS - Petrocon Arabia Limited

Nature of Business : Consulting and Engineering Firm

Date Employed : September 23, 1994 to October 10, 2004

Position Held : I&C – SUPERVISING ENGINEER

Project Assignment : WORLEYPARSONS OFFICE – Al Khobar KSA

12A. Seconded to ABB Energy Automation S.p.A/S.A.Kents

Madinah Yanbu Al-Sinaiyah Power and Water Control System Upgrade to ABB Symphony

Nov. 17, 1998 to October 2004

Lead Control System Engineer

12B. Seconded to RAYTHEON ENGINEERS & CONSTRUCTORS

1200 MW Combined Cycle project. Riyadh Power Plant

Jan. 29, 1995 to Feb.13, 1998

I&C Lead Construction & Start-Up Engineer

14.Company Name : UME/SMAS – AYTB (Raytheon Engineers & Co.)

Nature of Business : Engineering and Constructors

Date Employed : May 4, 1992 to April 17, 1994

Position held : Instrumentation Superintendent

Project Assignment : ARAMCO UWSS-1/UWIP-1/QURAYYAH

SEAWATER TREATMENT PLANT

15.Company Name : AL SAGRI TRADING and CONTRACTING

Nature of Business : O&M (AUTOMATION WORK SYSTEM)

Date Employed : January 29, 1989 to March 31, 1991

Position held : ATC / Automation Engineer

16.Company Name : ASTER SAUDI ARABIA LIMITED

Nature of Business : O&M (AUTOMATION WORK SYSTEM)

Date Employed : February 6, 1986 to January 28, 1989

Position held : ATC / Console Engineer

17.Company Name : UNITECH ENGINEERING CORPORATION

Nature of Business : Control system Specialist (HONEYWELL Distributors)

Date Employed : November 14, 1983 to February 6, 1986

Position held : Project Engineer (Instrumentation)

18.Company Name : ENGINEEERING EQUIPMENT INCORPORATED

Nature of Business : General Contractor (YOKOGAWA Instrument)

Date Employed : March 1982 to October 1983

Position held : Electrician/Foreman

19.Company Name : DOMAC CONSTRUCTION COMPANY

Nature of Business : General Contractor

Date Employed : January 1980 to March 1982

Position held : Electrical Technician

PERSONAL DATA

Nationality : PHILIPPINES

Date of Birth : April 05, 1960

Address : #12 k6th Street, Kamuning Quezon City 1103

EDUCATIONAL BACKGROUND

College : Technological Institute of the Philippines

Bachelor of Science in Electrical Engineering (BSEE)

1982 (Graduate)

Engineering Licensure Exam : Electrical Engineering Board Exam

Licensed Registered Electrical Engineer

Professional Regulation Commission

CHARACTER REFERENCES

Ir. Shahar Abdullah

Company Director

ada2sv@r.postjobfree.com

+601*-*******

Ir. Ashari Ebrahim

Head-Mech Department

ada2sv@r.postjobfree.com

+601*-*******

Dzarieff Bakri Mohammad

Oil & Gas Commissioning Manager

+601*-*******



Contact this candidate