VINIT KUMAR DUBEY
E-mail:acs6s3@r.postjobfree.com Contact: +91-976*******(M)
942-***-****(H)
Challenging assignments in MAINTENANCE, COMMISSIONING, PLANNING and ERECTION
EXECUTIVE SUMMARY
A dynamic professional with 8.6 year of experience in Maintenance, commissioning, Project Management, planning, Erection & Quality Assurance & Man Management.
Presently working with ADANI POWER MAHARASHTRA LIMITED as an Deputy manager at Tirora Distt- gondia (Maharashtra)
Experience in Maintenance and Commissioning of Ash Handling Plant and ESP of 660 MW (660MW x 5 Units) Super Critical Thermal Power Plant.
Root Cause Analysis of failures
Created annual budget for AHP & ESP mechanical maintenance budget.
Analysing Mechanical Maintenance cost and budgeting
Preparation of mechanical maintenance budget.
Preventive Maintenance, Break Down maintenance & Annual O/H of all equipment’s and Water & Ash transport pipe lines. Ash Dyke management, Mechanical maintenance & Annual O/H of ESP, Spares & vendor management
Maintaining integrity of maintenance SAP-PM and SAP-MM data, analysis and costs - by timely and correct data entries and validations.
Accountable for ensuring that cost control strategies are in place and acted upon according to the priorities along with skills in assuring availability of sufficient human & financial resources to carry these out.
Hands on experience in overseeing project activities from stage of conceptualization to execution including developing technical specifications, spare parts planning, procuring raw materials, conducting stage inspections, scheduling,
Leading, mentoring & monitoring the performance of team members to ensure efficiency in process operations and meeting of targets
Monitoring contract payments, schedule and all contract administration requirements as detailed in the specifications
Preparing contract documents for various work items including contractual terms and conditions, technical specifications and commercial terms as well as identifying spares for procurement
Completing pre-tender obligations like submitting pre-qualifications, study of contractual conditions, project cost analysis including considering cost impact of techno-commercial conditions
Preparing various project reports for identifying areas of obstruction / defects, conducting troubleshooting, service and repair to rectify the equipment’s.
Overseeing execution of preventive maintenance of Instruments, including schedules / shutdown maintenance to ensure trouble free and seamless operations
Spearheading activities involving working out various requirements & monitoring overall project operations for ensuring timely completion.
Monitoring the activity at sites and review of project schedule, ensuring cost control within budget, planning for cash flow requirements, etc.
Expertise on Erection & commissioning Electrostatic precipitator (ESP) of 5X660 MW thermal Power plant.
Expertise on Erection of Coal bunker and Man Power House (Turbine structure) of thermal power plant.
Expertise on Erection of ash handling system (rotary and piping) 5X600 MW of thermal power plant.
Expertise on planning of projects
Expertise on planning & erection of steel structural and piping work.
Expertise on assembly and erection of machineries and equipment’s.
Well versed in implementing cost saving measures to achieve substantial reduction in terms of production, raw materials, manpower and machine utilisation.
Skilled in managing works as per client’s requirements as well as knowledge of converting raw material into finished components.
Effective communicator with assertive and strong leadership qualities and analytical.
Make a plan for monthly and yearly for site
Planning and estimating the cost of project.
Record of executed work i.e. reports after execution, daily progress report.
Preparation of Bills for Sub contractors in SAP Module.
Preparing monthly, weekly and daily reports for contractors and as per requirement.
Proper communication with Sub contractors and client regarding work process and progress.
Expertise on erection and alignment of structural and equipment work.\
Employment Record
Tenure Company Name Designation
Since June’11 ADANI POWER LIMITED Deputy manager
Since Out’09 LARSEN & TOUBRO LTD ECC DIVISION Sr. Engineer
Since Jul’07 M/S GANNON DUNKERLEY & COMPANY LIMITED Assistant Engineer
Key Result Areas:
Maintenance
Carried out commissioning and mechanical maintenance of:
Ash Handling System including Ash Dyke Management, Dry Ash System, Maintenance of Water Pumps, Slurry Pumps, Vacuum Pumps, & Blowers etc., Equipment’s of bottom ash evacuation system & ESP.
Ash Handling System & ESP of Unit No. I, II, III, IV & V.
Suggested & successfully implemented various changes in design for the Ash Handling system for 5x660 MW Units of Adani Power Plant at Tirora.
Root Cause Analysis of failures.
Created annual budget for AHP & ESP mechanical maintenance budget.
Assisting in Spares identification for procurement.
Analysing Mechanical Maintenance cost and budgeting.
Preparation of mechanical maintenance budget.
Preparation of audit related documents.
Collation of data for performance monitoring and reporting.
Preventive Maintenance, Break Down maintenance & Annual O/H of all equipment’s and Water & Ash transport pipe lines. Ash Dyke management, Mechanical maintenance & Annual O/H of ESP, Spares & vendor management.
Maintaining integrity of maintenance SAP-PM and SAP-MM data, analysis and costs - by timely and correct data entries and validations.
Identification & interaction with Workshop for repair activities.
Contractor management.
Project Management
Managing the projects from concept to commissioning stage & handling project activities involving working out various requirements with respect to planning, utilities, machines, manpower & monitoring overall project execution for ensuring timely completion.
Developing financial projections, preparing budgets and performing extensive project costing.
Quality Assurance
Taking stringent quality measures including preparation / maintenance of necessary documents and conducting audits to ensure compliance with standards.
Monitoring adherence to quality systems and comply with ISO 14001/ TPM quality standards and maintaining requisite documents.
Implementing quality systems in the organisation to reduce rejections and ensure zero defect products.
Erection & Fabrication Operations
Ensuring effective site management and discipline to ensure safe execution of the projects.
Studying drawings, plans or patterns of structures to be made or repaired as per requirements.
Marking out shapes and other measurements on the metal.
Testing of the fabrication to ensure that they are precise, accurate, reproducible, "fool-proof" and specific to the product.
Eliminating redundant / obsolete processes involved in the design, development processes and working towards value-addition.
Ensuring fabrication and erection of steel structural and piping work as per drawing.
Ensuring erection of rotary equipment as per drawing.
Man Management
Managing a team of executives & guiding site staff members to address and resolve performance bottlenecks.
Planning effective manpower deployment & works scheduling of qualified workforce; addressing training needs to enhance morale and skills of staff and workmen.
Attainments:
Significantly did planning and erection of man power house & Coal bunker for ADANI POWER LIMTED (4x660MW) Mundra (Gujrat) Project being employed in GANNON DUNKERLEY AND COMPANY LIMITED.
Significantly did planning and erection of Electrostatic precipitator (ESP) and Boiler Structure for ADANI POWER LIMTED (4x660MW) Mundra (Gujrat) Project being employed in LARSEN & TOUBRO LTD ECC DIVISION.
Significantly doing planning, co-ordination erection commissioning and maintenance Activity of Ash Handling System and Electrostatic precipitator (ESP) (5x660MW) being employed in ADANI POWER MAHARASHTRA LIMITED in tirora (M.H.)
Academic Credentials
B.E. (Mechanical Engineering) from B.I.S.T, BHOPAL (M.P), R.G.P.V in 2007, secured 63.8%.
Academic Projects
LPG gas kit for 2 wheeler 4- stroke engine
Advanced detonator placing machine with drilling mechanism used in coalmines for blasting purpose.
Organization : Bansal Institute of Science and Technology Bhopal
Title : Advanced detonator-placing machine with drilling mechanism used in coalmines for
Blasting purpose.
Description : This project has been designed to ensure minimum risk and eliminate risk factors in
Blasting of coal walls. According to the concept operators can control the detonator placing machine and drilling mechanism with the help of computers. Total security for manpower with precise and fast working.
Training Attended
Organization : N.T.P.C. Vindhyanagar
Duration : 4 week
Department visited during training session - milling section & pressure parts.
Personal Vitae
Date of Birth : 15th June 1986
Address : NH-1 B-201, Vindhyanagar, Dist. –Singrauli- 486885, M.P.
Present Address : Adani power township, Shantigram Room No- 148
Passport detail : H8223319, valid from- 27/11/2009 to 26/11/2019
Marital status : Married