James Morrison QC Inspector
PO BOX **** New Glasgow, NS *****.********@*******.** 902-***-****
WORK EXPERIENCE
Senior QC Site Inspector KBR Edmonton, AB May 2014 to November 2014
Responsibilities Senior QC Site Inspector
Organizing all site QC Personnel to perform and maintain QC activities to see project
deadlines and completion.
Visual Inspections on Z662, and B31.3 piping spools Verifying Welding Procedures and
Test Planning for Welding and Hydro. Flagging Welds for NDT Crews and Requests
Ensuring all percentages were met for all NDT requirements Weld Mapping Weld Logging
Verifying Welding Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups
Punching Systems/Lines and Making Punch Lists for Pre Hydor Walks
QC Lead Inspector Khreen Inspections Ltd. Edmonton, AB March 2013 to November
2013
Leading Inpsectors For The Scope Of Work to See Project Completion
Visual Inspections Flagging Welds for NDT Crews and Requests Ensuring all percentages
were met for all NDT requirements Weld Mapping Weld Logging Verifying Welding
Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups Punching
Systems/Lines and Making Punch Lists for Pre Hydor Walks Test Planning and
Implementation Aspects:
QC Lead Inspector Aecon Suncor ETF Edmonton, AB January 2013 to March 2013
Visual Inspections Flagging Welds for NDT Crews and Requests Ensuring all percentages
were met for all NDT requirements Weld Mapping
Weld Logging Verifying Welding Procedures Mechanical Testing Checking pipe spool fit
ups and bolt ups Punching Systems/Lines and Making Punch Lists for Pre Hydor Walks
Test Planning and Implementation Aspects:
QC Inspector URS Flint Energy Services Christina Lake, AB June 2012 to December
2012
Duties
Quality Control Aspects: Visual Inspections Flagging Welds for NDT Crews and Requests
Ensuring all percentages were met for all NDT requirements Weld Mapping Weld Logging
Verifying Welding Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups
Punching Systems/Lines and Making Punch Lists for Pre Hydor Walks Test Planning and
Implementation Aspects:
QC Inspector WorleyParsonsCord Edmonton, AB January 2012 to April 2012
Duties
Quality Control Aspects: Visual Inspections Flagging Welds for NDT Crews and Requests
Ensuring all percentages were met for all NDT requirements Weld Mapping Weld Logging
Verifying Welding Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups
Punching Systems/Lines and Making Punch Lists for Pre Hydor Walks Test Planning and
Implementation Aspects:
QC Inspector The Regina Co Op Refinery on Shutdown and Revamps February 2011 to
June 2011
Duties: My main duties on this project is visual inspection, making sure were welders are
following all welding procedures for all carbon steel welding, stainless steel, and chrome.
Checking progress on tie points with exsisting spools for carbor cuts, bevel preps, mt
inspection, visual inspection, rt inspection, and postweld heat treatment and rt inspecton
after stress.
Quality Control Aspects:
Visual Inspections Flagging Welds for NDT Crews and Requests Ensuring all percentages
were met for all NDT requirements Weld Mapping Weld Logging Verifying Welding
Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups Punching
Systems/Lines and Making Punch Lists for Pre Hydor Walks Test Planning and
Implementation Aspects:
QC Inspector at Suncor Firebag Stage 3 Ledcor Industrial Edmonton, AB March 2010
to October 2010
project in Fort McMurray Duties: My Main duties on this project was doing pre hyrdro
punches to verify everthing was in place to proceed with hydro testing, then verified all
paper work was in place to proceed with hydro test with client, when hydros were done,
myself along with others in the QC department did reinstatement walks to officially sign off
and proceed with turnover. Also did Pneumatic testing on Instrument Air and Utility Air
lines which I organized and directed myself.
Quality Control Aspects: Visual Inspections Flagging Welds for NDT Crews and Requests
Ensuring all percentages were met for all NDT requirements Weld Mapping Weld Logging
Verifying Welding Procedures Mechanical Testing Checking pipe spool fit ups and bolt ups
Punching Systems/Lines and Making Punch Lists for Pre Hydor Walks Test Planning and
Implementation Aspects: Preparing Pneumatic and Hydro Tests Deadweight Testing and
Logging Witness Hydro Test, Pneumatic Test
QC Inspector Ledcor Industrial Edmonton, AB July 2008 to December 2009
at the Albian Sands Expansion 1 project in Fort McMurray
Duties: Quality Control Aspects: Visual Inspections Flagging Welds for NDT Crews and
Requests Ensuring all percentages were met for all NDT requirements Weld Mapping
Weld Logging Verifying Welding Procedures Mechanical Testing Checking pipe spool fit
ups and bolt ups Punching Systems/Lines and Making Punch Lists
Engineering Support Aspects: Understanding P&Ids Reading ISOs Redlining Drawings if
necessary Ensuring all field test are carried out to engineering specs Preparing RFIs and
complying with responses Designing tests based on client and engineering requirements
Test Planning and Implementation Aspects: Preparing Pneumatic and Hydro Tests
Deadweight Testing and Logging Witness Hydro Test, Pneumatic Test and Mandrel
Testing
System Turnover and Reinstatements Aspects: Assisting preparation for turnover
packages Preparing and witnessing reinstatement packs ensuring all paper work is signed
off and ready for client Preparing walks with client for reinstatements Signing off
reinstatement packs with client
Welder TrentonWorks LTD Trenton, NS January 1996 to May 2006
Duties: Experience in the following welding processes, FCAW, SMAW, and SAW
Operated a automatic welding machine that used six welding guns at one time Operated a
welding robot Experience with radiograph machines, cutting equipment, shears, punches,
burning tables, plasma burning tables, and torches
SKILLS
Certified CSA W178.2 Level 2 Inspector Codes B31.3, W47 & W59, Z662
ADDITIONAL INFORMATION
CSTS Certified Fall Arrest Training H2S Alive Certified
Reference:
Reg Kirby Construction Coordinator CPF Sunrise Energy Project Oil Sands Tel: 1 780
749 0435
Cell: 1-780-***-****