Post Job Free

Resume

Sign in

Planning Engineer Maintenance Instrument, Electrical Electrical

Location:
Al Jubail, Eastern Province, Saudi Arabia
Posted:
April 12, 2015

Contact this candidate

Original resume on Jobvertise

Resume:

M U N IR AH MAD SHER MO HAM MED

Planner Maintenance, Mechanical, Inst rument, & Electrical

P.O. Box 1832, Al Jubail 31951, Saudi Arabia

Tel (H): +966 (13) 3447279

Mobile: +966 (0-501******

E-mail: m aco5br@r.postjobfree.com

Iqama # 201-***-****

SUM MARY

I am hard working, sincere and a thorough technical professional, who can carry out

major technical assignments independently with commitment to safety, health and

environment system. and seeking a suitable position with a progressive organization where my

s kills and experience will add value and increase productivity.

T EC HN ICAL CAPABIL I T I ES & SKILLS

Develop maintenance job plans and discuss in detail the SAP notifications received from

operations with maintenance engineers for assigning resources and spares.

Ut ilize extensive knowledge of craft skills and knowledge of equipment involved and place

job steps in the proper sequence to ensure efficient completion of work to meet operational

requirements.

Possess a good working knowledge of CMMS systems and the ARAMCO Materials System

(AMS), including use of the AMS Catalog, requisitioning of AMS stock i tems, requisitioning of

D irect Charge Materials, use of surplus materials and procedures for returning surplus and

excess materials to the Storehouse. (RTI).

Create work plans for maintenance jobs with necessary information to allow efficient

scheduling and execution of maintenance work.

Have the knowledge, experience, and skills for handling and coordinating major Tu rnaround

/ Shutdown projects at various plants.

WORK EXPER IENCE

2 nd M a rch

H adeed Sabic Jubail Saudi Arabia

2014 - P resent

Site Engineer Instrument and Electrical

Job Responsibilities

To support SME / Engineering staff in the USA for the Hadeed Project work.

To execute all the jobs as per the project scope.

To guide technicians and other team members to expedite the execution of project work.

To communicate with Hadeed SME for any technical clarifications.

To review the existing drawing, compare with actual at the field and reflect the changes

on the drawings.

Take Picture / Videos of all the marked components as requested by consultants in USA.

Update the daily progress to the team lead.

Follow the project plan and ensure timely completion.

Ensure following all Hadeed s Safety & Organizational rules & policies.

SHARQ Petrochmical Company ( Sabic Affiliate) 7TH AUG, 2012 28TH FEB 2014

Planning Engineer Maintenance ME I.

Job responsibilit ies.

Performing the activities as per new work management process AHC ( Asset Health Care )

i ncluding initiation, scoping, planning & scheduling, execution, monitoring & controlling.

Responsibilities carried out included preparation, estimation, budgeting, planning

scheduling motoring, reporting, resource planning, work order processing, contractor &

p rocurement monitoring.

Implementation of SHEM (EHSS) & quality requirement during packages preparation, and

p lanning.

Receive notifications, log and process all work orders, ensuring conformance with the

l atest revision of the maintenance work order.

Prepare purchase requisition (PR) in SAP and follow-up with materials department to

receive spares / services in timely manner .

Identify all materials, tools, equipment, and special preparations required for each job

s tep.

Schedule meetings with Operations and Maintenance sections for jobs selection.

Participate in the Weekly Schedule Coordination Meeting and present the weekly

schedule of workable maintenance jobs from the backlog.

Ensure that a clear understanding exists of which jobs will be worked upon in the

u pcoming week.

Finalize the Weekly Schedule for Operations approval.

Focal point for updating the status of the notifications and work orders in schedule list.

Prepare detailed job step plans in proper execution sequence, with details of craft man-

hour and crew size requirements for each step.

Ensure that materials are on-site prior to scheduling the job.

Arrange for support service equipment to coincide with the work order scheduling.

Responsible for communicating the work maintenance section, operation, engineering and

reliability when required.

Comply with all relevant safety, health and environmental procedures to ensure a healthy

and safe work environment.

Apply approved section policies, processes and procedures and monitor adherence so that

work is carried out in a controlled manner.

Perform other related duties or assignments as directed.

Establish, maintain and improve the Spare parts planning and coordination with supplies

department.

Update the history of job in SAP and close the work orders.

Periodically review and improve existing planning procedures.

Provide inputs regarding spares and services for budgeting purpose.

SaudiTaab Cont racting Company 28 Feb,2012 1

J uly, 2012

BMS Construction Engineer

Project Management with regards to the installation and testing of all types of

i nstruments and control valves, related to HVAC System at the Saudi Aramco Corporate

Data Center, Dhahran.

Participate in pre-commissioning activities of all SCPs.

QA/QC in maintenance and operation. Proficient in Evaluation & Monitoring of site

activities.

Ability to develop and implement a planning strategy for a project.

Extensive industrial work experience of various Industrial Projects.

31 ST A UG, 2009 26 T H

M a'aden Phosphate Company

J AN, 2012

M a intenance Planner U t il ities

Responsible for initial screening of incoming work notifications to work orders.

Closes work orders in a timely manner through planning and communication.

Prepare daily schedule from the approved Weekly Schedule.

C

oordinate daily schedule with Maintenance Foreman, Supervisor, and Operations

Foreman.

Apply day to day activities assigned for the section to ensure compliance with the

established standards

and procedures.

Responsible for the preparation on the schedule of corrective and preventive maintenance

activities.

Pr

oficient with computer knowledge on MS office, windows, MS outlook, CMMS

(Avantis system)

O racle and SAP.

H

ave sounds technical knowledge of Engineering Standards and different industrial

r ules and regulations

Saudi Elect ricity Company, Ghazlan Power Plant

1983 - 2009

For 25 years I have worked at the largest power plant in the Middle East, which comprises of 8

s team turbine units with a total capacity of 4400 MW and 3 water desalination uni ts with

total capacity of 12,000 cubic meters per day. My work assignments were both in

M aintenance and Technical Services Divisions of the Plant in the following capacities:

M a intenance Planner / Scheduler ( I+C)

1997 2009

As an Instrumentation & Controls Maintenance Planner, I am responsible for Corrective,

P redictive and Preventive Maintenance of I+C equipment from the start of the electronic

work order (in CMMS) until the completion for the work and its documentation. The job

i ncludes following activities:

Receiving the on-line work order, assessment for i ts correctness, and review with the

concerned Operations staff and Engineering staff to categorize the maintenance.

Review of the work scope by making site visits and discussions with concerned people.

Resource allocation, including parts, materials, tools & equipment, manpower, time and

work duration, special arrangements such as boundary isolations, and safety requirements,

etc.

Prioritizing of the work orders based on the criticality, system redundancy, availability of

resources, and safety/hazard issues.

Ordering of the required parts and materials th rough the company warehouse. If not

available, coordination the procurement of the parts.

Follow-up of the work through i ts execution until completion, and closing of the work

orders for KPI purpose.

Ensuring that all data (planning, execution, man-hour & material usage, costs, etc.) are

entered in the SAP (CMMS System) properly and on-time.

Maintaining the work backlog and issuing statistical reports to the concerned.

Issuing routine reports on work order statistics showing all Key Performance Indicators

( KPI).

M ateri a ls Coordinator ( Instrument and Electr ical)

1990 - 1997

As a Material Coordinator, I was in-charge of the in-Plant instrument and electrical store

room, where I managed all parts and tools for routine work in the Plant. My responsibili ties

i ncluded:

Controlling the f low of materials received from clients, company suppliers and ensuring

delivery to the projects & worksites in accordance with the company policies and procedures.

To receive, inspect and store materials and deliver to the worksite according to the project

schedule and in relation to the project s safety and quality policies.

Managing the store inventory to optimum level, setting up the min/max levels, organizing

t he store according to the type and usage of stocked i tems. Managing the electronic database

of the inventory.

Communicate with outside vendors, the Company warehouse and the Plant Maintenance

and Engineering Divisions on store and materials related issues.

Prepare technical specification, scope of work, and raising purchase request for new

equipments. Also responsible to make technical evaluations for all offers from material

suppliers.

Prepare scope of work and plan spare parts for annual tu rnaround maintenance.

Sr. I nstrument Technician

1983-1990

.

The safe use of a wide variety of hand and power tools, electronic and electric test

equipment as related to field and shop work; and safe work practices.

Skill in: Inspecting, testing, repairing, and installing industrial instrumentation and

controls according to established procedures and standards, reading instruments accurately

working from and in terpreting wi ring and mechanical drawings; use of hand and power tools

and equipment to test and calibrate instrumentation and controls.

Making estimates of labor and materials.

Ability to Communicate effectively and establish and maintain effective working

relationships.

Keep accurate, complete records and prepare reports

I C I Polyester Plant, Sheikhupura, Pakistan

1981-1983

Sr. I nstrument Technician

As a Senior Instrument Technician, I was responsible for the maintenance of major and

c ritical plant instrumentation. My duties included:

Conducting routine PM work and planned CM work.

Troubleshooting of failed instruments and equipment both in-situ and in the shop.

Filed repair, installation & calibration of key field instruments according to the industry

s tandards.

A t tending to instrument related Plant emergencies on short notices and staying on job

u ntil the problem

is solved and emergency removed.

Pak-Arab Fertilizers L imited, M ultan, Pakistan

1978- 1981

I nstrument Technician

My duties included:

I was responsible for ensuring instrumentation, control systems and automation systems are calibrated

and functioning properly,

Providing input to optimize the systems and ensure appropriate regulatory requirements and records are

maintained, assessing, maintaining, repairing, and monitoring control systems.

And systems associated with compressors, pumps, generation and well control, and maintaining the

performance of temperature, pressure, flow and level measurement control equipment, as well as VALVES

hydraulic control panels and single loop controllers. .

TRA IN I NG & CERT I F ICATES

CMMS (Oracle Maintenance & Warehousing System) ( 2 Modules: In terlinked)

CMMS (Avantis) Training Course.

Westinghouse Electro-Hydraulic Control System Maintenance Course.

Automatic Boiler Control with Bailey 820 System Course.

Plant Safety Course.

FOXBORO Training Course (Fundamentals of Pneumatic and Electronics

I nstrumentation)

Certification of TQM Techniques (Team Leaders & Members)

First Aid Training Certificate.

Oracle Employee Self Service Certificate.

Asset Prioritization Workshop-Ammonia Plant Certificate.

Asset Maintenance Task Validation Workshop Certificate .

ED UCAT IO N

D iploma of Associate Engineer in Electr ical Technology

Government College of Technology, Mul tan, Pakistan

P ERSONAL DATA

P rofile: 57 years old, Mar ried with 2 children

Nationality: Pakistani

Cur rent Location: Saudi Arabia

P refer red Location: Saudi Arabia, UAE

Language: E nglish, Urdu, Punjabi

Sala ry Expectation: Negotiable

References:

Ziaullah Siddiqui:

Email: aco5br@r.postjobfree.com

Phone Off : 013*******

Phone Mobile: 050*******

Abdulhamid Qureshi

Email: aco5br@r.postjobfree.com

Phone Off: 013*******

Phone Mobile: 050*******



Contact this candidate