Delaney Construction Corp./Tetra Tech Construction, Inc. Mayfield, NY September 2008 – Current
Project Engineer
! Developed and maintained cost and production tracking of work performed
! Monitored safety and environmental protection measures and completed incident reports
! Ensured work is accomplished within contract requirements and is delivered as per agreed budget
! Created project schedules and produced updates for clients
! Negotiated prices with subcontractors and suppliers for multi- million dollar construction projects
! Assisted project managers and superintendents with day-to-day operations
! Participated in project engineering reviews, studies and site investigations
! Prepared submittals and engineered various plans/procedures including formwork, demolition,
erection, maintenance and protection of traffic for approval by owners and design engineers
Delaney Construction Corporation Mayfield, NY June 2007 – December 2007
Estimation Intern
! Calculated material take off for various heavy civil projects ranging in price from $.5 to $85 million
! Digitized diverse site plans using Insite software to calculate mass earthwork
! Responsible for sending RFQ’s to subcontractors and vendors for private and DOT projects
! Utilized Hard Dollar and Primavera to develop accurate cost estimates
Dick Glode Construction, LLC Plattsburgh, NY Summer 2000 - 2006
Site Foreman/Carpenter
! Supervised employees and subcontractors to ensure timely completion of projects
! Coordinated ordering and billing of materials
! Operated heavy machinery including bulldozers, backhoes, excavators, loaders, telehandlers and
skidstreers
! Managed and completed equipment repairs
! Assisted in estimation, scheduling and bidding of upcoming projects
TECHNICAL SKILLS
Operating Systems: Windows, MAC OS X
Applications: Microsoft Office, Adobe Photoshop, Adobe Illustrator, Primavera P6, Insite, Hard Dollar and
Timber Line
Certifications: 30 Hr OSHA Certified, CPR and First Aid Response Certified, Man Lift and Fork Lift Certified,
NYS Flagger Certified, VT. Certified Traffic Control Supervisor, Qualified Rigger and Signal Person
Field: Automatic Level, Theodolite, Total Station, GPS, Heavy Equipment Operation, Rough and Fine
Carpentry, Mechanical (HVAC, Electrical, Plumbing), equipment repair
Design: AutoCAD, Land Desktop
EDUCATION
August 2008
Wentworth Institute of Technology, Boston, MA
Bachelor of Science in Civil Engineering Technology
PROFESSIONAL AFFILIATIONS
American Society of Civil Engineers
PAST PROJECT EXPERIENCE
Vtrans I-89 Bridge #81 Design Build, Milton, VT February 2013 – Present
Structures Project Engineer
Project Cost: $23,100,000
Working with the designer to develop plans for the replacement of two existing I-89 bridges known as
Interstate Bridge 81 North and South over the Lamoille River in Milton, Vermont. The two bridges will
be replaced with a single bridge consisting of three spans. Further responsibilities include
managing/scheduling of subcontractors, cost control, material deliveries, design review and submittals.
NYSDOT Route 17 Bypass, Parksville, NY May 2009 – October 2012
Structures Project Engineer
Project Cost: $95,000,000
Managed scheduling of subcontractors, material deliveries, cost control and submittals for 4.5 miles of
road, thirteen new bridges and five rehabilitated bridges. Performed field tests and assisted field
personnel with equipment utilization and repair. Coordinated completion of 1.5 million cubic meters of
rock cut. Supervised field operations for the completion of five rehabilitated bridges by Tetra Tech
Construction crews and subcontractors. Developed punch list and project close out.
Marble River Wind Farm, Clinton County, NY November 2010 – February 2011
Project Engineer
Project Cost: $20,000,000
Generated project reports and coordinated material deliveries for 145,000 linear feet of road, seventy-
two 2.5 mega watt Vestas Turbines. Tracked materials and produced cost control analysis for roads and
foundations, erosion and sediment control and maintenance and NYS Ag & Market restoration.
High Sheldon Wind Farm, Wyoming County, NY August 2008 – May 2009
Field Engineer
Project Cost: $24,000,000
Generated owner quality control record binders for seventy-five 1.5 Mega Watt GE Turbines and
twenty five miles of road. Tracked materials, equipment utilization and produced cost control reports
and assisted the project manager and superintendent as needed.
Perkins Restaurant, Plattsburgh, NY December 2005 – January 2006
Site Superintendent
Project Cost: $18,000
Coordinated and worked with owner to complete finish work installation in order to meet dead line for
store opening. Oversaw the carpentry work and other on-site subcontractors, ordered materials, and
coordinated with office staff building labor.
Esposito Home Addition and Remodel, Plattsburgh, NY June 2005 – August 2005
Site Superintendent
Project Cost: $380,000
Completed carriage house addition and remodel of historic house built in the 1800’s by working with
the owner, architect and Clinton County Historic Society. Responsible for ordering materials and
coordination of on-site subcontractors for HVAC, plumbing and electrical work.
Valcour Home, Plattsburgh, NY June 2004 – August 2004
Site Superintendent
Project Cost: $1,800,000
Managed construction of state of the art home on Lake Champlain. Coordinated materials and finishes
with the owner and architect. Directed production of employees and on-site subcontractors for
excavation, framing, HVAC, plumbing, electrical and finish work.