CB&I, Canton, MA
Oct. 2013 – present
Vogtle Unit 3 & 4 AP1000 Nuclear Power Plant
QA/QC
Reviewing incoming modules by confirming specifications, conducting visual and measurement tests, and
rejecting and returning unacceptable modules from vendors.
Book reviewing the incoming module packages by commenting and inputting data into quality database for
vendor to repair unacceptable modules.
Approving finished modules packages once unacceptable modules has been rework and has been reviewed
CB&I, Canton, MA
Jan. 2010 – Oct. 2013
Pipe Stress & Support Analyst
Analyzed and performed pipe stress by hand calculation and AutoPIPE for piping system in Annex, Radwaste,
and Diesel Building for AP1000 Nuclear Power Plant.
Analyzed and designed pipe supports and HVAC duct supports in accordance with ASME B31.1 Piping Analysis
guidelines using Support Modeler
Drafted detailed drawings using Microstation by extracting from Support Modeler.
Reviewed and inspected vendors drawing on structural, equipments, and supports.
Prepared and reviewed pipe stress and support calculations using Gt Strudl and MathCAD.
Prepared reports and resolved documentations such as Request for Information (RFI), Engineering & Design
Coordination Report (E&DCR), Design Change Proposal (DCP), and Conditional Release Notice (CRN).
Coordinated with other engineering disciplines to prevent and resolve interferences in 3D model using Intergraph
Smart Plant Review (SPR).
CB&I, Two Rivers, WI & Salem, NH
Next Era Energy Point Beach Nuclear Power Plant – Extended Power Uprate Jan. 2009 – May 2009
May 2009 – Jan. 2010
Mechanical Engineer
Supported a multitude of plant modifications including main feed water pump and heat exchanger.
Worked with conceptual design, technical write-up of design description, construction support and post-
installation package.
Provided real-time problem solving and resolution through engineering change documents.
Performed field walk-down to establish the boundaries of demolition work on the existing installation and verify
constructability of the new modified installation.
Responsibilities also included uploading and tracking down transmittal and Request for Information (RFI) by
utilizing eRoom, Passport, and SharePoint Documentum.
EDUCATION
WENTWORTH INSTITUTE OF TECHNOLOGY, Boston, MA
Bachelor of Science in Mechanical Engineer December 2010
TECHNICAL COMPETENCIES
Operating System: Windows (98/ME/XP/Vista/7)
Application: MS Office 2010 Suite, Adobe Professional, AutoCAD, AutoPIPE, CamWork, GT Strudl,
Intergraph Smart Plant Review (SPR), LabVIEW, MathCAD, MicroStation, PDS, PC-Preps,
Proto-Flo, Pelican Forge 3D Support Modeler, SolidWorks 3D, Pro/Engineer
Qualified Training: Certified in Radiation Containment Area (RCA), Fall Protection, Matrix Clearance Order Tag
Out, Confined Space, Scaffold, Personal Protective Equipment (PPE)
Language: C, SQL
1 2
Page
SECURITY CLEARANCE
Nuclear Plant Security Clearance, Point Beach Power Station – Two River, WI, 2009 Inactive, June 2009
Nuclear Plant Security Clearance, Vogtle Unit 3 & 4 – Waynesboro, GA, 2013 Active, October 2013
2 2
Page