Ilham Djamaluddin

( Makassar, ** November **** )

Kav. 19 Bumi Purabaya Indah Residence, Letkol G.A Manulang Street, West Bandung Regency, West Java Province, Indonesia 40553 Mobile Cell : +62-085*-****-**** – Email : ac933a@r.postjobfree.com Summary

Civil Engineering 18 Years and 8 Months

Structural Engineering 10 Months

( Steel Structure )

Expert 29 Months ( 2 Years and 7 Months )

Project Manager / Team

Leader

13 Months ( 1 Year and 1 Month )

Site Manager 3 Years

Construction Engineering 2 Years

Civil Superintendent 6 Months

Planning Engineering 10 Months

Estimation Engineering 3 Years

Senior Assistant 3 Years

Senior Inspector 9 Months

Supervisor Engineering 1 Year

Highlight

Structural Engineering Steel Structure for Guard House, Mosque Building, Administration Building, Garage Building, Workshop and Warehouse Building, Laboratory Building, Circulating Water Pump Building, Water Treatment Plant, Wasted Water Treatment Plant, Main Power Building ( Turbine & Boiler House ), Coal Crusher Building, Coal Shed Building and others Facilities ( 10 Months )

Expert Irrigation ( 2 Months ) and Structural Drainage / Civil ( 2 Years ) and Inventory Performance for embung ( 4 Months ) and Investigation for Position Check Dam ( 1 Month )

Project Manager / Team

Leader

Cut and Fill Work included material / soil transportation from resource placing to location by dump truck and cutting material / soil by excavator and transfer to dump truck and soil compacted by tandem roller and water Spreading by Tank Truck ( 6 Months ), Rehabilitation Feasibility Study of Lais Kuro Tidur Irrigation of North Bengkulu Regency ( 7 Months)

Site Manager Utility and Facility for Housing, Dormitory, Building, Pump House, Workshop, Generator House, Warehouse, Road ( 3 Years ) Construction Engineering Oil and Gas ( Permanent Facilities ), PLTA / Hydroelectric Middle Capacity, Housing, Workshop, Road and Facility for Road, Bridge, Proposal for Conveyor/ from site placing ( Coal terminal ) to ship for coal transportation, Drainage / V type and U type and others ( 2 Years ) Civil Superintendent Oil and Gas / Temporary and Permanent Facilities included Workshop and stone crusher plan / cut and fill work, foundation till steel structure

( 6 Months )

Planning Engineering Irrigation, Man-Powers for Civil Works, Equipment for Civil Works, activities for Civil Works and Drainage ( 10 Months ) Estimation Engineering Housing and Facilities, Road, Drainage, Workshop, Building, Cut and Fill included equipment, Equipment for Civil Works, Man-Powers for civil works ( 3 Years )

Senior Assistant Permanent Facility for DAM and DAM ( 3 Years ) Senior Inspector Building for Manufacture included Facilities, Road, Bridge, Drainage, Workshop, Housing and Facilities, Cable Trench and Construction for Manufacture water treatment ( 9 Months )

Supervisor Engineering Facilities for Telecommunication ( 1 Years ) Education

Bachelor ( S1) Civil Engineering Degree University of Christian Maranatha, Bandung City, West Java Province, Indonesia ( 1986 – 1993 )

Final Task in University One of Method of Quality Assurance Mix Asphalt Related Skill

Languages Indonesia and English

Computer MS. Word, MS. Excel, MS. Power Point, MS. Windows, AutoCAD, Primavera Project Planner ( P6 )

Skill Certificate Expert of Quality Management System ( 14-02-2018 until 14-02-2021 ) By Construction Services Development Board of Centre Sulawesi Province of Indonesia Republic

Expert of Construction Management ( 14-08-2015 until 14-08-2018 ) By Construction Services Development Board of DKI Jakarta of Indonesia Republic ( on Going Update )

Expert of Water Resources ( 22-11-2016 until 22-11-2019 ) By Construction Service Development Board of Riau Island Province of Indonesia Republic

Accomplishment

Plan project related to civil engineering work together with team until completion of the project DC-1 / CGPX Project Five Hundred Thousand Man-Hours without Injury ( Record-able Injury ) Work Experiences :

Site Engineer

Consultant PT INDRA KARYA with KSO, Indonesia

Apry 2018 – Now :

“Flood Management in Selected River Basin Sector Project”, at Ambon, Maluku Province, Indonesia

Duty and Responsible for :

Construction of check dams and small retention ponds in Way Batu Merah and Way Ruhu

River normalization in Way Batu Merah and Way Ruhu

Carry out checks for conformance of work as per design and Specification

Manage and supervise contractors in a daily basis in the role of Supervising Engineer

Prepare partial, substantial and final completion certificates

Supervise and monitor the local consultants of contractors

Supervise construction on a day-to-day basis and control and monitor quality of construction

Assist in the issuance of interim payment certificates

Examine the contractors’ claims

Examine need for contract variations and advise TL to make adjustments

Advise, guide and supervise the contractors in civil works including river dredging work that includes but not limited to utilization/transportation/dumping of dredged materials

Work closely with Geo-technical engineer and cross check every consequence of dredging and propose measures against possible negative scenarios

Provide assistance to the CPMU and PIUs in technical supervision of civil works implementation, including contract management

Irrigation Expert

Consultant PT WAINDO SPECTERRA INDONESIA, South Jakarta, DKI Jakarta Province, Indonesia January 2018 – March 2018 :

“Topographic Mapping and Aerial Photographic with LIDAR System and Bathymetry Measurement of Echo Sounding System Project”, at South Jakarta, DKI Jakarta Province, Indonesia

Duty and Responsible for :

Marking in Topographic Mapping and Aerial Photographic with LIDAR System : Primary Canal, Secondary Canal, Tertiary Canal, Drainage Channels.

Marking in Topographic Mapping and Aerial Photographic with LIDAR System : Off-Take Structure, Division Structure with Off-Take, Division Structure, Tertiary Box, Culvert, Flume Aqua Duct, Inverted Syphon, Drop Structure and others related with irrigation works.

Meeting and coordinated with the service user ( management ) and other agency related for supporting work activity, both through discussion and meeting

Created final report ( just related with irrigation works ) Team Leader for Rehabilitation Feasibility Study of Lais Kuro Tidur Irrigation of North Bengkulu Regency / Expert of Water Resources

Consultant PT Sarana Badja Bumi, Bandung, West Java Province, Indonesia January 2017 – August 2017 :

“Rehabilitation Feasibility Study of Lais Kuro Tidur Irrigation of North Bengkulu Regency” at Lais River of North Bengkulu Regency, Bengkulu Province, Indonesia

Duty and Responsible for :

Coordination with all expert and supporting persons in work implementation accordance with work reference frame, management or technique.

Preparation planning work for consultant, control work implementation accordance with planning work.

Coordinated with the service user ( management ) and other agency related for supporting work activity, both through discussion and meeting

Compose of Contract quality plan and Pra RK3K

Compose of weekly report, preliminary report, interim report and final report included control other report

Responsibility related with result work consultant and report presented

Expert of Position for Check Dam / Water Resources Consultant PT Sarana Badja Bumi, Bandung, West Java Province, Indonesia December 2016 – January 2017 :

“Position for Check Dam” at Citanduy River of Tasikmalaya Regency, Cikidang River of Tasikmalaya and Garut Regency, Ciwalen River 0f Tasikmalaya Regency, Cipali River of Ciamis Regency, Ciloseh River of Tasikmalaya Regency, Cihelang River of Tasikmalaya Regency and Cibeurem River of Tasikmalaya Regency, West Java Province, Indonesia Duty and Responsible for :

Meeting with team before investigation at site .

Investigation at site for position check dam ( Citanduy River of Tasikmalaya Regency, Cikidang River of Tasikmalaya and Garut Regency, Ciwalen River 0f Tasikmalaya Regency, Cipali River of Ciamis Regency, Ciloseh River of Tasikmalaya Regency, Cihelang River of Tasikmalaya Regency and Cibeurem River of Tasikmalaya Regency ) .

Created report for position check dam ( Citanduy River of Tasikmalaya Regency, Cikidang River of Tasikmalaya and Garut Regency, Ciwalen River 0f Tasikmalaya Regency, Cipali River of Ciamis Regency, Ciloseh River of Tasikmalaya Regency, Cihelang River of Tasikmalaya Regency and Cibeurem River of Tasikmalaya Regency ) .

Expert of Inventory Performance for Embung / Expert of Water Resources Consultant PT Sarana Bhuana Jaya, Bandung, West Java Province, Indonesia September 2016 – December 2016 :

“Inventory Performance for Embung Project” at Jeneberang Pompengang Central Office River Region, South Sulawesi Province and Office River Region of Sulawesi III, West Sulawesi Province, Indonesia Duty and Responsible for :

Meeting with Head of Operational and Maintenance of Jeneberang Pompengang Central Office River Region, South Sulawesi Province .

Meeting with Official Fetcher Commitment ( PPK ) of Operational and Maintenance 1, 2, 3, 4 and 5 of Jeneberang Pompengang Central Office River Region, South Sulawesi Province .

Visit with staff of Operational and Maintenance 2, 3, 4 and 5 of Jeneberang Pompengang Central Office River Region, South Sulawesi and staff of Operational and Maintenance 3 of Office River Region of Sulawesi III, West Sulawesi Province :

- Existing condition for embung of : Takalar, Jeneponto, Salayar, Sidenreng Rappang, Wajo, Bone, Sinjai, Bulukumba, Bantaeng, Maros, Barru, Pare-Pare, Enrekang, Tanah Toraja, Palopo, Luwu Utara and Luwu Timur Regency, South Sulawesi Province and Mamuju, Majene, Polewali Mandar Regency, West Sulawesi Province.

- Existing Dimension for embung included reservoir are : Takalar, Jeneponto, Salayar, Sidenreng Rappang, Wajo, Bone, Sinjai, Bulukumba, Bantaeng, Maros, Barru, Pare-Pare, Enrekang, Tanah Toraja, Palopo, Luwu Utara and Luwu Timur Regency, South Sulawesi Province and Mamuju, Majene, Polewali Mandar Regency, West Sulawesi Province.

Created final report and Executive Summery included sketch each embung at South Sulawesi and West Sulawesi Province .

Meeting with owner and other consultants related final report and executive summery each embung at South Sulawesi and West Sulawesi Province .

Structural Engineering ( Steel Structure )

Consultant Consortium PT Reconsult – PT Andalan RC, South Jakarta, Indonesia April 2015 – May 2016 :

“Ampana Coal Fired Steam Power Plant ( 2 x 3 ) MW Project “ at Sabo Village, Ampana Tete Sub-District, Tojo Una-Una Regency, Center Sulawesi Province, Indonesia

Duty and Responsible for :

Review and monitoring steel structure construction activities :

- Review steel structure construction activity accordance with design approval and EPC contract agreement

- Review steel structure construction method and procedure

- Follow to coordination in construction meeting

- Review steel structure planning QA / QC

- Data steel structure punch list activities

Assistance to PT. PLN UIP KIT SULMAPA in control material receiving report ( MRR ) :

- Control documents shipping for steel structure

- Control certificate material for steel structure included bolts, nut and washer

- Control dimension and hole for bolts included accessories steel structure

- Visual check welding and paint for steel structure

- Control report arrangement for material receiving report ( MRR )

Assistance to PLN UIP KIT SULMAPA to control progress of steel structure work

Assistance to PLN UIP KIT SULMAPA to construction steel structure schedule included preparation to as build drawing

Expert of Structural Engineering ( Civil )

PT. VIRAMA KARYA, Jakarta, Indonesia

May 2013 - March 2015 :

“ Technique Proposal for Consulting Construction of Regional Technique of Sumatera “ at Directorate Development of Clean Water, South Jakarta, Indonesia

Duty and Responsible for :

Preliminary

Company Profile

Feedback and suggestions

Appreciation and Innovation

Implementation Schedule

Methodological Approach and Work Program

The composition of The Teams and Assignments

Experts Assignment Schedule

“ Preliminary Design for National Brain Hospital Project and Around Hospital “ at East Jakarta, Indonesia

Duty and Responsible for :

Review design for drainage trench ( secondary and primary included main-hole, control box and other relative )

Calculation for construction cost ( estimation for construction cost )

Meeting with client ( sub-department of environmental sanitation housing, Cipta Karya Directorate and hospital leadership )

Pre-survey about site condition

“ Drainage Study of Bekasi Regency “ at Bekasi Regency, West Java Province, Indonesia

Duty and Responsible for :

Structure : drainage, water reservoir, situ, sluice, water pump and water pump housing, road, pipe concrete drainage, culvert drainage, U-ditch drainage and infiltration well

Drainage drawing : sluice, pipe concrete drainage, culvert drainage, U- ditch drainage and infiltration well

Cost estimation calculation

Soil mechanic and foundation

SOP ( Operational and Maintenance Standards )

Meeting with client ( sub-department of environmental sanitation housing, Cipta Karya Directorate and hospital leadership ) CE ( Construction Engineering )

PT. REKAYASA INDUSTRY, South Jakarta, Indonesia

May 2012 - May 2013 :

” Dayung Compression and Central Gas Plant Debottleneck Project of Conocco Phillips Gressik Ltd “ at South Sumatera Province, Indonesia Duty and Responsible for :

Construction method for permanent civil work

Meeting with client for preparation work ( permanent civil work )

Meeting with sub-ordinary/sub-contractor for preparation work

(permanent civil work)

Kick off meeting for work ( permanent civil work )

Permit to work for permanent civil work

Procedure work for permanent civil work

Job Safety Analysis ( JSA ) for permanent civil work

Control implementation for permanent civil work ( excavation, re-bar, form work, concrete till back fill )

” Bontang Coal Terminal (BoCT) Expansion ( 30 MTPA / Matrix Ton Production Air ) of Iindominco MandiriI PT “ at Bontang, East Kalimatan Province, Indonesia

Duty and Responsible for :

Construction method for civil work

Proposal for civil work

Meeting for preparation proposal

Temporary facility planning

Schedule for equipment mobilization

Schedule for direct man power

” Banyun Urip Project EPC-5 is Infrastructure Facilities ( if ) Contract Packages, of Mobil Cepu Ltd “, at Cepu Area, Bojonegoro, East Java Province, Indonesia

Duty and Responsible for :

Construction execution plan

Construction method for civil work

Requisition for civil work

Schedule for activity

Schedule for equipment mobilization

Schedule for direct man power

Civil Superintendent

PT. SEKAWAN KONTRINDO, Palembang City, South Sumatera Province, Indonesia October 2011 - March 2012 :

” Donggi Senoro LNG Project “ at Uso Sub-District, Luwuk Regency, Centre Sulawesi Province, Indonesia

Duty and Responsible for :

Duct bank work ( included excavation, re-bar, concrete form / form work, concrete till back fill )

Sleepers for support pipe and bridge pipe ( included excavation, re- bar, concrete form / form work, concrete till back fill )

V – ditch open and close drainage ( included excavation, re-bar, concrete form / form work, concrete till back fill )

U – ditch open and close drainage ( included excavation, re-bar, concrete form / form work, concrete till back fill )

Building for temporary office, training room, warehouse, generator foundation, BBM tank foundation and others

Guard basin ( included excavation, re-bar, concrete form / form work, concrete till back fill )

Fencing ( included excavation, re-bar, concrete form / form work, concrete till back fill )

Road ( sub-grade, sub-base course, base course and asphalt )

Stone crusher plan foundation ( included excavation, re-bar, concrete form / form work, concrete till back fill )

Expert of Drainage Structure ( Civil )

PT. VIRAMA KARYA, Jakarta, Indonesia

June 2011 – September 2011 :

” Drainage Study of DKI Jakarta “ at DKI Jakarta, Indonesia Duty and Responsible for :

Structure : drainage, water reservoir, situ, sluice, water pump and water pump housing, road, pipe concrete drainage, culvert drainage, U-ditch drainage and infiltration well

Drainage drawing : road, pipe concrete drainage, culvert drainage, U- ditch drainage and infiltration well

Cost estimation calculation

Soil mechanic and foundation

Site Manager ( SM )

PT. SURYA RESEARCH INTERNATIONAL, Serpong City, Tangerang Regency, Banteng Province, Indonesia

August 2010 - May 2011 :

” Sure Center Building Project “ at Serpong, Tangerang Regency, Banteng Province, Indonesia

Duty and Responsible for :

Completing the project on time with project management : Schedule

(activities, man power, material, equipment ) and s curve

Checking the implementation of the field with planning

Monitoring and Checking : daily report, progress and time schedule with s curve

Directs the implementation of the field if the executor requires explanation with drawings implementation

Provide technical support in the field

Meeting Coordination with consultant ( architecture, structure, mechanical and electrical ) and main contractor ( architecture, structure, mechanical and electrical )

Checking : drawing implementation, before and after working implementation, testing material

Checking physic progress report and payment progress Construction Engineering ( CE )

PT. KWARSA HEXAGON ( KWARSA HEXAGON GROUP ), Bandung City, West Java Province, Indonesia

August 2009 - February 2010 :

” PLTM/ Hydroelectric Middle Capacity Project “ at Henua Sub-District, Mamuju Regency, West Sulawesi Province, Indonesia

Duty and Responsible for :

Completing the project on time with project management : Schedule

(activities, man power, material, equipment ) and s curve

Checking the implementation of the field with planning

Monitoring quantity and quality and budget project implementation with budget planning included materials, equipment and man power

Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation

Provide technical support in the field

Creating daily reports, weekly and monthly

Checking physic progress report and payment progress

Meeting with client and sub-contractor

Meeting coordination with sub-contractor

Construction Engineering ( CE )

PT. STABILA ( KWARSA HEXAGON Group ), Bandung City, West Java Province, Indonesia February 2009 – August 2009 :

“ PLTM/ Hydroelectric Capacity Middle Project ” at Tentena Sub-District, Poso Regency, Centre Sulawesi Province, Indonesia

Duty and Responsible for :

Completing the project on time with project management : Schedule

(activities, man power, material, equipment ) and s curve

Checking the implementation of the field with planning

Monitoring quantity and quality and budget project implementation with budget planning included materials, equipment and man power

Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation

Provide technical support in the field

Creating daily reports, weekly and monthly

Supporting checked physic progress report and payment progress

Meeting with client and sub-contractor

Meeting coordination with sub-contractor

Senior Assistant

Nippon Koei Co., Ltd & Associates, Makassar City, South Sulawesi Province, Indonesia February 2006 - February 2009 :

“ Ponre-Ponre Dam Project ”, at Bone Regency, South Sulawesi, Indonesia Duty and Responsible for :

Monitoring quality and quantity project implementation

Checking the implementation of the field with a plan, do something with that has been planned. If not, it will be coordinated with related parties

Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation

Supporting checked physic progress report included calculation Project Manager ( PM )

PT. BLOEDUS Management Indonesia ( BOSOWA Group ), Makassar City, South Sulawesi Province, Indonesia

August 2005 – February 2006 :

“ Rappang Market Project ” at Rappang Regency, South Sulawesi Province, Indonesia

Duty and Responsible for :

Planning and cost estimates for cut and fill work such as costs of equipment excavators, dump trucks, loader, dozer and related

Checking the implementation of the field with a planning

Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators

Creating methods of operation and improve the method in accordance with field conditions if necessary

“ Section IV Toll Reformation Project “ at Makassar City, South Sulawesi Province, Indonesia

Duty and Responsible for :

Collection data

Plan and cost estimates for cut and fill work such as costs of equipment excavators, dump trucks, loader, dozer, roller compaction, water tank truck, and related

Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators

Checking the implementation of the field with a planning

Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators

Creating methods of operation and improve the method in accordance with field conditions if necessary

Assistant of JICA ( Japan International Cooperation Agency ) Expert JICA – BAPPEDA, Makassar City, South Sulawesi Province, Indonesia April 2003 - March 2005 :

“ RDPLG / Regional Development Planning for Local Governance of South Sulawesi “, at Makassar City, South Sulawesi Province, Indonesia Duty and Responsible for :

Collection data

Processing data

Share information about local / regional development to government of Sulawesi and stakeholders

Research regional / local development, such as Field practices of the best practice and the next seminar or workshop

Training to increase capacity building local government and stakeholders

Assistant of JICA ( Japan International Cooperation Agency ) Expert JICA – Bina Bangda, Makassar City, South Sulawesi Province, Indonesia April 2001 - March 2003 :

“ JICA - RDPLG / Regional Development Planning for Local Governance of Sulawesi“, at Makassar City, South Sulawesi Province, Indonesia Duty and Responsible for :

Collection data

Processing data

Share information about local / regional development to government of Sulawesi and stakeholders

Research regional / local development, such as Field practices of the best practice and the next seminar or workshop

Training to increase capacity building local government and stakeholders

Assistant of JICA ( Japan International Cooperation Agency ) Expert JICA – BAPPENAS, Makassar City, South Sulawesi Province, Indonesia March 1999 - March 2001 :

“East Indonesia Region Development Policy ”, at Makassar City, South Sulawesi Province, Indonesia

Duty and Responsible for :

Collection data

Processing data

Share information about local / regional development to government of Sulawesi and stakeholders

Research regional / local development, such as Field practices of the best practice and the next seminar or workshop

Training to increase capacity building local government and stakeholders

Supervisor Engineer

PT. SIEMENS, Ujung Pandang / Makassar City, South Sulawesi Province, Indonesia March 1997 - April 1998 :

“ East Indonesia Networking Telecommunication Project ”, at Makassar City, South Sulawesi Province, Indonesia

Duty and Responsible for :

Checking the implementation of the field with a plan included specification

Controlling implementation : main-hole and hand-hole (Houses for underground cables included its structure ), cabinet foundation

(Houses on ground cables), pole foundation, pulling primary and secondary cables house.

Controlling : installation, connecting and placing the cable in main hole, hand-hole, cabinet, pole and operation telecommunication Centre

Senior Inspector

PT. Deverindo Widya Karawang, ( TEXMACO Group ), Karawang Regency, West Java Province, Indonesia

February 1996 – October 1996 :

“ Texmaco Group Karawang Project ” at Karawang Regency, West Java Province, Indonesia

Duty and Responsible for :

Checking the implementation of the field with a plan included specification

Controlling implementation : concrete, reinforcement, steel, concrete form, residences, road, drainage, bridge, construction industry waste, foundation, and related

Controlling the concrete compressive strength testing in the laboratory field, including other materials such as sand, block paving etc

Site Manager, Officer Engineer and Site Engineer

PT. RAHMAT BHAKTIUTAMA, Jakarta, Indonesia

December 1994 - January 1996 :

Officer Engineer on “ Workshop Project “ at Ciracas Sub-District, Bogor Regency, West Java Province, Indonesia

Duty and Responsible for :

Collection data

Processing data

Planning workshop and schedule included activity

Calculating budget planning and implementation

Monitoring budget planning with implementation

Site Engineer on “ Corridor Median Project “ at Cawang Tj. Priok, DKI Jakarta, Indonesia

Duty and Responsible for :

Collection data

Processing data

Checking the implementation of the field with a plan

Calculating the budget planning and execution

Monitoring budget planning with implementation

Monitoring quantity and quality implementation

Site Manager on “ Bell-Air Mountain Resort and Residences “ at Bogor Regency, West Java Province, Indonesia

Duty and Responsible for :

Collection data

Processing data

Planning schedule, activity ( labor, material and works )

Checking the implementation of the field with a plan

Calculating the budget planning and execution

Monitoring budget planning with implementation

Monitoring quantity and quality implementation

Completing the project on time with project management

Physic progress report and payment progress

Planner

PT. Wiranta Buana Raya, Bandung City, West Java Province, Indonesia July 1994 – December 1994 :

“ South Sumatera Irrigation Project ( Work Bank Project)” at Lubuk Linggau Regency, South Sumatera Province, Indonesia Duty and Responsible for :

Detail Design of land-clearing

Design and detail of irrigation

Creating field planning and farm road

This Curriculum Vitae, I made with really.