CIVIL FOREMAN

** ***** ** ********** *n Construction (Structural, Architectural and Civil)

JOB DESCRIPTION:

Coordinates to engineer in charge regarding work schedule, plans and scope of works

Prepares and make listing of manpower, equipment’s, tools and materials to be use.

Provides and set a layout for working area.

Supervised and managed the project site construction

Supervised and managed and implement the work according to shop drawing/plans/details and specification and instruction from engineer.

Checks and ensure compliance of all personnel and activities to all safety requirements, such as the wearing of Personnel Protective Equipment (PPE), installation of site Safety tools and abiding to Safety procedures.

Provide quality of work

Makes and submit daily report.

SKILLS:

Acting Civil Supervisor

Civil Foreman

Finishing Carpenter

Steel Fabricator

Driving light vehicle

PERSONAL DATA:

Date of Birth: March 04, 1966

Gender: Male

Civil Status: Married

Height: 168 cm

Weights: 165 lbs.

Nationality: Filipino

Religion: Catholic

EMPLOYMENT RECORD:

March 10, 2018- March 31, 2019

Civil Foreman

BCOVES Builders & Development Corp.

813 Mateo st.Gatchalian Subd.

Brgy. Manuyo Dos

1745 Las Pinas City, Philippines

2 Storey Residence Project

In charge for Structural & architectural Works

Earthworks,

Fabrication and installation of Rebars

Rough and Finishing Carpentry works

Concrete Pouring /Masonry finishing works

Plumbing works and Painting works

09 of February 2016 –28 of June 2016 (5 mos.)

Civil Foreman Midtown Pools Center Venice Luxury Residence Project Mckinley Hill, Fort Bonifacio Philippines

Supervision and Preparation for Structural and Architectural lay-out according to civil cutting list/ sketches

Responsible and Preparation for Carpentry sash works, rough to finishing, Door / window jamb, flush door, panel door, all kinds of cabinets, chairs, tables & desk and installation of metal furring joist/ gypsum board for ceiling, metal stud/gypsum board for drywall

Masonry works, ChB laying, Cement plastering, concrete topping, concrete pouring for footing foundation, column and floor slab

Fabrication and installation of granite stone, ceramic tile for walling and flooring

02 June 2014 – 20 May 2015 (1 year)

Acting Building Supervisor

Bonatti SPA Branch. KSA

C02 Purification and Liquefaction Project (SABIC, JUBAIL KSA)

Supervision and Preparation for lay-out according to Civil cutting list/ sketches and fabrication, installation, dismantling of formworks

Responsible and preparation for bending and fixing of re-bar as per to cutting list schedule

Earthworks activity, excavation for footing foundation, vessel foundation, man -hole, catch-basin, and drainage sewer line, electrical cable trench and road paving

Backfilling and compaction of selected-fill material or base-course materials for

the soil improvement

Responsible for installation of anchor bolts and embedded item

shall be set accurately using templates within the tolerances specified alignment to ensure the location, projection and orientation is correct base to drawing

Responsible and preparation for concrete pouring including erection of precast

foundation and all masonry activity

Make a daily progress report

01 March 2013-31 May 2014 – (1 year 3 mos.)

Acting Building Supervisor

Bonatti SPA Branch, KSA

Seawater Revamp Project Phase 5 & 7 Gas Plant (SABIC, Jubail KSA)

Preparation for board filling to construct filling foundation

Fabrication and installation of formworks and rebar

Earthworks activity- excavation of footing foundation for pipe rack, motor pump foundation, open ditch canal and road paving

Responsible for installation of anchor bolts and embedded item

shall be set accurately using templates within the tolerances specified alignment

Responsible and preparation for concrete pouring and all masonry work

Ensures materials, manpower, tools and equipment were available as required by

the job

15 Nov. 2012- 28 Feb.2013 (1 year 3 mos.)

Civil Foreman Basic

Bonatti SPA Branch, KSA

C10 Purification Project

Jubail United Petrochemical Plant (SABIC, Jubail, KSA)

Responsible for Civil Activity

Supervision of construction for oily separation tank, fabrication and erection of

shutter frame, fabrication and fixing of reinforcement bar

Responsible and preparation for concrete pouring and all masonry works

Backfilling and compaction for soil improvement

10 June 2010-31 Oct. 2012 (1 year 4 mos.)

Wood Carpenter Foreman

Bonatti SPA Branch, KSA

Upgrading of Abu Ali Gas Plant (ARAMCO)Jubail, KSA

Responsible all Civil Activity

Supervision for excavation of manhole. RTR sewer line and fabrication of wooden

form, installation of re-bars and formworks

Responsible and preparation for concrete pouring and all masonry works

18 June 2009- 09 June 2010 (1 year)

Wood Carpenter Foreman

Bonatti SPA Branch, KSA

Motor Project-SA0203 (Aramco)

Uthmaniyah and Shedgum Gas Plant, KSA

Responsible all Civil works to construct of compressor motor foundation

Supervision of earthworks, carpentry works, re-bars fabrication and installation

Responsible and preparation for concrete pouring and all masonry works

24 August 2007- 02 Nov. 2008 (1 year 2 mos.)

Civil Work Foreman

Saudi Arabian Saipem Ltd. (SAS)

Sea Water Pipeline Project (ARAMCO)

Khurais, KSA

In-charge for civil works-fabrication and installation of shutter for anchor trust

block and steel-fixing

Excavation for pipe support foundation and main valve foundation including erection of precast foundation and perimeter fence post

Coordinate with civil supervisor on the prior inspection

Make daily accomplishment report.

22 march 2006 -22 march 2007 –(1 year )

Charge-Hand civil )

Consolidated Construction Company w.l.l.

Hawiyah NGL Recovery Plant Project (ARAMCO) KSA

In-charge for construction sub-station building. Fabrication and installation of form-works for footing foundation, column, beam, floor slab, retaining wall

Carpentry finishing works, installation for ceiling joist, gypsum panel board, steel

panel door and door jump

March 2004 - May 2005 (1 year 2 mos.)

Civil Foreman

Senbel Fine Chemicals Co., Inc.

Cotta, Lucena City, Philippines

Industrial Plant upgrading project

Supervision for construction of team maintenance building, road and canals

Carpentry formworks installation to steel structures as column, beam, and floor slab including the installation of high scaffolds

For masonry works- concreting of footing foundation and upper floor slab of

building including road paving

Finishing works like cabinets, ceiling joist, panel door, stair railing

February 2001- April 2003 (2 years 2 mos.)

Civil Work Foreman

Filjem Construction Inc.

8429 West service Road South Expressway

Parañaque City, Philippines

In charge for civil activity

Renovation and expansion for residence home

Carpentry finishing works for interior cabinet, ceiling and flash door

Concreting of ground floor slab, laying of concrete hollow block and sand plaster

22 July 1997-27 Sept. 2000 (3 yrs. & 2 mos.)

Civil Work foreman

Royal Development Corporation of the Philippines (RDCP)

3rd floor Diamond Bldg. (EDSA)

Cubao Quezon City, Philippines

Water supply and School facilities project

In-charge of the civil works, construction of school building and improvement water facilities.

Prepared necessary material for daily activity, supervised and preparation for fabrication of formworks, rebar, excavation, concrete block laying, sand plastering

and installation of roof

Fabrication and installation of reinforcement bar for intake box and reservoir tank, fabrication and installation of formwork and stripping

Make calculation the quantity of concrete volume and preparation a schedule of concrete pouring

Make daily accomplishment report

July 23, 1990- December 29, 1991 (1 year & 5 mos.)

Leadsman Carpenter

Five Star Builders and Construction Services

National Highway, Sta Cruz Cam Sur, Philippines.

Government Construction project

Construction of Municipal hall and road renovation

Carpentry formworks, fabrication and installation column, beams, and floor slab, concreting of foundation, column, walls and upper floor slab of building

I hereby certify that the above information is true and correct to the best of my knowledge