NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA

Designation

: Project Manager/Resident Engineer

Profession : Civil Engineer

Nationality : Indian

Date of Birth : 30/05/1966 – Age 51

Years of Experience : 28 years (22 years in Brunei) ( 6 years in India) Educational Qualification

Address for

Communication

: Bachelor of Engineering (Civil)

: No. 2B, Spg 282, Jalan Sg Tilong, Jalan Muara

Bandar Seri Begawan, Negara Brunei Darussalam.

Contact Number : +673*******

E-Mail : ac8d27@r.postjobfree.com

Languages Known : English, Bahasa Melayu, Tamil

Driving Status : Class 3 / International Licence

Professional Qualification

TERTIARY : Bachelor of Engineering B.E. (Civil)

Of Madurai Kamaraj University/India.

MBA of Madurai Kamaraj University/India

(Distance Learning Programme).Incomplete

Member of Canadian Council of professional

Engineers (CCPE Log # 00085707).Assessment only

Member of American Society of Civil Engineers

(ASCE # 502219)

ICE- REG NO: - 68206811

Training and Other Skills : MS Office, MS Project, Project Planner. NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 2

Summary of Experience

July 2017 to Till Date: SAMAN CORPORATION – KOREA

Position : Project Manager (Water Pipeline works)

Project Description : PROPOSED CONSTRUCTION OF PULAU MUARA BESAR BRIDGE ROAD AND UTILITIES IN BRUNEI DARUSSALAM

Project Value : BND 13,039,000.00

GENERAL

The Works associated with the water supply system shall include design (including detailed Engineering design and calculations), supply of materials, install, construct, and test and commission a complete water supply system consisting of the following:

SCOPE OF WORKS;

The Contractor shall design, execute and complete the Works in accordance with the Contract, and shall perform the Operation Service and remedy any defects in the Works.

• Offshore Bridge: 2,680m – consisting of 900m west approach bridge section, 400m main bridge section, and 1,380m east approach bridge section

• Road: 3,235m – consisting of 310m west approach road (on the Mainland at Kampung Serasa) and 2,925m east approach road at PMB Island.

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 3

• Utilities: 5.8km – Water supply system, including untreated/treated water; and Treated water supply system (200mm dia), pumping station. Untreated/raw water supply system (350mm dia) pumping station. Utilities including power, telecommunication July 2014 to May 2107 : DEPARTMENT OF WATER SERVICES MINISTRY OF DEVELOPMENT, BRUNEI DARUSSALAM.

Position : Resident Engineer

Project Description : UPGRADING WORK ON STORAGE RESERVOIR AT MENGKUBAU DAM (DESIGN AND BUILD)

Project Value : BND 12.8 Million

1) GENERAL

This is infrastructure Project for raising the existing Mengkubau Dam to increase the storage capacity of the dam, thereby increase the reservoir yield in order to meet the increasing raw water demand of Brunei Muara area.

2) SCOPE OF WORKS

The main scopes of works are listed below:

Detail design covering all aspects of dam and reservoir upgrade,Site clearance and grubbing

The probable maximum full supply level to be raised to EL 32.90m, which is 4.2m higher Than existing design

Raising the dam embankment (approximately 340m long) by 3.7m and its appurtenant Structures

Replacing the existing Ogee spillway with raised Labyrinth type and its spilling capacity is designed to be identical to the existing spillway capacity

Extending both draw-off towers to suit the new Full Supply Level (FSL) and replacing Architectural features identically

Providing a new draw-off point as surface intakes on each extended draw-off tower and Replacing all the hydro-mechanical equipment to suit the new FSL

Installing new dam instrumentation and extending the existing ones

Re-constructing the dam access road to suit the raised crest level

Extending draw-off culvert no.2 to suit the downstream slope of raised embankment NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 4

April 2010 to June 2014 : INTEGRATED ENVIRONMENTAL CONSULTANTS SDN BHD – (UNDER JKR)

DRAINAGE AND SEWERAGE DEPARTMENT

Position : Resident Engineer

Project Description : SKIM PENGURUSAN BANJIR DI DATARAN SG TUTONG / TUTONG FLOOD PLAIN MANAGEMENT (PHASE 1)

Project Value : BND 10.82 Million

1) GENERAL

This is a civil infrastructure project involving capital works to reduce flood susceptibility and damages in Tutong Floodplain. Works are based on the Drainage Works packages outlined in Sungai Tutong Floodplain Management Plan.

2) SCOPE OF WORKS

The Works involve: diversion of waterways into retention areas; construction of collector channels and concrete drains; new culverts to replace bailey bridges, and driveway crossings to ensure access along roads and into houses; gabions and other materials for embankment stabilisation. Location of the works is spread over 15km2 of the Tutong Floodplain between Layong through Lamunin, Kiudang, Kebia and Birau.

3) PROJECT COMPONENTS

Facilities proposed are generally in order of highest priority, and greatest flood reduction for the lowest cost outlay. Exact scope may be refined following topo-survey and land ownership constraints along channel and drain alignments. Location and works include:-

Matasan: Trunk Drain: 530m trunk drain, culverts replacing 2 Bailey bridges, 2,200m2 Reno mattress gabions to outlet channel and scour aprons, driveway crossings, 520m pathway and safety railings, piling for structural works.

Kiudang/Floodway: Earth channel 3700m with concrete low-flow channel, 50 no. flood retention markers, levees to form retention basin, connector drains 500m, raise local road, embankments, place 3 new triple culverts, services relocation, gabions at channel direction changes, outlet scour apron to Pengkalan Mau channel, 80m safety railing.

Beruang Channel Extension: 185m r.c. drain 7.5m wide, 375m r.c. drain 4m wide, 270m r.c. drain 2m wide, 3 no. double cell culverts, 1 no. single cell, Reno mattress/gabions to channel changes and scour aprons at outlets, 1624m pathway and safety railings, piling works.

Lamunin flood Diversion: 505m r.c. drain 7m wide, 3 no. double cell box culverts, Reno mattress/gabions at inlet and scour apron at outlet, 1010m pathway and safety railings, piling works.

Abang Flood Diversion and Retention: 17 ha clearing, 5060m earth channel 10m base width, 4920 v-notch r.c. low-flow drain to earth channel, 890m r.c. drain 8m base width, 3 no. triple cell culverts, 4610m2 Reno mattress to inlet/outlet aprons, Layong embankment, diversion structure, 350 no. gabions to channel direction change, retention basin outlet structure at tidal check valve, overflow spillway, 4650m embankment levee, 1710m pathway and safety railings, topsoil and hydro seeding to 53,860m2 channel slopes and 63,500 Type D levees, protection mat to levee water side slope, piling works for structures and drains NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 5

Road Crossings Upgrade: Demolition and removal of existing undersized road crossings to be replaced with 26 nos. new r.c. box culvert, headwalls and sumps throughout Jln. Lamunin, Rambai and Tanjong Maya

October 2006 to March 2010 : KONSULTAN MWHC (UNDER JKR) DEPARTMENT OF WATER SERVICE

Position : Senior Project Engineer

Project Description :

1) KUALA BELAIT – SERIA – SUNGAI LIANG WATER

SUPPLY STAGE 5 PHASE 1 NEW SUNGAI LIANG WATER

TREATMENT WORKS (PACKAGE 1)

Project Value: BND 68 Million

2) KUALA BELAIT – SERIA – SG LIANG WATER SUPPLY

STAGE 5 – PHASE 1, SERIA RAW WATER PUMPING

MAIN UPGRADE AND TELISAI TREATED WATER

TRANSMISSION MAIN (PACKAGE 2)

Project Value: BND 12 Million

3) KUALA BELAIT – SERIA – SUNGAI LIANG WATER

SUPPLY STAGE 5 – PHASE 1, TREATED WATER

STORAGE RESERVOIRS, ASSOCIATED PIPELINES AND

WATER MONITORING SYSTEM (PACKAGE 3)

Project Value: BND 14.5 Million

March 1997 to September 2006 : HABAT ENGINEERING COMPANY BRUNEI DARUSSALAM

Position : Project Manager

Project Description : A) Reinforcement of 11kV-network system for Pengkalan batu Lumapas & Sungai Kebun

SCOPE OF WORKS:

1) Construction of 11KV Sub Stations

2) 11KV Under Ground Cable Laying Works

3) Relocating of Existing Services

4) Cable Ducting and Reinstatement works.

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 6

B) Construction and completion of Road widening of Jalan Kebangsaan

SCOPE OF WORKS:

1) Preparation of Road Formation, Sub Base for Road and Road Base 2) Testing of Materials

3) Surface Water Drains

4) Relocating of Existing Services

5) Road Furniture’s

C) Interchange at Jalan Muara-Lebuhraya Sultan Hassanal Bolkiah Extention

SCOPE OF WORKS:

1)Preparation of Road Formation, Sub Base for Road and Road Base 2)Piling Works ( Concrete Piles, Spun Piles, Steel Piles, Sheet Piles) 2) Bridges and Retaining Wall

2)Testing of Materials

3)Surface Water Drains

4)Relocating of Existing Services

5)Road Furniture’s

D) Proposed 13 houses for National housing scheme at Kg Rimba Gadong contract H23B

SCOPE OF WORKS:

1) Construction of Type D Houses 13 Units and Infrastructure Works 2) Road Works, Sewerage, Water, Tele com works

3) Preparation of Road Formation, Sub Base for Road and Road Base 4) Piling Works ( Concrete Piles, Steel Piles)

E) Contraction of Stor Senjata Polis, Police Head Quarters Gadong

SCOPE OF WORKS:

1) Construction of Ammunition Building and Infrastructure Works 2) Piling Works ( Concrete Piles, Steel Piles)

3) Road Works, Sewerage, Water, Tele com works

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 7

August 1995 to

January 1997

HANSHIM CORPORATION (B) SDN. BHD.

BRUNEI DARUSSALAM

Position

Project Description

Project Value

:

:

:

Site Engineer

MUARA PORT EXTENSION PROJECT UNDER DEPARTMENT

OF PORTS, MINISTRY OF COMMUNICATION

CONTRACT NO: BSB/DOD/VI.22/1994

BND 70 Million

SCOPE OF WORKS:

Removal of soft soil by dredging

Reclamation of backfilling with sand

Piling for the foundation of the jetty and wharf using 600mm diameter Precast Prestressed Concrete Spun Piles

Construction of the suspended wharf structure in prestressed and reinforced concrete

Construction of seawall and sheet pile wall

Construction of 250m long Container Freight Station

Construction of Substation and Pump house

May 1989 to

July 1995

:

P.G.SIVAKUMAR & ASSOCIATES

INDIA

Position

Project Description

:

:

Site Engineer (On various construction project)

In-charge of construction of seven-storey

Building Shopping Complex (RC Frame), Four storey Housing Units

(RC Frame), Student’s hostel, etc.

Areas of Particular Expertise

COMMUNICATION : Effective liaison with government

Department Consultants and other

Professional and non-professional bodies

ADMINISTRATION : Planning, organizing, implementing of project Delegating of responsibilities

Staff management, Technical and management

problem solving, Ability to work as part of team

Logical reasoning and statistical ability

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 8

ENGINEERING : Planning, preparation of drawing and drawing Up technical specifications

Extensive experience in managing contractors and

dealing with contractual problems Extensive

knowledge in foundation and Superstructure of

building.

RESPONSIBLE FOR

Bidding and

Negotiation Duties

:

1) Assist the Project Director in bidding negotiations 2) Collect and canvas the necessary information on tools, equipment, building Materials and manpower requirements needed for the project. Quality Control

Duties

: 1)Understand the factors affecting completion time for construction project

2)Understand the factors affecting construction costs 3)Provide the expertise and advise to the site supervisors and/or subcontractors in a specific and /or all areas of construction 4) Make sure that all materials, tools, equipment’s to be used are in good order and condition.

Project Management

Duties

: 1)Planning, organizing and staffing duties

2)Undertake project management evaluation and suggest improvements 3)Meet and review project requirements, work plan and operating arrangements with Project Manager

4)Schedule and record all meetings

5) Make sure that all materials, tools, equipment’s are delivered On time.

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 9

CHARACTER

REFERENCES

: MR.GARRY ANDERSON

NZCE(Civil) M.IPENE MREAAA

Project Manager

KONSULTAN MWHC

No;190,Simpang 528,

Kg Sungai Hanching Baru,

Jalan Muara BC 2115

Negara Brunei Darussalam

Tel: 2334165/178/227 (Office)

DYG LIM SUI KAU ALICE.

Director of Water Services

Water Services Department

Public Works Department

Ministry of Development

Negara Brunei Darussalam

Tel: +673221993(Office)

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 10

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 11

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 12

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 13

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 14

NEELAKANDAN PRABAKARAN

PROJECT MANAGER (WATER WORKS) SAMAN CORPORATION – KOREA 15



Contact this candidate